UNION OF INDIA & ORS. versus TANTIA CONSTRUCTION PVT. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2011] 5 S.C.R. 397 UNION OF INDIA & ORS. v. TANTIA CONSTRUCTION PVT. LTD. (Special Leave Petition (C) No.18914 of 2010) APRIL 18, 2011 [ALTAMAS KABIR AND CYRIAC JosePH, JJ.] CONTRACT: A Tender - Risk and Cost Tender - Construction of Rail c Over-Bridge - Tender of respondent-company accepted and agreement entered into between the parties - Changes in design thereafter whereby Viaduct had to be extended involving additional cost - Respondent-company declining to take up the construction work of extended Viaduct which wa:? 0 not covered in agreement and for which a separate tender was floated - Railways directing the Company to carry out the complete work including the additional work - Held: The work relating to construction of Rail Over-bridge a~er the revised design consisted of two parts, one which the respondent- E company was executing ahd the other to be executed by a different contractor - Respondent-company has satisfactorily explained its position regarding its offer being confined only to the balance work of the original tender and not to the extended work- To proceed on the basis that the respondent- company was willing to undertake the entire work at the old F rates was an error of judgment and the termination of, the contract in relation to original Tender on the basis of $Bid supposition was unjustified and was rightly set aside by the Single Judge of the High Court,ยท which order was affirmed by the Division Bench. G CONSTITUTION OF IND/A, 1950: Articles 226 and 32 - Writ petition - Maintainability of in 397 H 398 SUPREME COURT REPORTS [2011] 5 S.C.R. A view of the plea of alternative remedy -Held : An alternative remedy is not an absolute bar to the invocation of the writ jurisdiction of the High Court or the Supreme Court - Constitutional powers vested in the High Court or the Supreme Court cannot be fettered by any alternative remedy- Injustice, B whenever and wherever it takes place, has to be struck down as an anathema to the rule of law and the provisions of the Constitution - The Court endorses the view of the High Court that notwithstanding the provisions relating to the Arbitration Clause contained in the agreement, it was fully within its c competence to entertain and dispose of the writ petition filed on behalf of the respondentccompany - Contract - Alternative remedy. The East Central Railways, on 12-12-2006, invited tenders by Risk and Cost Tender No. 76 of 06-07 for the D work of construction of a Rail Over-Bridge. The tender of the respondent-company was accepted at a cost of Rs. 19,11,02,221.84p. and an agreement dated 30-4-2007 was entered into between the parties in respect of the contract work. On account of some of the procedural E work, including the change of the span of the bridge, change in the design of the peir cap, the requirement of shifting obstacles and also due to heavy rains, the construction of wall was delayed. The delay in preparation of the designs and drawings which involved F the work of a specialized agency also contributed to the delay. On account of changes in the design whereby the Viaduct had to be extended involving an additional cost of Rs. 36.11 crores, petitioner No. 6 requested the respondent-company to convey its consent for execution G of the complete work including the revised work. By letter dated 13.2.2008, the respondent- company apprised petitioner No. 6 of its inablility to take up the construction work of the extended Viaduct which was not covered in the Agreement dated 30.4.2007. Thereupon, the Railways H floated a separate Tender No. 189 of 2008 for the UNION OF INDIA & ORS. v. TANTIA CONSTRUCTION 399 PVT. LTD. additional work of extended portion of the Viaduct for the A Road Over-Bridge. The approximate cost earmarked for the said work was raised from Rs. 24.50 crores to Rs.26,35,96,878.63p. Two tenderes from two different companies for Rs. 34, 11, 16,279.39p. and Rs. 35,89,93,215.66p. were submitted. While the tender B process for the extended contract on the Viaduct was going on, the respondent-company wrote to petitioner No. 6 on 12.4.2008, agreeing to execute the varied contract at the same rate, terms and conditions of the contract agreement, but on condition that the price increase due C to Price Variation Clause, would be payable to the company. The petitioners by their letter dated 15.6.2008 called upon the respondent-company to execute the
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex