UNION OF INDIA versus M/S. CONCRETE PRODUCTS & CONST. CO. ETC.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2014] 3 S.C.R. 535 UNION OF INDIA v. MIS. CONCRETE PRODUCTS & CONST. CO. ETC. (Civil Appeal Nos. 2950-2951 of 2014) MARCH 3, 2014 [SURINDER SINGH NIJJAR AND FAKKIR MOHAMED IBRAHIM KALIFULLA, JJ.] A B Arbitration and Conciliation Act, 1996: s.37(1) - Interest C for the amount withheld by the railway administration - Grant of - Held: Arbitrator passed an award directing the railway administration to refund the amount along with interest and subsequent interest @ 18% PA. - Arbitrator in awarding interest to the contractors failed to take into ac.count the D provisions contained in Indian Railways Standard Conditions of Contract which disentitled the contractors from claiming any interest or damages for withholding or retention under lien by railway administration - Also, as per s.37(1), the arbitrator could not have awarded any interest from the date when the E recovery was made till the award was made - Interest would have been payable from the date when the award was made till the money was deposited in the court - Upon the amount being deposited, no further interest could be paid to the contractors - Interest. F . The appellant-Railway administration and the contractor-respondents entered into contract for supply of concrete sleepers. By letter dated 12 July 1997, appellant-Railway administration informed the respondents that the excess payments had been made G to the respondents and, therefore, certain amount was recoverable from the respondents and that said amount would be recovered from sum due or payable from 535 H 536 SUPREME COURT REPORTS (2014] 3 S C.R A running contract. This gave rise to dispute which was referred to arbitrator. The arbitrator passed an award directing the appellant to refund the amount along with interest and subsequent interest @ 18% PA. The respondents filed an application seeking direction to the B appellant to pay amount awarded from the amount deposited by the appellant with the High Court along with the accrued interest as on date on the said amount. The application was allowed. The appellant filed intra court appeals challenging the order of the single judge c principally on the ground that the appellant was not liable to pay any interest for the period subsequent to the deposit of the principal amount into the court. The Division Bench of the High Court dismissed the appeal holding that appellant had not questioned the power of 0 the sole arbitrator to award interest; that the said issue was also not raised before the single judge and a pie.a was raised for the first time before the Division Bench that the award of interest was contrary to Clause No. 2401 of the Indian Railways Standard Conditions of Contract. E The question which arose for consideration in the F instant appeals was whether the contractors are entitled to interest for the amount withheld. Allowing the appeals, the Court HELD: 1.1. Clause 2401 provides that the railways shall be entitled to withhold and also have a lien to retain any amount deposited as security by the contractor to satisfy any claims arising out of or in the contract. In such circumstances, the railways can withhold the amount G deposited by the contractors as security and also have lien over the same pending finalization or adjudication of the claim. In case, the security deposit is insufficient to cover the claim of the railways, it is entitled to withhold and have lien to the extent of the amount claimed from H any sum payable for any works done by the contractor UNION OF INDIA v. MIS. CONCRETE PRODUCTS & 537 CONST. CO. ETC. thereafter under the same contract or any other contract. A This withholding of the money and the exercise of the lien is pending finalization or adjudication of any claim. This clause further provided that the amount withheld by the railways over which it is exercising lien will not entitle the contractor to claim any interest or damages for such B withholding or retention under lien by the railways. [Para 15) [548-D-G] 1.2. Clause 2403 provides that any sum of money due and payable to the contractor under the contract may be C withheld or retained by way of lien by the railway authorities or the Government in respect of payment of a sum of money arising out of or under any other cont~act made by the contractor with the railway authority or the Government. Clause 2403(b) further provides that it is an agreed term of the c
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex