LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

VENKATESH CONSTRUCTION COMPNAY versus KARNATAKA VIDYUTH KARKHANE LIMITED (KAVIKA)

Citation: [2016] 1 S.C.R. 511 · Decided: 20-01-2016 · Supreme Court of India · Bench: T.S. THAKUR · Disposal: Appeal(s) allowed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2016] 1S.C.R.511 
VENKATESH CONSTRUCTION COMPNAY 
A 
v. 
KARNATAKA VIDYUTH KARKHANE LIMITED (KAVIKA) 
(Civil Appeal Nos.461-462 OF 2016) 
JANUARY 20, 2016 
[T.S. THAKUR, CJI., A.K. SIKRI AND R. BANUMATHI, JJ.) 
Contract - Execution of Work Contract - Suit by contractor 
making a claim for Rs. 30 lakhs for the work already completed, 
for extra work, stocking of materials etc. - Trial Court decreed the 
suit and directed the defendant to pay Rs. 3,23,0001- to the plaintiff 
with 12% per annum interest - Cross appeals - High Court set 
aside the decree - On appeal, held: Findings of trial court need not 
be interfered with by the appellaie court unless they are erroneous 
or reached ignoring the evidence on record - bi the present case 
findings of trial court and the amount awarded was based -on 
evidence and material on record - The High Court, without 
considering oral or documentary evidence erroneously interfered 
with the factual findings of trial court - In view of the facts of the 
case, rate of interest is reduced to 6% per annum. 
Allowing the appeal, the Court 
HELD: 1. .The Appellate Court may uot interfore with the 
finding of the trial court unless the finding recorded by the trial 
court is erroneous or the trial court ignored the evidence on 
record. The amount awarded by the trial court under various 
heads was based on evidence and material on record. The High 
Court reversed the decree passed by the trial court without 
discussing oral and documentary evidence and several grounds 
raised before the trial court. The High Court veered away from 
themainissueandwenton to.elaborate on the law ofarbitration 
and the mode of setting aside the arbitral award under Section 
34 of the Arbitration Act, which was n'ilf warranted. The High 
Court erred in interfering with the factual findings recorded by 
the trial court. [Paras 15 and 16) [519-B-D) 
2. The defendant has not adduced any evidence to 
discredit the testimony of PWs l and 3 that extra work was 
511 
B 
c 
D 
E 
F 
G 
H 
512 
A 
B 
c 
D 
E 
F 
G 
H 
SUPREME COURT REPORTS 
[2016] I S.C.R. 
required to be done on account of seepage of water and soil 
caving in and widening and deepening the trench. In so far as 
the direction of the respondent to stop the work is concerned, 
on appreciation of evidence, trial court rightly held that the 
respondent asked the appellant to stop the running work for 
want of revised design. So far as the claim of the appellant that it 
suffered loss due to loss of stock of material, PWs 1 and 3 have 
stated that they have stocked the Β·material of worth about 
rupees six lakhs at the work site. Even though the appellant 
has claimed rupees six lakhs on account of loss of the material 
stocked, as the appellant had not produced any bill relating to 
purchase of material nor produced authentic trip sheet, the 
trial court rightly awarded rupees one lakh only on account of 
loss of building material. (Paras 11, 12, 13 and 15([517-B-C, H; 
518-F-H; 519-A] 
3. The High Court took note of clause 11 of the 
contract which states that the contractor is not authorized to 
do any extra work or make any alteration without the previous 
consent in writing of the respondent. The respondent has not 
raised the plea relying upon clause 11 of the contract. Further, 
by perusal of Ex.P2 dated 20.12.1991, a letter addressed by the 
appellant to the respondent informing the respondent about the 
extra work which needs to be done and the fact that PW-4 was 
engaged hy the respondent to prepare the new design for the 
work, it is evident that the respondent was aware of the fact of 
the change in the nature of work and that there is alteration in 
the work done by the appellant. When the evidence and material 
clearly depict the change of nature of work involved and when 
the extra work to be done was also admitted by DW-1, parties 
cannot be expected to go for a revised agreement/contract, 
and specially when the work was to be completed within a specified 
time-frame. The High Court was not right in placing reliance 
upon clause 11 of the contract to reverse the findings of fact 
recorded by the trial court. [Para 14] [518-A-J<'] 
4. In the facts and circumstances of the case and having 
regard to the fact that the matter is pending for over two decades 
and in the interest of justice, it is appropriate that the interest 
of 12% per annum awarded by the trial court is reduced to 6% 
per annum. [Para 17] [519-F] 
VENKATESH CONSTRUCTION COMP

Excerpt shown. Read the full judgment & AI analysis in Lexace.