WESTERN ELECTRICITY SUPPLY CO. OF ORISSA LTD versus M/S BABA BAIJANATH ROLLER AND FLOUR MILL P. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2014] 4 S.C.R. 121 WESTERN ELECTRICITY SUPPLY CO. OF ORISSA LTD A & ORS. v. M/S BABA BAIJANATH ROLLER AND FLOUR MILL P. LTD. (Civil Appeal No. 4023 of 2014) B MARCH 26, 2014 [GYAN SUDHA MISRA AND PINAKI CHANDRA GHOSE, JJ.) Electricity Act, 1910: s.26 - Applicability of, in case of tampering of meter- Held: s.26 is applicable only when there is any difference or a dispute in connection with correctness of a meter - In that case, upon being applied by either party, c the matter has to be decided by an Electrical Inspector and if D in the opinion of the Inspector the meter is found to be defective, the Inspector shall estimate the amount of energy supplied to the consumer or the electrical quantity contained in the supply during such time not exceeding six months - But if there is a question of fraud in tampering with the meter, in E that case there is no question of applicability of s. 26 of the Act - In the instant case, the respondent never asked or applied for checking of the meter by the Electrical Inspector on the ground of defective meter - Therefore, the ingredients of s.26(6) were not followed by the respondent to meet the F necessity of checking the meter in question in accordance with the said provision - The inspection was made in the presence of the representative of the respondent who was a Manager of the said company and in his presence the meter was checked up and was found to be tampered with - Electricity G supply company was right in raising penal charges and penal bill on the respondent on the ground of unauthorised consumption by way of tampering the metering equipment. The appellant conducted inspection at the premises 121 H 122 SUPREME COURT REPORTS [2014] 4 S.C.R. A of the respondent and noted meter tampering and accordingly raised bill imposing penal charges and issued notice of disconnection in default of payment of penal charges. The respondent did not make payment and the electricity supply was disconnected. Aggrieved, B the respondent filed a writ petition. The High Court held that the representation filed by the respondent was never considered before the imposition of penalty, far less giving an opportunity of hearing. Accordingly, the High Court held that this action of the appellant was in clear c violation of the principles of natural justice and set aside the penalty charges. The inspection report was also quashed on the ground that such inspection was never done in the presence of the authorised persons of the respondent. In these circumstances, the High Court 0 further directed the appellant to refund the amount so paid within three months. Hence the instant appeal. Allowing the appeals, the Court HELD: 1. Section 26 of the Electricity Act, 1910 is E relevant only when there is any difference or a dispute in connection with correctness of a meter. In that case the matter shall be decided, upon being applied by either party, by an Electrical Inspector and in the opinion of the Inspector if it is found that the meter is defective, the F Inspector has to estimate the amount of energy supplied to the consumer or the electrical quantity contained in the supply during such time not exceeding six months but if there is a question of fraud in tampering with the meter, in that case there is no question of applicability of Section G 26 of the said Act. In the instant case, the respondent never asked or applied for checking of the meter by the Electrical Inspector on the ground of defective meter. Therefore, the ingredients of Section 26(6) were not followed by the respondent to meet the necessity of checking the meter in question in accordance wlth the H WESTERN ELECTRICITY SUPPLY CO. OF ORISSA LTD. v. BABA BAIJANATH 123 ROLLER & FLOUR MILL P. LTD. said provision. [Para 11] [136-D-H] 2. The inspection was made in the presence of the representative of the respondent who was a Manager of the said company and in his presence the meter was checked up and was found to be tampered with. The plea A B c of duress or coercion in signing the inspection report was raised by the respondent but in reality no allegation was made by the respondent before an appropriate authority excepting such bald allegations were made before the writ court without any basis or pvidence. Therefore that fact has no bearing in deciding this matter. The said fact cannot be ignored while dealing with the matter concerning tampering
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex