ZONAL GENERAL MANAGER, M/S IRCON INTERNATIONAL LTD. versus M/S VINAY HEAVY EQUIPMENTS
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2015] 6 S.C.R. 938 A ZONAL GENERAL MANAGER, M/S IRCON INTERNATIONAL LTD. v. M/S VINAY HEAVY EQUIPMENTS B (Civil Appeal No. 4211 of 2015) MAY06, 2015 [VIKRAMAJIT SEN AND SHIVA KIRTI SINGH, JJ.] Arbitration and Conciliation Act, 1996 - s. 34 - c Arbitration award - Challenge to - Main contract between the Company S as main contractor and the appellant as successful tenderer - For execution of the same appellant entered into sub-contracts, C1 and C2 packages with the respondent-sub-contractor- Completion of67% of the work D by respondent but thereafter ceased to work- Non-payment of certain amount to respondent by appellant - Arbitration matters - In the First Arbitration, respondent made claims against appellant claiming the unpaid b~lance amount - In E the Second Arbitration, appellant made claims against the main contractor regarding pending payments pertaining to C1 and C2 packages - Award passed by the arbitrator wherein appellant liable to make payment to respondent - Appellant challenged the award by filing petitions uls. 34 - F Subsequently respondent filed applications contending that while appellant rejected its claim initially, at the same time it claimed the amount against the main contractor-Appel/ant's case that the main contract and the sub-contracts are wholly of 'back to back nature and thus, liability of the appellant G would be restricted to and co-extensive of that which main contractor acknowledges - Both the High Court dismissed the appellant's petition and allowed the respondent's applications - On appeal, held: Orders passed by the arbitrator and courts below do not call for interference - On I H facts, it cannot be said that contractor's contract with the 938 ZONAL G. M., M/S IRCON INTERNATIONAL LTD. v. M/S 939 VINAY HEAVY EQUIPMENTS appellant provided for "back to back" subcontracts whereby A main contractor would be directly answerable for the claims raised by contractors - Subletting was provided for by the main contract - However, it cannot be said that main contractor contractually (in the main agreement) assumed primary liability for the subcontractor's claims in respect of B agreements made with the appellant - Appellant conceded before the Arbitrator that it would countenance an Award in favour of the respondent as long as it was indemnified for the payment made to the respondent by an equal offsetting payment by way of an Award in its favour in its arbitration C with main contractor-Appellant was granted such an Award - Concession could be called a conditional one, however, the admission itself, taken alone, was not conditional - Appellant was bound and bonded by the legal consequences D of the initial admission made by it before the arbitrator. Oil and Natural Gas Corporation Ltd. Vs. Western Geco International Ltd. (2014) 9 SCC 263 - referred to. Case Law Reference (2014) 9 sec 263 Referred to. Para 12 CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4211 of2015. From the Judgment and Order dated 07 .12.2006 of the High Court of Judicature at Madras in OSA No. 313/ 2005. WITH Civil Appeal Nos. 4213 and 4212 of 2015. E F G Arun Khosla, Sudhir Kumar Gupta, Abhinav Gupta, Manish Gupta, R. K. Gupta, Satish Kumar for the Appellant. H 940 SUPREME COURT REPORTS [2015) 6 S.C.R. A Subramonium Prasad, AAG, C. A. Sundaram, Mohini 8 Giri, Mukesh K. Giri, 8. Balaji, Rajeev Dalal, Sudarsh Menon for the Respondent. The Judgment of the Court was delivered by VIKRAMAJIT SEN, J. 1. Leave granted. 2. The Appellant, IRCON International, is impugning the Judgment of the Learned Division Bench of the Madras High Court, which had dismissed two Original Second C Appeals preferred by the Appellant. Recapitulating the facts of this litigation, the Appellant was the successful tenderer in respect of a contract awarded to it by SIPCOT (not a party to the present dispute/ Appeal), for the construction of an D Internal Road for the Industrial Complex at lrungattukotta', Sriperumbpudur Taluk, Kanchipuram District, Tamil Nadu. The contract between these parties was made on 10. 07 .1997 and was valued at Rs.13,06,60,587/-. In furtherance of the execution of this contract, the Appellant entered into two E subcontracts (hereinafter, "the subcontracts") with the Respondent herein, in respect of two Packages, namely "C1" and "C2", for the laying of roads valued at Rs.3,20,64,752/- and Rs.1,67,01,821/- respectively. The cumulati
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex