WELSPUN SPECIALTY SOLUTIONS LIMITED (FORMERLY KNOWN AS REMI METALS GUJARAT LTD. versus OIL AND NATURAL GAS CORPORATION LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 120 SUPREME COURT REPORTS [2021] 11 S.C.R. WELSPUN SPECIALTY SOLUTIONS LIMITED (FORMERLY KNOWN AS REMI METALS GUJARAT LTD.) v. OIL AND NATURAL GAS CORPORATION LTD. (Civil Appeal Nos. 2826-2827 of 2016) NOVEMBER 13, 2021 [N. V. RAMANA, CJI AND SURYA KANT, JJ.] Arbitration and Conciliation Act, 1996: ss. 37 and 34 – Appealable orders – Arbitral award – Sustainability of, under section 37 – On facts, execution of contract wherein appellant was to supply pipes to the respondent-ONGC – During execution of contract, certain delays in meeting the obligations as required under the contract – Deduction of certain amount by respondent as liquidated damages from various bills submitted by the supplier – Dispute before the arbitral tribunal – Arbitral tribunal proceeded to determine the actual damages, holding that the liquidated damages could not be granted as there was no breach of contract since time was not essence of contract – Interference with – Held: It has to be culled out from the reading of the entire contract as well as the surrounding circumstances whether time is essence of the contract – Merely having an explicit clause may not be sufficient to make time the essence of the contract – As the contract was spread over a long tenure, the intention of the parties to provide for extensions surely reinforces the fact that timely performance was necessary – Fact that such extensions were granted indicates respondent’s effort to uphold the integrity of the contract instead of repudiating the same – Thus, award cannot be interfered since the arbitral tribunal’s interpretation of contractual clauses having extension procedure and imposition of liquidated damages, are good indicators that ‘time was not the essence of the contract – Arbitral tribunal’s view to impose damages accrued on actual loss basis could be sustained in view of the waiver of liquidated damages and absence of precise language which allows for reimposition of liquidated damages – High Court and District Court strayed beyond the limitation u/s. 34 and 37 – Order of the High Court as well as the District Court is set aside – Award of the arbitral tribunal is upheld – Contract Act, 1872 - ss. 55 and 74. [2021] 11 S.C.R. 120 120 A B C D E F G H 121 Allowing CA Nos. 2826-2827 of 2016 and disposing of CA Nos. 6834 of 2021, the Court HELD: 1.1 The main challenge to the award is against the imposition of unliquidated damages, when the matter of fact stood that the contract between parties stipulated for pre-estimated damages (liquidated damages). The concerned contract contained provisions for liquidated damages for breach of contract, particularly breach of deadlines set in the contract. Under Contract law, such liquidated damages are recognized, subject to the same being reasonable. [Para 26][136-B-D] 1.2 Time not being the essence of the contract’, as determined by the Arbitral Tribunal, was beyond reproach. Reliance on the contractual conditions and conduct of parties to conclude that existence of extension clause dilutes time being the essence of the contract, was in accordance with rules of contractual interpretation. The award concludes that as time was not the essence, liquidated damages could not be granted. [Para 27, 28][136-F-G] 1.3 In order to consider the relevancy of time conditioned obligations, some basic principles are that subject to the nature of contract, general rule is that promisor is bound to complete the obligation by the date for completion stated in the contract. That is subject to the exception that the promisee is not entitled to liquidated damages, if by his act or omissions he has prevented the promisor from completing the work by the completion date. These general principles may be amended by the express terms of the contract as stipulated in this case. [Para 29][137-A-D] 1.4 It is now settled that ‘whether time is of the essence in a contract’, has to be culled out from the reading of the entire contract as well as the surrounding circumstances. Merely having an explicit clause may not be sufficient to make time the essence of the contract. As the contract was spread over a long tenure, the intention of the parties to provide for extensions surely reinforces the fact that timely performance was necessary. The fact that such extensions were granted indicates ONGC’s effort WELSPUN SPECIALTY SOLUTIONS LTD. (FORMERLY KNOWN AS REMI METALS GUJARAT LTD.) v. ONGC A B C D E F G H 122 SUPREME COURT REPORTS [2021] 11 S.C.R. to
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex