UNION OF INDIA versus M/S V. PUNDARIKAKSHUDU AND SONS AND ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B c UNION OF INDIA v. MIS V. PUNDARIKAKSHUDU AND SONS AND ANR. SEPTEMBER 9, 2003 [V.N. KHARE, CJ. AND S.B. SINHA, J.] Arbitration Act, 1940-Sections JO-Misconduct-Meaning of-One part of the award inconsistent with the other part of the award-Held, amounts to legal misconduct-Award can be set aside. Arbitration Act, 1940-Sections JO-Award-Setting aside of-Non application of mind by the arbitrator-Effect of-Arbitrator holding that a party is responsible for delay in execution of the contract-Still awarding award in favour of the defaulting party-Non-application of mind by the D arbitrator-Award can be set aside. Arbitration Act, 1940-Sections JO-Award-Challenge to--Arbitrator awarding claims of both parties holding that there was breach of contract by both-One party not challenging the award in favour of another-Held, the party must be held to have accepted the finding that it committed a E breach of contract-Finding attains finality-Acts as res judicata-Words and Phrases-Res Judicata. The appellant entered into an agreement with the first respondent for construction of an auditorium. The time for completion of the F contract was extended from time to time and ultimately, the appellant terminated the contract under clause 54 of the agreement. The said clause empowered the appellant to rancel the contract, ifthe contractor failed to complete the work within stipulated date for completion and clear the site on or before the date of completion. As disputes and differences arose between the parties, the parties referred the matter G for arbitration in terms of the agreement. Both the appellant as well as the first respondent raised claims before the arbitrator. The arbitrator made an award for Rs. 14,31,463 in favour of the first respondent upon arriving at a finding that the appellant was responsible for causing delay in completion of the contract. At the same H time, the arbitrator also awarded Rs. 33,95,000 to the appellant. 506 U.0.1. v. V. PUNDARIKAKSHUDU AND SONS 507 The first respondent filed petitions under Section 15, 16, 30 and 32 A of the Arbitration Act praying for modification/setting aside of the award in favour of the appellant and for judgment and decree in terms of the award made in favour of the first respondent. The appellant, on the other hand, filed a petition for judgment and decree in terms of the award made in favour of the appellant. B The District Judge upheld the objections of the first respondent holding that as the award of the arbitrator in favour of the first respondent was made upon arriving at a finding that the appellant was responsible for causing delay in completion of the contract, the award made in favour of the appellant was inconsistent with the said finding and could not have been granted. The District Judge also confirmed the C award of the arbitrator made in favour of the first respondent. The appellant filed appeals against the order of the District Judge, which were dismissed by the High Court. Thereafter, the appellant filed the present appeals. The appellant had earlier filed special leave petitions against the judgment and order of the High Court in respect of the order of the District Judge whereby the District Judge had confirmed the award made in favour of the first respondent. The said special leave petitions were dismissed by his Court. Dismissiug the appeals, the Court D E HELD: 1.1. If one part of the award is inconsistent with the other and furthermore if in determining the disputes between the parties the arbitrator failed to take into consideration the relevant facts or based F his decision on irrelevant factors not germane therefor; the arbitrator must be held to have committed a legal misconduct. The award suffering from non-application of mind by the arbitrator is liable to be set aside. ยท (516-8, 517-H] Bharat Coking Coal Ltd. v. Mis Annapurna Construction, (2003) 7 G Scale 20; KP. Poulose v. State of Kera/a, (1975) 2 SCC 236; Union of India v. Jain Associates and Another, (1994) 4 SCC 665 and Dandasi Sahu v. State of Orissa, (1990) 1 SCC 214, relied upon. 1.2. The question as to whetheroneparty or the other was responsible for delay in causing completion of the contract job squarely fell for H 508 SUPREME COURT REPORTS (2003] SUPP. 3 S.C.R. A consideration before the arbitrator. The arbitrator could not have arrived at a finding that both committed breaches of the terms of contrac
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex