LexaceLexace Ask the AI ›
βš–οΈ Ask the AI about your situation:πŸš— Car AccidentπŸ’Ό Work / Job🏠 Housing / EvictionπŸ‘ͺ Family / DivorceπŸ“‹ Contract DisputeπŸ’° Money Owed

SUBODH SINGH versus UNION OF INDIA AND OTHERS

Citation: [2024] 6 S.C.R. 708 · Decided: 16-05-2024 · Supreme Court of India · Bench: HIMA KOHLI, AHSANUDDIN AMANULLAH · Disposal: Appeal(s) allowed

cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 6 S.C.R. 708 : 2024 INSC 458
Subodh Singh 
v. 
Union of India and Others
(Civil Appeal No. 6458 of 2024)
16 May 2024
[Hima Kohli and Ahsanuddin Amanullah, JJ.]
Issue for Consideration
Whether the appellant is entitled to additional compensation for 
the left out portion of land at least @ 5% of the value of the award 
for a period spreading over 84 months.
Headnotes
Compensation – Additional compensation for the left out 
portion of land – Payment towards the delay only to two 
months – Appellant claimed payments towards delay of 84 
months – Correctness:
Held: Respondents had acquired a land by Notifications issued u/s. 
20(E)(1) of the Indian Railways Act, 1989 – An award was declared 
on 08.02.2010 in respect of land that respondent acquired – A parcel 
of land admeasuring 0.0624 Hectare was left out – The High Court 
vide order dated 20.09.2016 directed the respondents to provide 
compensation to the appellant for 0.0624 Hectare of land, which 
was left out, along with additional compensation – While calculating 
the additional compensation, respondent confined the same to a 
period of two months for delayed period – Appellant claimed that he 
was entitled to compensation for a period of 84 months and relied 
on one Kamla Devi & Ors. – This Court noted that an order dated 
18.09.2017, passed by the Competent Authority refers to an order 
dated 19.07.2017, passed by the High Court in a Writ Petition filed by 
Kamla Devi and others and goes on to record that after completion 
of formalities of publication, some portion of the land admeasuring 
0.0890 Hectare had been left out, as the same was not required for 
the subject project – Subsequently, another award was declared in 
respect of the left out area and additional compensation was paid 
to the land owners @ 5% per month of the award for a period of 66 
months, i.e. from 19.04.2012 to 12.09.2017 – In light of the above, 
the appellant herein cannot be treated differently in his case, the 
respondents ought not to have confined the delayed payment on the 
[2024] 6 S.C.R. 
709
Subodh Singh v. Union of India and Others
awarded amount for the left out portion of land to only two months – 
Thus, the appellant is held entitled to additional compensation for 
the left out portion of land at least @ 5% of the value of the award 
for a period spreading over 84 months. [Paras 3, 4, 9, 12]
Case Law Cited
Dedicated Freight Corridor Corporation of India v. Subodh Singh 
[2011] 3 SCR 1160 : (2011) 11 SCC 100 – referred to.
List of Acts
Indian Railways Act, 1989.
List of Keywords
Compensation; Additional compensation; Award; Delay in payment; 
Payment of additional compensation; Additional compensation for 
left out portion of land.
Case Arising From
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6458 of 2024
From the Judgment and Order dated 31.08.2017 of the High Court 
of Judicature at Allahabad in WC No. 39875 of 2017
Appearances for Parties
S. B. Upadhyaya, Sr. Adv., Aftab Rasheed, Aftab Ali Khan, M. Z. 
Chaudhary, Mansur Ali Khan, Rahat Ali Chaudhary, M.A. Mansoori, 
Advs. for the Appellant.
K M Nataraj, A.S.G., Amrish Kumar, Mrs. Indira Bhakar, Anuj Udupa, 
Manoj Mishra, Chitvan Singhal, Padmesh Mishra, Saurabh Mishra, 
Shrimay Mishra, Abhinav Pandey, Rakesh Chander, Nirbhaya S 
Tewari, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Order
1.	
Leave granted. 
2.	
The present appeal is directed against the order dated 31st August, 
2017, passed by the Division Bench of the High Court of Judicature 
at Allahabad whereby, the Writ Petition filed by the appellant herein 
praying inter alia for issuing directions to the respondents to pay 
710
[2024] 6 S.C.R.
Digital Supreme Court Reports
additional compensation for the entire land area, subject matter of 
the Notification dated 12th December, 2008, issued under Section 
20(E)(1) of the Indian Railways Act1, 1989, at the rate higher than 5% 
per month and further pay interest @ 18% per annum for delay in 
payment from 30th March, 2011, i.e. the date on which this Court had 
passed an order in Civil Appeal No. 2794 of 20112 titled β€œDedicated 
Freight Corridor Corporation of India Vs. Subodh Singh”, till the actual 
date of payment in respect of the award dated 08th February, 2010. 
3.	
It is submitted on behalf of the appellant that the respondents 
had acquired land in Village Kakrahi, Tehsil and District Auriya, 
Uttar Pradesh vide Notifications dated 10th June, 2008 and 16th 
December, 2008 issue

Excerpt shown. Read the full judgment & AI analysis in Lexace.