SUSHIL KUMAR AGARWAL versus MEENAKSHI SADHU & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 756 SUPREME COURT REPORTS [2018] 12 S.C.R. SUSHIL KUMAR AGARWAL v. MEENAKSHI SADHU & ORS. (Civil Appeal No. 1129 of 2012) OCTOBER 09, 2018 [A. M. KHANWILKAR AND DR. D. Y. CHANDRACHUD, JJ.] Specific Relief Act, 1963 β s.14(3)(c)(i) and (ii) β Specific performance of contract under β Appellant-developer and predecessor-in-interest of the respondents entered into a development agreement for construction of a building on the land of the respondents β Respondent denied execution of the agreement β Appellant filed for specific performance of the contract against the respondent β Held: The appellant-developer need to satisfy the two conditions laid out in sub clause (i) and (ii) of s.14(3)(c), for the suit for specific performance to be maintainable against the owner β The clauses 8, 13, 20 and 22 of the agreement had not clearly brought out, the exact extent of work to be carried out by the developer and the obligation of the parties β Parties had not clearly defined, inter alia, the nature of material to be used, the requirements of quality, structure of building, sizes of flats and obligations of the owner after the plan is sanctioned β Also, clause 9 of the agreement stated that the owner shall pay the contractor costs, expenses along with agreed remuneration only after completion of the building on receiving the possession β However, exact amount of remuneration payable by the owner to the contractor was not found in the agreement β Agreement between the parties was vague, so the first condition in s.14(3)(c)(i) was not fulfilled β Furthermore, the developer had incurred an expenditure of Rs.18,41,000/- towards clearing outstanding dues, security deposit and development, incidental and miscellaneous expenses β The alleged losses/damages incurred by the plaintiff could be quantified and recompensed with β Thus, developer had failed to satisfy the conditions under sub-clause (i) and (ii) of s.14(3)(c) of the Act β In such a case, specific performance could not be granted. Specific Relief Act, 1963 β s.14(3)(c)(iii) β Interpretation of β Held: Anomaly is created by the use of the words βthe defendant has, by virtue of the agreement, obtained possession of the whole 756 [2018] 12 S.C.R. 756 A B C D E F G H 757 or any part of the landβ in s.14(3)(c)(iii) β Under a development agreement, an interest in the property may have been created in favour of the developer β If the developer is the plaintiff and the suit is against the owner, strictly applied, clause(iii) would require that the defendant should have obtained the possession under the agreement, however, the owner is in possession of the land by virtue of the lawful title, the defendant-owner cannot be said to have obtained possession of the land by way of the agreement β This would lead to an anomalous situation where the condition in s.14(3)(c)(iii) would not be fulfilled in the case of a suit by a developer β Thus, purposive interpretation has to be given to s.14(3)(c)(iii), departing from the literal rule of interpretation β By giving a purposive interpretation to s.14(3)(c)(iii), the anomaly and absurdity created by the third condition will have no applicability in a situation where the developer who has an interest in the property, brings a suit for specific performance against the owner β The developer will have to satisfy the two conditions laid out in sub clause (i) and (ii) of Section 14(3)(c), for the suit for specific performance to be maintainable against the owner β This will ensure that both owners and developers can avail of the remedy of specific performance under the Act β Interpretation of Statutes β Purposive rule of Interpretation. Appellant and predecessor-in-interest of the respondents entered into a development agreement for construction of a building on the land of the respondents. Respondent denied execution of the agreement. Appellant filed a suit against the respondent for specific performance of the contract. Trial Court held that sanctioned plans of the proposed building was not obtained by the appellant as per agreement and therefore, it could not be said that he had obtained possession of the land, as a result suit was barred by s.14(3)(c). Appeal was dismissed by the High Court. Thus, the present appeal. Dismissing the appeal, the Court HELD: 1. The issue before this Court is whether Section 14(3)(c)(iii) of Specific Relief Act, 1963 is a bar to a suit by a developer for specific performance of a development agreement bet
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex