LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

STATE OF U.P. versus ALLIED CONSTRUCTIONS

Citation: [2003] SUPP. 2 S.C.R. 55 · Decided: 31-07-2003 · Supreme Court of India · Bench: V.N. KHARE, K.G. BALAKRISHNAN, S.B. SINHA · Disposal: Disposed off

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

STATE OF U.P. 
A 
v. 
ALLIED CONSTRUCTIONS 
JULY 31, 2003 
[V.N. KHARE, CJ., K.G. BALAKRISHNAN AND S.B. SINHA, JJ.] 
B 
Arbitration Act, 1940: Arbitration-Force majeure clause of agreement-
Contract between the parties for construction of a bridge-cum-fall-Work 
partly done by contractor destroyed by flood-Claim by contractor for loss 
sustained-Matter referred to arbitrator who made an award in favour of C 
contractor-Plea of State Government to invoke force majeure clause of 
agreement rejected-Held, a perusal of relevant clause of the agreement shows 
that it protected the State from liability and damage occasioned by 
unprecedented flood which could not have been foreseen or avoided as a 
prudent person-No evidence was led before the arbitrator to show that the D 
rain as a result of which the loss was sustained by the respondent was 
unprecedented and in fact it was an act of God-A fact to this effect has be(m 
recorded by the arbitrator as well as the High Court and, therefore, both 
came to the conclusion that force majeure clause of the agreement was not 
attracted-Contract-Force majeure clause in the agreement-Applicability 
ef 
E 
Award by arbitrator-Setting aside of-Held, award made by pn 
arbitrator can be set aside only if one or the other term specified in sections 
30 and 33 of the Act is attracted-The arbitrator is a judge chosen by the 
parties a11d his decision is final-Court is precluded from reappraising the F 
evidence-Once it is found that the view of the arbitrator is a plausible one, 
court will refrain itself from interfering-On facts, it is not a case wherein it 
can be said that the ar'bitrator has misconducted the proceedings-
Interpretation of a contract is a matter for arbitrator to determine-It was 
within his jurisdiction to interpret the force majeure clause of the agreement 
having regard to the fact situation obtaining therein-The award is a speaktng G 
one-The arbitrator has assigned sufficient and cogent reasons in support 
thereof 
Mis. Sudarsan Trading Co. v. The Government of Kera/a, AIR (1989) 
SC 890; UP. State Electricity Board v. Searsole Chemicals Ltd., (2001:1 3 
55 
H 
56 
SUPREME COURT REPORTS [2003] SUPP. 2 S.C.R. 
A SCC 397; /SPAT Engineering & Foundry Works, B.S. City, Bokaro v. Steel 
Authority of India Ltd B.S., City, Bokaro, (20011 6 SCC 347, relied on. 
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 14152 of 
1996. 
B 
From the Judgment and Order dated 18.12. I 995 of the Allahabad High 
Court in F.A.O. No. 715 of 1994. 
Ravi Prakash Mehrotra and Garvesh Kabra for the Appellant. 
Uday Umesh Lalit for the Respondent. 
c 
The following Order of the Court was delivered : 
Under a contract entered into by and between the appellant and the 
respondent, the respondent undertook construction of bridge-cum-fall at Munda 
Khera Scape at the estimated cost of Rs. 37.2 lakhs. While the work was in 
D progress, the work area was flooded in the night of August 25 and 26, I 99 I. 
The respondent-contractor herein filed a claim on account of loss 
sustained by him due to flooding of the work area. Ultimately, the matter was 
referred to an arbitrator. The arbitrator gave an award for payment of a sum 
of Rs. 12,55,365 together with interest at the rate of 18 per cent from 1.11.1991 
E till the date of the award and 6 per cent thereafter. The respondent filed the 
award for being made rule of the Court. The appellant herein filed a petition, 
inter alia, on the ground that the arbitrator has misconducted the proceeding3, 
inasmuch as the force majeure contained in Clause 47 disentitled the 
respondent from making any claim which was on account of unprecedented 
F rain. The said objection was rejected and the award was made rule of the 
Court. The appellant thereafter filed a first appeal from order before the High 
Court and the same was dismissed. It is against the said judgment, the appellant 
is in appeal before us. 
Learned counsel appearing for the appellant reiterated his argument 
G raised before the High Court. In fact, his argument based on force majeure 
is that because of unprecendented rain the liability of loss cannot be thrust 
upon the appellant. We do not find any merit in this contention. Clause 47 
of the Agreement runs as under: 
"Neither party shall be liable to the other for any loss or damage 
H 
occasioned by or arising out of act of God, such as unprecedented 
\. 
ST A TE v. ALLIED CONSTRUCTIONS 
57 
flood, volcanic eruption, earthquake or other convulsio

Excerpt shown. Read the full judgment & AI analysis in Lexace.