STATE OF U.P. versus MIS RAM NATH INTERNATIONAL CONSTRUCTION PVT. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
- STATE OF U.P. v. MIS RAM NATH INTERNATIONAL CONSTRUCTION PVT. LTD. NOVEMBER 10, 1995 fS.C. AGRAWAL AND G.B. PATTANAIK, JJ.) Arbitration Act, 1940-Section 30-Arbitration Award-Jurisdiction of Court to inteifere-Arbitrator cannot entertain and decide any dispute not ref e"ed to it. A B c The Respondent-contractor entered into an agreement with the ap- pellant for construction of non overflow and overflow sections with bridge spillway and other appurtenant works. The agreement was entered into on 26.8.1985 and work commenced from 1.9.1985. The period stipulated for completion of the work was 42 months. Disputes having arisen between the D parties in respect of the quantity of work in excess of the estimated quantity in the agreement, the parties invoked the arbitration clause. The dispute was referred to the sole arbitrator. The contractor claimed higher rate than what was agreed to in the agreement while the State refused to accede to the contractor's demand. According to the contractor, on account E of substantial change in designs and drawings there had been abnormal increase in the quantities of work compared to the estimated quantity of work in the original agreement and in respect of such additional quantity of work he was not bound to be paid at the agreed rate but at an enhanced rate on the basis of the analysis of rate submitted by him. The appellant State while denying its liability to pay at the revised rate as claimed by the contractor, admitted that there had been a change in the drawings and designs and on account of such change, the quantity of work had increased but the claimant was not entitled to any enhanced rate. The arbitrator came to the conclusion that the contractor could not have refused the work in accordance with the alterations and modifications in the drawing and design; that there had been a fundamental change in the drawings and designs which abnormally increased the quantum of work than the estimated quantum indicated in the agreement and under F G the agreement though the contractor could not claim any excess rate for work upto the excess of 10%, but beyond the same the contractor would be H 99 100 SUPREME COURT REPORTS (1995) SUPP. 5 S.C.R. A entitled to claim a higher rate. In respect of the quantity of work executed after the date of the completion of the work indicated in the agreement, the arbitrator granted as per the rate claimed by the contractor and in respect of works executed after 30th April, 1990, the claimant would be paid at the same rate. B c D E F G The contractor filed _an application for making the award a rule of Court. The appellant State filed his objections challenging the legality of the award. The Trial Court being of the opinion that the Court has no jurisdiction to interfere with an award of the arbitrator since the ar- . bitrator had decided all the issues properly with detailed analysis as well as after perusing all the necessary documents, made the award a rule of the Court. The Court held that the arbitrator was fully within his powers to accept the analysis of rate submitted ยทby the contractor which was in fact not disputed by the State and therefore there was no error in the award which could be interferred with by the Court and the objection filed by the State could not be entertained and perused as the same was filed beyond the period of 30 days. The award having been madt: a rule of Court and the objection of the State having been rejected, the State preferred an appeal u/s 39 of the Arbitration Act. The High Court set aside the con- clusion of the Trial Judge with regard to the entertainability of the objec- tion filed by the State and held that taking into account the magnitude of the claim of Rs. 1 crore and that the objection could not be filed on 23.3.1991 on account of Lawyers' strike and 24.3.1991 being a Sunday, the objection filed on 25.3.1991 had to be considered on condoning the delay, in the interest of justice. On merits the High Court refused to interfere with the decision of the Trial Judge on the ground that the arbitrator had not committed any error in allowing the claim of the contractor as per the analysis of rates given by it in respect of the extra quantity of work and it was not permissible for the Court within the parameter for exercise of its jurisdiction to interfere with the award. Appeal having been dismissed, the State had filed this appeal against
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex