STEEL AUTHORITY OF INDIA LTD. versus J.C. BUDHARAJA, GOVERNMENT AND MINING CONTRACTOR
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
STEEL AUTHORITY OF INDIA LTD. A v. J.C. BUDHARAJA, GOVERNMENT AND MINING CONTRACTOR SEPTEMBER 1, 1999 [D.P. WADHWA AND M.B. SHAH, JJ.] B Arbitration Act, 1940: Section 30. Misconduct-Jurisdictional error-Contract stipulated that no claim would be tenable for delay in handing over the work site-Contract only C provided extension of time for completion in case of such delay-Despite such prohibition, award given for losses due to delay in handing over work site-Held: Arbitrator has to function within the limits of the agreement and cannot exceed his jurisdiction-Whether or not the arbitrator has so functioned would be a jurisdictional fact and required to be gone into by the court- D Arbitrator may have jurisdiction to entertain a claim but does not have jurisdiction to pass award in respect 'of prohibited items of contract-I/ he does so it will be a jurisdictional error-Hence, the said award is, on the face of it, illegal. Arbitration-Disputes-Reference to-Period of limitation-Cause of action-Arising of-Contractor gave notice on 29-8-1979 demanding a E certain sum-No response and no payment from company-Contractor's right to receive damages not kept alive in subsequent supplementary agreement- Instead contractor agreed to complete work within the stipulated time on a higher rate-Company wrote letter in [on 3.9.1983} repudiating the claim made by the contractor-No action to refer the dispute for arbitration taken p by contractor within 3 years from 29-8-1979-When dispute with regard to second agreement [dated 20.12.1980} arose in 1985 contractor gave notice for appointment of arbitrator and the matter was referred to arbitration-In that reference contractor raised the dispute pertaining to the first agreement- Arbitrator appointed in December I 985 with reservation that the claim was barred by the period of limitation-Held: Cause of action arose on G 29-8-1979, the date of notice of demand-Hence, Claim before the arbitrator in December 1985 barred by period of limitation-:-Letter written in 1983 would not give fresh cause of action because on that date cause of action for recovering the amount was barred by the period of three years prescribed under Art. 137 of the Limitation Act-Under S. 3 of the Limitation Act it was H 155 '\ Cl 156 SUPREME COURT REPORTS [1999] SUPP. 2 S.C.R. A the duty of the arbitrator to reject the claim as it was, on the face of it, barred by limitation-Limitation Act, 1963, Art. 13 7 and S. 3. Arbitration-4ward-Speaking or non-speaking-Contractor claimed damages for delay in handing over the work site-Arbitrator awarded damages and also gave reasons for it-Held: The reasons clearly reveal that the B award is a speaking award-Hence, court can go behind it. The predecessor of the appellant executed a contract with the predecessor of the respondent for certain construction within a wild life sanctuary. The agreement stipulated that no claim for delay in giving the C entire site or giving it gradually would be tenable and in such cases the appellant was only obliged to extend the time for completion of the work. The respondent raised a dispute on 29-8-1979 for losses incurred due to delay in handing over the work site but there was no response from the appellant and no payment was made. Thereafter a supplementary agreement D was executed between the appellant and the respondent in which it was nowhere stated that the respondent's .alleged right of getting payment for damages or losses suffered was kept alive. On the contrary, the respondent had agreed to complete the work within the time stipulated in the second agreement by charging some higher rate. The respondent had not sought E any reference of the aforesaid dispute within three years from the date when cause of action arose i.e., 29-8-1979. However, the appellant wrote a letter in 1983 repudiating the respondent's claim on account of damages or losses suffered by him. When a dispute arose with regard to the second agreement the F respondent gave a notice on 2-12-1985 to appoint an arbitrator and the matter was referred to arbitration. In that reference, the respondent raised certain claims relating to the work done under the first agreement. The appellant appointed an arbitrator with a specific reservation regarding the tenability, maintainability and validity of reference as also on the ground that G the claim was barred by the period of limitation and it pertained to excepte
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex