TRUSTEES OF THE PORT OF MADRAS versus ENGINEERING CONSTRUCTIONS CORPORATION LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A TRUSTEES OF THE PORT OF MADRAS v. ENGINEERING CONSTRUCTIONS CORPORATION LIMITED AUGUST 14, 1995 B [S.C. AGRAWAL AND B.P. JEEVAN REDDY, JJ.] Arbitration Act, 194(}-S ections 16( 1) C, 30( C rReasoned award- Error apparent on the face of the award-Held, means "e1mr of law" and not "error of fact''-Error must have appeared from the award-Or from document C incorporated or appended to it.Β· D E F Contract Act, 1872-Section 46-Explanation-Question of reasonable time-Wliere no period is presC1ibed for executing a contract-Held, is a question off act and not a question of law. Practice and Procedure-Letters Patent Appeal-Interference in Award-On question of fact-Not acceptable. The Board of Trustees of Madras Port Trust invited tenders for certain work at the port in 1957, for which the Respondent submitted its tender specifying the entitlment to certain deviations with regard the period for completion of work and for importing plant and machinary for executing the work compensation on account of delay and also that requi- site foreign exchange was to be made available by the Board. The Board refused to agree to any change iq the draft agreement and an agreemet was entered into by the respondent without incorporating the modifications suggested by the Respondent. Since there were delays in importing the requisite machinery the contract was completed in the extended period asked to respondent and granted by the board. After the completion of contract the Respondent raised a dispute claiming additional amount on account of delay in supplying the machinery and other heads. The respon- G dent invoking the arbitration clause in the agreement, nominated a retired Judge as the arbitrator and the Board nominated another retired judge as their nominee. Since the arbitrators could not agree among themselves, the;y designated an Umpire. The Umpire inter alia found that there was no undertaking by the H Board to supply to the respondent the imported machinery within a period 672 - TRUSTEES PORT OF MADRAS v. ENGG. CONST. CORPN. LTD. 673 of six months from the acceptance of the tender, that the Board was not A responsible for the dealy and that the contractor was not entitled to payment of any compensation. The umpire further held that in case the respondent was found entitled to any compensation, a sum of Rs. 5 lakhs would represent a fair compensation for the delay in the supply of im- ported machinery and another one lakh for delay on other grounds. B The appellant filed a petition for making the award as rule of court and the respondent filed a petition for setting aside the award on two grounds viz., misconduct and error apparent on the face of the award. The Single Judge of Madras High Court made the Β·award a rule of court, over ruling the objections raised by the respondent. On Appeal the Division C Bench inter alia held that the claim of the respondent did not arise from the contract but only from other correspondence, that Section 46 of the Contract Act, 1872, would govern the situation since there was no time stipulated in the contract, that the undertaking given by the Board was an implied undertaking and the Board was under a bounden duty to have supplied the machinery within a reasonable time, and that the failure of D the Board to supply the machinery was a breach of implied promise. The Division Bench set aside the judgment of the Single Judge and remanded the matter to the Umpire for a fresh consideration. In the appeals against the judgment of the Divisin Bench of the High Court, it was contended by the respondent that the dela;r. on the part of the Board in importing the machinery has caused loss for which the Board was bound to compensate. The Appellants denied that they undertook an obligation to import machinery within a particular period, that the period of six months was only a rough estimate or an expectation, that the extra payment of nine percent of the contract price agreed upon by the Board and the contractor was not only intended to cover delays caused due to suspension of work, failure to supply in time primary material and services etc. but also the delays, if any, caused in supplying the imported machinery and spares. Allowing the Appeals, this Court HELD : 1. The concept of error aparent on the face of the award is an en"Or of law apparent on the face of the award and not an error of fact. The error of law can be discovered from the
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex