WEST INTERNATIONAL CITY PVT LTD versus DEVASIS RUDRA
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 1070 SUPREME COURT REPORTS [2019] 2 S.C.R. KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA (Civil Appeal No. 3182 of 2019) MARCH 25, 2019 [DR. DHANANJAYA Y CHANDRACHUD AND HEMANT GUPTA, JJ.] Consumer Protection Act, 1986: Housing β Failure to deliver possession β Buyer having claimed compensation from the developer, entitled to seek refund amount or estopped from doing so β On facts, in terms of the buyerβs agreement, developer was to handover possession to the buyer by the stipulated date with a grace period of further six months β However, failure of developer to deliver the possession of houses β Complaint by the buyer seeking possession of houses and in alternate for refund of the amount paid to developer with 12% interest p.a. and compensation of Rs.20 lakhs β Order by the State Commission directing the developer to refund the amount with 12% interest p.a. and compensation of Rs 5 lakhs β However, compensation amount reduced to Rs. 2 lakhs by the National Commission β On appeal, held: In the buyerβs agreement, for default on the part of the buyer, the buyer liable to pay interest at the rate of 18% p.a., however, for default on the part of the developer, the developer liable to pay interest only at the savings bank rate prescribed by the SBI β Agreement being one sided, would not preclude the right and remedy available to the buyer to claim reasonable interest or compensation β Buyer can be expected to wait for possession for a reasonable period β It would be unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession β Completion certificate was received nearly seven years after the extended date for the handing over of possession which was not at all reasonable β Thus, the orders passed by the forum below for refund justified β Rate of interest payable by the developer to the buyer modified to 9% p.a. instead of 12% p.a. β Interest. [2019] 2 S.C.R. 1070 1070 A B C D E F G H 1071 Disposing of the appeal, the Court HELD: 1.1 Under the Agreement clause, any delay beyond 30 June 2009 would result in the developer being required to pay interest at the prevailing savings bank interest of the State Bank of India. Interestingly, where the buyer is in default, the agreement stipulates that interest at the rate of 18 per cent from the date of default until the date of payment would be charged for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one sided. The clause will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation. [Para 10][1074-A-D] 1.2 In terms of the Buyerβs agreement, the date for handing over possession was 31 December 2008, with a grace period of six months. Even in 2011, when the buyer filed a consumer complaint, he was ready and willing to accept possession. It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. [Para 11][1074-E-G] 1.3 In the circumstances, the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified. Having regard to all the facts and circumstances of the case, the order of the NCDRC is modified by directing that the appellant would pay interest at the rate of 9% per annum to the respondent instead and in place of 12% as directed by the NCDRC. [Para 12, 13][1075-A] CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3182 of 2019. From the Judgment and Order dated 21.11.2016 of the National Consumer Disputes Redressal Commission, New Delhi in First Appeal No. 958 of 2016. KOLKATA WEST INTERNATIONAL CITY PVT LTD v. DEVASIS RUDRA A B C D E F G H 1072 SUPREME COURT REPORTS [2019] 2 S.C.R. Ra
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex