UTTAR HARYANA BIJLI VITRAN NIGAM LTD. & ANR versus ADANI POWER (MUNDRA) LIMITED & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 468 SUPREME COURT REPORTS [2023] 5 S.C.R. [2023] 5 S.C.R. 468 468 UTTAR HARYANA BIJLI VITRAN NIGAM LTD. & ANR. v. ADANI POWER (MUNDRA) LIMITED & ORS. Civil Appeal No. 4143 of 2020 APRIL 20, 2023 [B. R. GAVAI AND VIKRAM NATH, JJ.] Electricity Act, 2013 : s. 63 β Determination of tariff by bidding process β Change in law β Haryana Utilities-appellants entered into Power Purchase Agreements-PPAs with the APML β PPAs entered pursuant to tariff based Competitive Bidding Process β Petition by APML before CERC seeking relief of increase in tariff on account of change in law, increase in coal price due to change in Indonesian Regulations β CERC allowed the petition granting change in law relief for the shortfall in the availability of 100% coal which was upheld by the APTEL β On appeal, held: No document on record that representation was given by APML that its bid is based on 70% domestic and 30% imported coal β APML entitled to benefit on account of the Change in Law if there was any shortfall of 70% of the domestic coal as was decided to be allotted by the SLC (LT) β No error with the concurrent findings that APML entitled to Change in Law relief for 100% of the contracted capacity, which is 70% of the installed capacity of the Project β As regards, the methodology for computation of Change in Law compensation laid down in GMR Kamalanga Energy Ltd.βs case, Haryana Utilities are indulging into approbation and reprobation β After accepting before the CERC that they would adopt the methodology as given in the case of GMR Kamalanga Energy Limitedβs case, it would not be appropriate on the part of the appellants-instrumentalities of the State, to change its stand after final orders are passed by the CERC β Thus, the concurrent findings of facts by two expert bodies does not call for interference. Dismissing the appeal, the Court HELD: 1.1 None of the documents placed on record would reveal that a representation was given by AP(M)L that its bid is based on 70% domestic and 30% imported coal. It could thus be seen that what has been stated in the Executive Summary by A B C D E F G H 469 AP(M)L is that its Power Plant had a strategic advantage inasmuch as it had proximity to Mundra Port. It further states that Mundra Port possesses World Class Coal handling facilities with 17 meter deep draft permitting capsize vessels to berth alongside. By the said document, it has proposed to supply 1425 MW to Haryana Power Generation Corporation Limited (HPGCL) from 1980 MW (3 x 660 MW) Phase IV extension of Mundra Project. The representation given is that it would use either imported or indigenous coal. [Paras 29, 30][479-B-C; D-F] 1.2 It could thus be seen that AP(M)L would be entitled to benefit on account of the Change in Law if there was any shortfall of 70% of the domestic coal as was decided to be allotted by the SLC (LT) in its meeting dated 12th November 2008, culminating in the Ministry of Coal - MOC issuing a LoA dated 25th June 2009 and the Fuel Supply Agreement - FSA being signed by AP(M)L with CIL on 9 th June 2012. [Para 34][480-B-D] 1.3 The claim of AP(M)L is with regard to shortfall in the assured quantity of 70%, and not above that. From the order passed by the APTEL, it is clear that it has been the consistent stand of the appellants that AP(M)L was in a position to generate and supply contracted capacity of 1424 MW out of the fuel linkage arising out of the FSA dated 9th June 2012 with Mahanadi Coal Field Limited. It has been its stand that AP(M)L should use the entire domestic coal availability towards the contracted capacity of the appellants first, and then use the imported coal for the deficit to reach the targeted PLF. It has further been its stand that the entire domestic coal available should be accounted towards 1424 MW contracted to Haryana Utilities. [Paras 35 and 36][480-D-F] 1.4 The entire domestic coal linkage came to be utilized for supplying power to Haryana Utilities, it is unjust on the part of Haryana Utilities to say that 70% of the installed capacity should be further bifurcated and the Change in Law benefit should be restricted only to 70% of the installed capacity which was allotted by the SLC (LT). [Para 40]P481-C-D] UTTAR HARYANA BIJLI VITRAN NIGAM LTD. v. S ADANI POWER (MUNDRA) LIMITED A B C D E F G H 470 SUPREME COURT REPORTS [2023] 5 S.C.R. 1.5 Even according to Haryana Utilities, the entire coal covered under FSA was required to be utilized for generating power to be supplied to i
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex