LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

THE MADRAS ALUMINIUM CO. LTD. versus THE TAMIL NADU ELECTRICITY BOARD AND ANR.

Citation: [2023] 10 S.C.R. 742 · Decided: 06-07-2023 · Supreme Court of India · Bench: BHUSHAN RAMKRISHNA GAVAI · Disposal: Appeal(s) allowed

cites 4 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A
B
C
D
E
F
G
H
742
SUPREME COURT REPORTS
[2023] 10 S.C.R.
THE MADRAS ALUMINIUM CO. LTD.
v.
THE TAMIL NADU ELECTRICITY BOARD AND ANR.
(Civil Appeal Nos. 7224-7226 of 2009)
JULY 06, 2023
[B. R. GAVAI, SANJAY KAROL AND
ARAVIND KUMAR, JJ.]
Contract – State, a party to the contract must abide by Article
14 – Reasonable period to consider an application – Application
made by the appellant for reduction to 10000 Kilovolt-Ampere (KVA)
– No steps effectuating such request were taken despite repeated
follow ups by the appellant – Action of the respondents in taking
considerable time from when the said application was made, to when
the revised agreement was entered into, if arbitrary and
unreasonable – Held: Yes – State action irrespective of being in the
contractual realm must abide by Article 14 – Appellant was
unjustifiably asked to furnish costs for unutilized electricity which
should not have extended beyond six months (considering
β€˜reasonable period’ to consider an application, to be so), for a
period much larger thereto, rendering such action unreasonable
and arbitrary – On facts, it is not open for the respondents to contend
that the petitioner is not liable for the refund of the amount deposited
under protest towards the bills so generated taking the maximum
load to be 23000 KVA – Particularly, when at no point in time, the
appellant neither sought for nor consumed the electricity more than
the maximum demand of 10000 KVA – Acknowledging the financial
health of the appellant, in the 1999 agreement, the respondent ought
to have taken a decision on the appellant request with a reasonable
dispatch and terms which ought to have been within a period latest
by six months and not two and a half years as was eventually done
– Judgment passed by High Court set aside – Respondent to return
the amount paid by the appellant for 13000 KVA, in excess to its
request of maximum sanctioned demand of 10000 KVA – Constitution
of India – Article 14 – Doctrines/Principles – Sick Industrial
Companies Act, 1985 – s.3(1)(O).
Doctrines/Principles – Principle of reasonable time –
Discussed – Contract.
[2023] 10 S.C.R. 742 : 2023 INSC 607
742
A
B
C
D
E
F
G
H
743
Allowing the appeals, the Court
HELD: 1.1 It is a matter of record that a fresh agreement
with the reduced maximum demand of 10000 KVA was entered
into between the parties in July, 2004. Undisputedly, such fresh
agreement was inked more than two and a half years after the
application was made on 24th December, 2001. The Appellant in
pursuance of the reduction of maximum demand made its
application and followed up repeatedly with the authorities. Save
and except two letters on behalf of the Board one, acknowledging
the said application and stating that same has been put up before
the authorities for consideration: and two, rejecting the date of
such reduction being effectuated and listing down certain
conditions upon which the same would be granted, no other
communication on part of the board forms the record. [Paras 23,
26][752-H; 753-A, E]
1.2 No reason whatsoever is forthcoming as to why this
particular application required such a vast length of time to be
acted upon. In the mean while the Appellant has been faced with
the threat of disconnection, and has had to pay, due to such
inaction, large amounts of money for electricity which it has not
utilized. It is true that the agreement states that the consumer,
(Appellant herein) is bound to pay such maximum demand amount
irrespective of utilization and also that such an agreement will be
in effect for a period of five years but in the considered view of
this Court, the Board cannot be allowed to take refuge of these
clauses while the company on the other side is saddled with heavy
cost in the interregnum of such decision. More so in view of the
communication dated 11th August 1994. [Paras 27 and 28][753-
F-H]
1.3 The Writ Court had observed that in the other instances
cited by the Appellant herein, the reduction sought was a small
amount of KVA as opposed to the 13000 KVA reduction sought
vide the instant application. While that may be true, it does not
supply reason to the act of keeping an application pending for
such a long period of time. [Para 29][754-A-B]
1.4 State action irrespective of being in the contractual realm
must abide by Article 14, and that a) after passage of a considerable
THE MADRAS ALUMINIUM CO. LTD. v. THE TAMIL NADU
ELECTRICITY BOARD AND ANR.
A
B
C
D
E
F
G
H
744
SUPREME COURT REPORTS
[2023] 10 S.C.R.
period of ti

Excerpt shown. Read the full judgment & AI analysis in Lexace.