U.P. POWER CORPORATION LTD. versus N.T.P.C. LTD. & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2013] 9 S.C.R. 805 U.P. POWER CORPORATION LTD. v. N.T.P.C. LTD. & ORS. (Civil Appeal No. 4117 of 2006) SEPTEMBER 18, 2013 [T.S. THAKUR AND VIKRAMAJIT SEN, JJ.] CENTRAL ELECTRICITY REGULA TORY COMMISSION (TERMS AND CONDITIONS FOR DETERMINATION OF TARIFF) REGULATIONS, 2001: Regulation 2.5 read with Regulation 1.9 - Taking over of Thermal Power Station - Excess expenditure - Fixation of tariff - Relevant period being 1.4.2001 to 31.3.2004 - Held: Basis A B c for fixation of tariff has to be the "actual capital expenditure" D incurred on the completion of the project -- But where the actual expenditure exceeds the approved expenditure, the excess so incurred can be taken into consideration to the extent the same is allowed by Central Electricity Authority or an appropriate independent agency nominated for the E purpose - This implies that the excess expenditure must go through a process of scrutiny either by CEA or the independent agency before it can constitute an input for determination of tariff - Scrutiny of the excess would in tum primarily involve examination of two distinct aspects: (a) Whether the excess expenditure has been actually incurred F or is a make believe or an exaggeration by the generating company; and (b) Whether the expenditure was capital in nature - In the instant case, CERC had on a prudent check disallowed a substantial part of the excess that was claimed by respondent-NTPC and the claim allowed had been G conceded by appellant-Corporation to have been actually spent by respondent for completion of project. Regulation 2.5 - Fixation of tariff - Reference to CEA or 805 H 806 SUPREME COURT REPORTS [2013] 9 S.C.R. A independent agency - Held: In the instant case, prayer for additional capitalisation was made by respondent-Corporation and considered by CERC after Electricity Act 2003 had come into force, repealing the earlier enactments - The new legislation did not set out any role for CEA, in the matter of B approval of schemes for generating companies or the capital expenditure for the completion of such projects - CERC was, therefore, right in holding that Central Electricity Authority had no part to play in the matter of approval for purposes of capitalisation of the extra expenditure incurred on a project - C However, on facts, since the issue of actual expenditure had been concluded by the admission of appellant, and in the absence of any question relating to the nature of the expenditure, the absence of a reference to CEA cannot be said to have caused any miscarriage of justice for the 0 appellant or vitiated the tariff fixation by the CERC. ELECTRICITY ACT, 2003: s. 70 ands. 73 read with s. 61 proviso, and Regulation 2.5 of Regulations of 2001 - Fixation of tariff - Capital expenditure E - Excess expenditure - Determination - Reference to CEA - Held: The far reaching changes that came about in the legal framework with the enactment of the 2003 Act, made Regulation 2.5 redundant in so far as the same envisaged a reference to CEA or an Independent Agency for approval of F the additional capitalisation - Insistence on a reference, to CEA for such approval, despite the sea change in the legal framework would have been both unnecessary as well as opposed to the spirit of new law that reduced the role of CEA to what has been specified in s. 73. G The respondent-National Thermal Power Corporation (NTPC) took over the Thermal Power Station in question from the erstwhile U.P. State Electricity Board on 13.02.1992, on an approved project cost of Rs.927 .85 crores. On a petition filed by NTPC for approval of tariff H for the tariff period 01.04.2001 to 31.03.2004 in respect of U.P. POWER CORPORATION LTD. v. N.T.P.C. LTD. & 807 ORS. the generating plant in question, the Central Electricity A Regulatory Commission (CERC) by an Order dated 24.10.2003 approved the tariff taking into consideration the capital cost at Rs.940.70 crores as on 01.04.2001 but did not consider the additional capitalisation claimed by the respondent since the same was based only on an estimated capital expenditure and was unsupported by 8 an auditor's certificate. The respondent-NTPC then moved a petition before the CERC seeking approval of the revised fixed charges in respect of the generating plant for the relevant tariff period taking into account the c additional capital expenditure incurred during the said period which w
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex