TEHRI HYDRO DEV. CORPN. LTD.& ANR. versus JAI PRAKASH ASSO. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2012] 8 S.C.R. 813 TEHRI HYDRO DEV. CORPN. LTD.& ANR. A v. JAi PRAKASH ASSO. LTD. (Civil Appeal No. 3682 of 2007) SEPTEMBER 25, 2012 [R.M. LODHA, ANIL R. DAVE AND RANJAN GOGOi, JJ.] B Arbitration - Maintainability - Contract for execution of works contained an arbitration clause - Grievance of C respondent-contractor that though the works had been completed, tile final bill was not prepared - Arbitration proceedings initiated, in course of which, final bill prepared and placed before the arbitrators by the appellant-corporation - Subsequently, another process of arbitration initiated for the D specific claims of respondent-contractor - Maintainability of the second round of arbitration proceedings - Held: The entitlement of respondent-contractor was not the subject matter of the earlier proceedings before the arbitrators - The claim of respondent-contractor got crystallized once the final E bill was prepared and placed before the arbitrators - It is these specific claims, after quantification, that were referred to the arbitrators in the subsequent arbitration proceedings - Thus, it cannot be said that the arbitration proceeding in respect of the specific claims of respondent-contractor stood barred in F view of the earlier arbitration proceedings between the parties. Arbitration - Arbitral award - Challenge to - Power of the Court - Contract for execution of works - Disputes arising therefrom - Matter referred to arbitration in terms of the arbitration clause contained in the contract - Claim of G respondent-contractor for refund of security deposit not adjudicated upon by the arbitrators on the ground that it was not arbitrable - Held: In such a situation, it was clearly beyond the power of the trial court to decree the claim - The High 813 H 814 SUPREME COURT REPORTS [2012] 8 S.C.R. A Court was justified in setting aside the claim, however, it erred in directing adjudication of the claim by an arbitrator nominated by it - The issue should have been left for determination in accordance with the procedure agreed upon B by the patties. Arbitration - Arbitral award - Grant of interest pendente lite - Justification - Held: Not justified, in view of the express bar contained in the contract between the patties. Arbitration - Arbitral award - Grant of interest for the past- e award period - Justification - Held: Justified. The appellants and the respondent-contractor had entered into a contract for execution of certain works in connection with the Tehri Hydro Dam Project. Though the 0 works in question were completed, the final bill of respondent-contractor was not prepared and security money, furnished by way of bank guarantee was not released. The parties went to arbitration in accordance with the arbitration clause under the contract/agreement. E In course of the arbitration proceedings, the appellant- Corporation submitted the final bill. Subsequently, another arbi.tration proceeding commenced between the parties for the specific claims of respondent-contractor. The arbitral award passed in F the aforesaid arbitration proceeding held the respondent- contractor entitled to Rs.10.17 lakhs on account of the work done with interest @ 6% p.a. from the date of invocation of the claim till the date of the award and @ 12% p.a. from the date of the award till payment or till the G award was made Rule of court, whichever was earlier. H Insofar as the claim of respondent-contractor of Rs.12.50 lakhs lying in deposit with the appellant-Corporation, the Arbitrators held the same to be beyond the scope of the dispute raised in the arbitration proceeding. TEHRI HYDRO DEV. CORPN. LTD.& ANR. v. JAi 815 PRAKASH ASSO. LTD. Objections against specific parts of the award by A which the respective parties felt aggrieved were filed before the District Judge. The District Judge (trial court) held the respondent-contractor entitled to both the amounts- Rs.10.17 lakhs as also Rs.12.50 lakhs and thereafter passed a decree in respect of the two amounts B alongwith interest thereon at the rate of 12% pendente lite and 6% for the post award period. In appeal, the High Court maintained the award of Rs.10.17 lakhs, however, as regards the claim of Rs.12.50 lakhs, it took the view that the said amount could not have been awarded by the c trial court as the said entitlement was not gone into by the Arbitrators, and remanded such claim to be settled by an Ar
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex