SSANGYONG CONSTRUCTION CO. LTD. versus NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI)
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 522 SUPREME COURT REPORTS [2019] 7 S.C.R. SSANGYONG ENGINEERING & CONSTRUCTION CO. LTD. v. NATIONAL HIGHWAYS AUTHORITY OF INDIA (NHAI) (Civil Appeal No. 4779 of 2019) MAY 08, 2019 [R. F. NARIMAN AND VINEET SARAN, JJ.] Arbitration and Conciliation Act, 1996 โ ss.34(2)(b)(ii), 34(2)(a)(iii) โ Respondent invited bids for construction of a four- lane bypass on National Highway 26 in the State of Madhya Pradesh โ Appellantโs bid was accepted โ Price adjustment for four of the components used in execution of the contract i.e. cement, steel, plant and machinery, and other local materials was to be calculated as per formula given in sub-clause 70.3 of the contract โ Price adjustment was being paid to the appellant by using the Wholesale Price Index (WPI) published by the Ministry of Industrial Development, which followed the years 1993-94= 100 (Old Series) โ However, w.e.f 14.09.10, the Ministry stopped publishing the WPI for the Old Series and started publishing indices under the WPI series 2004-05= 100 (New Series) โ As both the indices C1 and Co were available to the appellant under the New Series for calculating price adjustment, the appellant raised bills accordingly โ On 15.02.13, the respondent issued a Policy Circular in which a new formula for determining indices was used stating that the Circular would be applied to the contract in question, as a result of which, a linking factor would have to be provided by which the Old Series was connected to the New Series โ Appellant challenged the Circular โ Eventually, the arbitral tribunal consisting of three members by majority award held that the Circular could be applied as it was within contractual stipulations โ Petition u/s.34 filed by the appellant โ Rejected by the High Court โ Appellant inter alia pleaded that s.34(2)(b)(ii) was attracted as the award was in conflict with the public policy of India and that s.34(2)(a)(iii) would also be attracted as principles of natural justice were violated โ Held: Government guidelines that were referred to and relied upon by the majority award to arrive at the linking factor were never in evidence before the Tribunal โ Tribunal relied upon the said guidelines by itself [2019] 7 S.C.R. 522 522 A B C D E F G H 523 stating that they are to be found on a certain website โ This being the case, the appellant would be directly affected, not being allowed to comment on the applicability or interpretation of those guidelines โ Thus, majority award set aside u/s.34(2)(a)(iii) โ Further, in order to apply a linking factor, a Circular, unilaterally issued by one party, cannot possibly bind the other party to the agreement without that other partyโs consent โ Indeed, the Circular expressly stipulated that it cannot apply unless the contractors furnish an undertaking/ affidavit that the price adjustment under the Circular is acceptable to them โ Appellant gave such undertaking only conditionally and without prejudice to its argument that the Circular does not and cannot apply โ Majority award created a new contract for the parties by applying the said unilateral Circular and by substituting a workable formula under the agreement by another formula de hors the agreement โ Thus, a fundamental principle of justice was breached โ Such a course of conduct would be contrary to fundamental principles of justice as followed in this country and shocks the conscience of the Court โ However, this ground is available only in very exceptional circumstances, as in the present case โ Judgments of the Single Judge and the Division Bench of the High Court, set aside โ Consequently, the majority award is also set aside โ In order to do complete justice between the parties, invoking power u/Art.142 of the Constitution of India, the minority award is upheld โ This award, together with interest now be executed between the parties โ Foreign Awards (Recognition and Enforcement) Act, 1961 โ s.7 โ Constitution of India โ Art.142 โ UNCITRAL Model Law on International Commercial Arbitration โ Art.26. Arbitration and Conciliation Act, 1996 โ s.34 โ Setting aside an arbitral award, in conflict with โpublic policy of Indiaโโ Law post Amendment Act, 2015 โ Held: โPublic policy of Indiaโ, whether contained in s.34 or s.48 of the 1996 Act would now mean the โfundamental policy of Indian lawโ as explained in paragraphs 18 and 27 of Associate Builders case i.e. the fundamental policy of Indian law would be relegated to the โRenusagarโ understanding of this
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex