STATE OF RAJASTHAN & ANR. versus MIS. FERRO CONCRETE CONSTRUCTION PVT. LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
-I [2009) 10 S.C.R. 31 "< 1 STATE OF RAJASTHAN & ANR. A v. MIS. FERRO CONCRETE CONSTRUCTION PVT. LTD. (Civil Appeal No.ยท 2764 of 2009) APRIL 22, 2009 B [R.V. RAVEENDRAN AND LOKESHWAR SINGH PANTA, JJ.] ARBITRATION ACT, 1940 s.30- Setting aside of award- Held: When there is no c allegation of moral misconduct against arbitrator, award can be attacked if there was legal misconduct on the part of the ~ arbitrator in making the award and/or if there was an error apparent on the face of the award - In the instant case, the D arbitrator, in respect of claims 1 and 37-A of the contractor and rate of interest payable to contractor (claims 12 and 13) committed a legal misconduct by ignoring terms of contract and it was also a case of error apparent on the face of award - In a reasoned award if claim of contractor is equated to proof E of the claim, then it is obviously a legal misconduct and an .-4 error apparent on the face of award - Allowing of interest at 18% in an award governed by 1978 Act was an error on the face of award - The rate of interest could not exceed the current rate of interest - As regards the award in respect of F other claims and counter claims, neither want of jurisdiction nor legal misconduct nor any error apparent on the face of award was made out, therefore, the award in respect of those claims and counter-claims is upheld - Award modified ~ accordingly - Interest Act, 1978. G INTEREST ACT, 1978 : S.3- Interest on claims allowed in an award made under .. Arbitration Act, 1940 - Held: In the absence of an express bar, 31 H - 32 SUPREME COURT REPORTS [2009] 10 S.C.R. ~ arbitrator had jurisdiction to award interest for pre-reference, โข A pendente lite and future periods - However, award of interest ~ at a rate higher than the current rate is an error on the face of award - Award modified accordingly - Arbitration Act, 1940. B The appellant (employer) entered into a contract with the respondent-contractor for manufacture, laying, โข testing and commissioning of water pipeline at a length ~ of 37.41 kilometers. The value of the work as per the work order was Rs. 9,91,94,602.50. Since the contractor could c not complete the work within the stipulated time, the employer got the work completed through alternate agency by treating the contract as having been abandoned. As regards the settlement of disputes between the parties through arbitration, the matter D reached the Supreme Court and ultimately a sole .. arbitrator was appointed. Before the arbitrator the contractor filed its claim in 43 heads aggregating to Rs.6,21,29,626/-. The employer, besides filing its reply to the claim statement, made five counter claims to the tune of Rs.11,55,98,388/-. The arbitrator allowed certain claims E of the contractor amounting to about Rs.1,&7,00,000 and one counter claim of the employer (amounting to Rs.59,42,275/-. The contractor filed an application to make j. the award a rule of the court. The civil court allowed the application subject to modification of the award made on F claim 37-A of the contractor (direction to employer to pay Rs.12,072/- per day towards idle charges for machinery and staff etc. from the date of award) holding that the said charges would be payable per day from the date of decree. Both, the employer as also the contractor filed G appeals. The High Court dismissed the appeal of the employer and allowed that of the contractor restoring the i- direction of the arbitrator to pay the compensation of Rs.12,072/- per day from the date of the award. H In the appeals filed by the employer, the question for STATE OF RAJASTHAN v. FERRO CONCRETE 33 CONSTRUCTION PVT. LTD. _, consideration before the Court was : whether there was A any legal misconduct or error apparent on the face of the award, in regard to the award of the arbitrator in respect of the claims and counter-claims. Allowing the appeals in part, the Court B HELD: 1.1. Section 30 of the Arbitration Act, 1940 inter alia provides that the award can be set aside on the ground that the arbitrator had misconducted himself or the proceedings, or that the award had been improperly c procured or is otherwise invalid. An error apparent on the face of the award, is a ground for setting aside the award u/s 30 or for remitting the award to the arbitrator u/s 16(1) (c) of the Act. [Para 13] [46-8-C] . ~ Champsey Bhara & Co. vs. Jivraj Ba/loo Sp
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex