V. R. SUBRAMANYAM versus B. THAYAPPA AND OTHERS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
I I 3 S.C.R. SUPREME COURT REPORTS V. R. SUBRAMANYAM v. B. THAYAPPA AND OTHERS. (J. L. KAPUR and J. C. SHAH, JJ.) 663 B11ilding contract-Defective work-Addition•! work not covered by agreement-Compensation, when can be allowed-Indian Contract Act, I872 (9 of I872), s. 70. The appellant entered into an agreement with the respondent who was a building contractor entrusting him with the work of constructing a house and shops. The respondent undertook the work but before it could be completed disputes arose between them and the appellant claimed compensation for effecting repairs to rectify defective work done by the respondent, and the respondent claimed compensation at certain rates set up by him for work for which there was no express provision in the written agreement. Suits based on their respective claims were filed by the appellant and the respondent which were partly .decreed by the trial court. The High Court dismissed the appellant's suit in its entirety and remanded the respondent's suit directing the appointment of a qualified engineer for determining, according to the directions given in the judgment, the amount payable to the respondent for work done in addition to the agreed work under the contract. The appellant contended that the respondent having failed to prove the oral agreement pleaded the respondents' suit should have been dismissed and compensation quantum meruit which was not claimed should not have been awarded. Held, that if a party to a contract rendered service to the other not intending to do so gratuitously and, the other party had obtained some benefit, the former was entitled to compensa- tion for the value of the services rendered by him. The respondent not intending to do gratuitous work was entitled to compensation for additional work not covered by the written agreement. Even if the respondent failed to prove his claim for compen- sation at the prevailing market rate under an oral agreement the court had jurisdiction to award compensation for work done under s. 70 of the Contract Act. The appellant's suit having been dismissed by the High Court and no appeal having been preferred against it, it was not open to him to reagitate the same question of compensation in the companion suits in which no equitable set-off was claimed. CIVIL APPELLATE JURISDICTION: Civil Appeals Nos. 321 and 322 of 1956. Appeals by special leave from the judgment and decree dated September 21, 1951, of the Mysore High Court in Regular Appeals Nos. 3, 24, 13 and 25 of 1948- 49; arising out of the judgment and decree dated 8~ February 1. Subramanyarn v. Thayappa Shah ]. 664 SUPREME COURT REPORTS [1961] January 9, 1948, of the Principal District Judge, Bangalore, in Original Suits X os. 55 of 1946-4 7 and 117of1945-46 respectively. S. K. Venkataranga Aiyangar and S. K. Aiyangar, for the appellant. B. K. B. Naidu., for the respondents. 1961. February 1. The Judgment of the Court was delivered by SHAH, J.-V. R. Subramanyam, the appellant herein is the owner of plot No. 29, Subedar Chattram Road in the town of Bangalore. B. Thayappa respondent is a building contractor. Tho appellant entrusted the respondent with the work of constructing a house and shops on the plot, on terms and conditions set out in a written agreement dated October 1, 1942, which was slightly modified on October 6, 1942. By the agree- ment the respondent WftS to construct for the itppellant on the plot six shops ft butting a public roa.d, the main building ftt the rear of the shops, an out-house and a garage according to a site plan. Thll respondent was to be remunerftled at rftte.q specified in the agreement: for constructions with R. C. C. roofing, -the ra.te stipulated was Rs. 4-2-0 per square foot anrl for" tiled construction " it was Rs. 3-2-0 per square f1JoL The :Municipality of Bangalore did nnt sanction the plan as proposed by the appellant·.. The plan was altered and it was sanctioned, subject to LLosc alterations. By the alterations the shops were deleted from the plan, the area of the out-house was increased, anrl a puja room on the grnund floor and a,n extrn room on the first floor were arlr],,d to the plan. A compound wall was also to be constructed. The respondent carrird out a subRtantial part of the construction work accord- ing to plan anrl the appellant paid to him diverse sums of money and delivered building materials. The aggregate H.
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex