VOLTAS LTD. versus ROLTA INDIA LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2014] 2 S.C.R. 797 VOLTAS LTD. V. ROLTA INDIA LTD. (Civil Appeal No. 2073 of 2014) FEBRUARY 14, 2014 [ANIL R. DAVE AND DIPAK MISRA, JJ.) ARBITRATION AND CONCILIATION ACT, 1996: ss.21, 43 - Counter claim - Limitation period - Held: Limitation period A 8 for filing counter claim should be computed as on the date of C service of notice of such claim on the claimant and not on the date of final counter claim - Exception to the said rule is if a party. against whom a claim is made in arbitration can satisfy that he had previously made a claim against the claimant and sought arbitration by serving a notice to the D claimant - However, limitation cannot be saved solely on the ground that a party had previously in a notice vaguely stated that it would be claiming liquidated damages. JUDGMENT/ORDER: Binding effect of - Held: A , judgment is not to be read as a statute but to understand the coffect ratio stated in the case it is necessary to appreciate the repetitive use of the words. E The appellant and the respondent entered into a civil construction contract for construction of buildings. F Dispute arose between them and on 03.12.2004, the respondent terminated the contract. By letter dated 29.03.2006, the appellant invoked the arbitration clause. On 17.04.2006, the respondent denied any amount being payable by them and called upon the appellant to pay G Rs.68.63 crores. The appellant filed an application for appointment of arbitrator and a sole arbitrator was appointed by the High Court. Before the arbitrator, the appellant filed its statement of claim on 13.04.2011 797 H 798 SUPREME COURT REPORTS [2014] 2 S.C.R. A claiming Rs. 23.31 crores. The respondent filed statement of defence and counter claim of Rs.333.73 crores on 24.08.2011. The Arbitrator passed interim order that the limitation for making a counter claim is required to be asserted with reference to the date on which the cause B of action arose and the date on which counter claim was filed. The respondent filed an application under Section 34 of Arbitration Act for setting aside decision of Arbitrator. The Single Judge of the High court rejected the section 34 application holding that when the notice was c given by the appellant on 29.03.2006, the said notice was only in respect of the disputes having arisen between the parties due to refusal of claims made by the respondent. On the date of issuance of such notice, the respondent had not even asserted its claim and after issuance of 0 notice dated 29.03.2006, the respondent by its letter dated 17.04.2006 had asserted its claim for the first time and, therefore, counter claim was beyond the period of limitation. On appeal, the Division Bench of the High Court set aside the order of the Single Judge. Hence the E instant appeal. Partly allowing the appeal, the Court HELD: 1.1. By letter dated 01.03.2005, the appellant, while referring to the letter dated 03.12.2004 issued by the F respondent terminating the contract on the ground of alleged delay and default in completion of the project, without prejudice had made a request for payment of final bill in full and settle the claim made therein at the earliest. It was also suggested therein that if the respondent G needed any additional information or material in support of the claim put forth, the appellant would furnish the same. On 18.03.2005, the respondent communicated to the appellant that it would compute its losses, damages, costs, charges, expenses, etc. after the building work was over and claim the same from the appellant. The appellant H VOLTAS LTD. v. ROLTA INDIA LTD. 799 by letter dated 7.4.2005 intimated the respondent that it A was not liable to pay any alleged losses, damages, costs, charges and expenses, allegedly suffered by the respondent. On 27 .04.2005 by another communication an assertion was made about the losses suffered by the respondent. The respondent asseverated that it was not B liable to pay to the appellant any compensation and damages or other amounts as claimed in the letter dated 01.0~.2005. In fact, the respondent was compelled to terminate the contract as per the recommendation of the architects and the respondent had suffered huge losses c and damages and had incurred heavy costs, charges and expenses for which the appellant was solely responsible. It was also mentioned in the letter that the respondent reserved its right to take appro
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex