LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

TAMIL NADU WATER SUPPLY & DRAINAGE BOARD versus M/S. SATYANARAYANA BROTHERS PVT. LTD.

Citation: [2007] 2 S.C.R. 347 · Decided: 07-02-2007 · Supreme Court of India · Bench: AR. LAKSHMANAN · Disposal: Dismissed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

TAMIL NADU WATER SUPPLY & DRAINAGE BOARD 
A 
v. 
MIS. SA TY ANARA Y ANA BROTHERS PVT. LTD. 
FEBRUARY 7, 2007 
[DR. AR. LAKSHMANAN AND AL TAMAS KABIR, JJ.] 
B 
:x 
Constitution of India, 1950-Article 136-Drinking water project 
formulated by State Government-Delay in execution of-Disputes-Appellant 
not raising any substantial question of law that needs to be considered by c 
Supreme Court-Questions raised are only question of fact-Matter was fully 
heard in the earlier round by Supreme Court whereupon matter was remitted 
to High Court-Well-considered judgment rendered by High Court on 
remission does not call for any interference. 
Certain disputes arose between Respondent-contractor and Appellant- D 
Board over delay in execution of drinking water project formulated by State 
~ 
Government. Arbitral proceedings were initiated in which both the parties 
~ 
appointed an arbitrator each who in turn appointed an Umpire. Umpire passed 
an arbitral award which was set aside by the Single Judge of High Court. 
Division Bench however passed decree in terms of the award passed by the 
E 
Umpire. Respondent filed SLP before the Supreme Court which remitted the 
matter to Division Bench ofthe High Court. On remission, the Division Bench 
held in favour of the Respondent holding that it had not committed any breach 
of contract. Hence the present appeal. 
.... 
Dismissing the appeals, the Court 
F 
HELD: The appellant is still proceeding under a false premise that the 
contractor is solely responsible for the delay in the execution of the work 
and the breach of contract which have been conclusively found against the 
appellant by the Single Judge as well as the Division Bench of the High Court 
while setting aside the award passed by the Umpire in the present case. The G 
appellant has not raised any substantial question of law that needs to be 
.). i, 
considered by this Court. The questions raised are only questions of fact and 
in view of the concurrent findings by both the Single Judge and the Division 
Bench, no interference by this Court is called for particularly when a matter 
347 
H 
348 
SUPREME COURT REPORTS (2007) 2 S.C.R. 
A was fully heard in the earlier round by the Supreme Court. The matter was 
remitted to the Division Bench of the High Court by this Court only after 
considering all aspects and the questions involved in the case. Now, it has 
been conclusively found that the respondent-contractor was not responsible 
for any breach of contract. The High Court, has decided the matter strictly in 
accordance with the remand order made by this Court. The High Court also 
B has not entered into any finding regarding the respective claims of the parties 
but set aside the award of the Umpire only on the ground oflegal malafidcs. 
The well-considered judgment rendered by the High Court on remission from 
this Court does not call for any interference. [Paras 13 to 15) 
[352-D-E, G; 353-A] 
":Y 
c 
D 
E 
F 
G 
H 
Sathyanarayana Brothers (P) Ltd., v. T.N. Water Supply & Drainage 
Board, [2004) 5 SCC 314, referred to. 
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 2880-2881 of 
2005. 
From the Final Judgment and Order dated ยท24.3.2004 of the High Court 
of Judicature at Madras in O.S.A. Nos. 248/1989 and 59 of 1993. 
Mohan Parasaran, A.S.G., Senthil Jagadeesan and Rakesh K. Shanna for 
the Appellant. 
Dipankar P. Gupta, T.L. Viswanatha Iyer, P.S. Nair, Indira Nair, Krishnan 
Nandakumar and T.G. Narayanan Nair for the Respondent. 
The Judgment of the Court was delivered by 
DR. AR. LAKSHMANAN, J. I. Heard Mr. Mohan Parasaran, learned 
Additional Solicitor General for the appellant and Mr. Dipanker P. Gupta and 
Mr. T. L. V. Iyer, learned senior counsel for the respondent. 
2. Aggrieved against the order passed by the Division Bench of the 
High Court of Madras dt.24.03.2004 in OSA Nos. 248of1989 and 59 of 1993, 
the above two appeals were filed. 
3. The case on hand has a chequered history. 
lbe Government of Tamil Nadu fonnulated a scheme known as "Veeranam 
Project" to provide drinking water to the city of Chennai and thereby overcome 
the problem of acute water scarcity in the city of Chennai. In order to 
implement the aforesaid scheme, the Government invited tenders for 
~ 
โ€ข 
... 
~ 
' 
A 
~-
TAMIL NADU WATER SUPPLY & DRAINAGE BOARD 1ยท. SA nยท ANARAYANA BROTHERS PVT.LTD. jLAKSHMANAN. J.J 349 
manufacturing, supplying and delivering 1676 mm pre-stressed concrete pipes A 
-...... .,~ 
and fittings including transp

Excerpt shown. Read the full judgment & AI analysis in Lexace.