LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

THE TATA POWER COMPANY LIMITED TRANSMISSION versus MAHARASHTRA ELECTRICITY REGULATORY COMMISSION AND ORS.

Citation: [2022] 19 S.C.R. 620 · Decided: 23-11-2022 · Supreme Court of India · Bench: D.Y. CHANDRACHUD · Disposal: Dismissed

Cited by 2 judgment(s) · cites 6 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A
B
C
D
E
F
G
H
620
SUPREME COURT REPORTS
[2022] 19 S.C.R.
   [2022] 19 S.C.R. 620
620
THE TATA POWER COMPANY LIMITED TRANSMISSION
v.
MAHARASHTRA ELECTRICITY REGULATORY
COMMISSION AND ORS.
(Civil Appeal No. 1933 of 2022)
NOVEMBER 23, 2022
[DR. DHANANJAYA Y CHANDRACHUD, CJI,
A. S. BOPANNA AND J. B. PARDIWALA, JJ.]
Electricity Act, 2003 – ss.61-63, 86, 125, 181 – Maharashtra
Electricity Regulatory Commission (MERC) issued an order granting
Adani Electricity Mumbai Infra Limited (AEMIL) the transmission
licence to develop the Aarey-Kudus transmission project based on
High Voltage Direct Current (HVDC) technology where tariff was
to be determined through the Regulated Tariff Mechanism (RTM)
approach u/s.62 – Order challenged by appellant before Appellate
Tribunal for Electricity (APTEL) – Appeal dismissed by APTEL –
Held: Provisions of the Electricity Act 2003 do not prescribe one
dominant method to determine tariff – ss.62 and 63 stipulate the
modalities of tariff determination – The non-obstante clause in s.63
cannot be interpreted to mean that s.63 would take precedence over
s.62 at the stage of choosing the modality to determine tariff – The
criteria or guidelines for the determination of the modality of tariff
determination ought to be notified by the Appropriate State
Commission either through regulations u/s. 181 of the Act or
guidelines u/s. 61 of the Act – In the present case, MERC has neither
framed regulations nor notified guidelines prescribing the criteria
or guidelines for choosing the modalities to determine tariff – Thus,
MERC shall determine the tariff by exercising its general regulatory
powers u/s. 86(1)(a) of the Act – MERC while exercising its general
regulatory powers u/s.86(1)(a) shall be guided by the National Tariff
Policy 2016, which shall be a material consideration – Further,
MERC and APTEL have arrived at concurrent findings that the
1000MW HVDC Aarey-Kudus project is an β€˜existing project’ for
the purpose of the applicability of the GoM’s GR 2019 – Supreme
Court deciding a statutory appeal u/s.125 of the Act cannot interfere
with the concurrent findings on a question of fact – Nonetheless,
even on an independent assessment of the facts, the HVDC project
A
B
C
D
E
F
G
H
621
is an existing project – The Electricity Act, 2003 or the policy
framework did not make it binding upon MERC to allot the HVDC
project only through the Tariff Based Competitive Bidding (TBCB)
route – Therefore, the Regulatory Commission’s decision to grant
the HVDC project u/s. 62 was within a reasonable exercise of its
powers.
Electricity Act, 2003 – ss.61, 181 – Framing of necessary
regulations by Regulatory Commissions to put into effect the
principles prescribed under the Act – All State Regulatory
Commissions directed to frame Regulations u/s.181 of the Act on
the terms and conditions for determination of tariff – Appropriate
Commission shall be guided by the principles prescribed in s.61,
which also includes the National Electricity Policy (NEP) and
National Tariff Policy (NTP) – The Commissions while being guided
by the principles contained in sec.61 shall effectuate a balance
that would create a sustainable model of electricity regulation in
the States – The Regulatory Commission shall curate to the specific
needs of the State while framing these regulations – Further, the
regulations framed must be in consonance with the objective of the
Electricity Act 2003, which is to enhance the investment of private
stakeholders in the electricity regulatory sector so as to create a
sustainable and effective system of tariff determination that is cost
efficient so that such benefits percolate to the end consumers.
Dismissing the appeal, the Court
HELD: 1. The Appropriate Commission is not mandated
to adopt the tariff determined through the bidding process
irrespective of the fulfilment of the statutory requirements. The
Commission can reject the tariff determined through the bid if
the tariff process is not (i) transparent; and (ii) in accordance
with the guidelines issued by the Central Government. Thus, if
the Commission does not adopt the tariff determined through
bidding, and if the decision is challenged, the bidding process
can be reviewed substantively (on the ground of transparency)
and procedurally (on the ground of compliance with Central
Government guidelines) to determine if the Commission could
have exercised its discretion to determine the tariff under Section
62 while rejecting the tariff determined under Sectio

Excerpt shown. Read the full judgment & AI analysis in Lexace.