THE HP POWER TRANSMISSION CORPORATION LTD. versus M/S BRUA HYDROWATT PVT. LTD. & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2025] 5 S.C.R. 1360 : 2025 INSC 680 The HP Power Transmission Corporation Ltd. v. M/s Brua Hydrowatt Pvt. Ltd. & Ors. (Civil Appeal No. 3919 of 2023) 14 May 2025 [Abhay S. Oka and Augustine George Masih,* JJ.] Issue for Consideration Whether the Appellate Tribunal for Electricity was correct in reversing the Order passed by Himachal Pradesh Electricity Regulatory Commission thereby exonerating respondent from bearing the entire construction cost for the Bay. Headnotes† Doctrine of Privity – Whether the appellant can recover dues and other charges despite being a stranger to the internal tripartite agreement (ITA) dated 27.12.2019 among the respondents: Held: The respondents executed an ITA wherein they agreed to pool in the power to be generated from their respective generative stations at Bay and the entire cost of the terminal, including metering arrangements, were to be shared between them in proportion to their individual generating capacities – Separately, the appellant executed a Connection Agreement with only respondent no. 1, wherein respondent no. 1 acted as lead partner of the consortium of the respondents, had the liability to pay for cost of construction, additional charges, and O&M Charges to the appellant in relation to the Bay – Respondent no. 1 was to ensure the payment to be made to the appellant and thereafter seek reimbursement in case of non- payment of the amount by the other generating companies within the time stipulated – Respondent no. 3 defaulted in its payment, the appellant raised a demand from the respondent no. 1 citing sole liability of the said respondent as per Connection Agreement dated 02.07.2021 – Since the appellant was not a party to the ITA which was executed by and between the respondent no. 1, 2 and 3, thus appellant could not have and cannot claim proportionate shares as per the installed capacity of the project from Respondent No. 02 and Respondent No. 03 – The right, to claim and seek recovery of the liability from Respondent No. 02 and Respondent No. 03 would be * Author [2025] 5 S.C.R. 1361 The HP Power Transmission Corporation Ltd. v. M/s Brua Hydrowatt Pvt. Ltd. & Ors. only with respondent no. 1 as per the ITA – Appellant is not privy to the ITA executed among the respondents, therefore does not have any right to claim for dues or liabilities from respondent no. 2 & 3 – As ITA does form part and parcel of the Connection Agreement executed between appellant and respondent no. 1, the exact wording only binds respondent no. 1 for the payment of concerned cost and charges – APTEL’s judgment is based upon wrong assumptions and misreading of the terms of agreement thereby ignoring the basic principle that a party not privity to the agreement or contract cannot be, unless the context otherwise makes it apparent, made liable for any term(s) and condition(s) unrelated to it. Case Law Cited Essar Oil Limited v. Hindustan Shipyard Limited and Others [2015] 6 SCR 924 : (2015) 10 SCC 642 – relied on. Jamna Das v. Pandit Ram Autar Pande and Others, 1911 SCC OnLine PC 35 – relied on. Tweddle v. Atkinson (1861) 121 ER 762 – relied on. List of Acts Electricity Act, 2003; The Himachal Pradesh Electricity Regulatory Commission (Conduct of Business) Regulations, 2005. List of Keywords Doctrine of Privity; Connection Agreement; Transmission Licence; Hydro Electric Process; Stranger to an agreement cannot enforce. Case Arising From CIVIL APPELLATE JURISDICTION: Civil Appeal No. 3919 of 2023 From the Judgment and Order dated 17.03.2023 of the Appellate Tribunal for Electricity at New Delhi at AN No. 30 of 2023 Appearances for Parties Advs. for the Appellant: Anand K. Ganesan, Nikunj Dayal, Pramod Dayal, Amal Nair, Ms. Shivani Verma. Advs. for the Respondents: Tarun Johri, Ankur Gupta, Vishwajeet Tyagi. 1362 [2025] 5 S.C.R. Supreme Court Reports Judgment / Order of the Supreme Court Judgment Augustine George Masih, J. 1. This Civil Appeal assails the Judgment dated 17.03.2023 in Appeal No. 30 of 2023 (“Impugned Judgment”) by the Appellate Tribunal for Electricity at New Delhi (“APTEL”) which reversed the findings returned vide Order dated 27.12.2022, by Himachal Pradesh Electricity Regulatory Commission at Shimla (State Commission) in Petition No. 35 of 2022, holding M/s Brua Hydrowatt Pvt. Ltd., Respondent No.01 herein (“BHP Ltd”) liable to bear the entire cost for Bay at the 66kV Switching Station at Urni (“Bay”), which was constructed
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex