SREE KAMATCHI AMMAN CONSTRUCTIONS versus THE DIVISIONAL RAILWAY MANAGER (WORKS), PALGHAT & ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2010] 10 S.C.R. 487 ยท SREE KAMATCHI AMMAN CONSTRUCTIONS v. THE DIVISIONAL RAILWAY MANAGER (WORKS), PALGHAT & ORS. (Civil Appeal Nos. 6815-6816 of 2010) AUGUST 20, 2010 [R.V. RAVEENDRAN AND H.L. GOKHALE, JJ.] A B Interest - Award of - Contract - Arbitration - Award refusing interest for pre-reference period and pendente lite - C Propriety of - Held: Award of interest for such period was rightly denied by arbitral tribunal - General conditions of the contract between the parties expressly barred award of interest - In view of s. 37(1) of Arbitration and Conciliation Act, arbitral tribunal is bound by the terms of the contract and thus cannot D award interest for pre-reference period or pendente lite - Arbitration and Conciliation Act, 1996 - s. 37(1) - Contract. First respondent-Railways entrusted construction work to the appellant under a contract. The appellant- E contractor invoked the arbitration clause, alleging breach of contract by the first respondent. Disputes were referred to arbitral tribunal, which ultimately passed a reasoned award rejecting all the claims of the Railways. It awarded only future interest and refused to award the interest for pre-reference period and interest pendente lite. However, it rejected two of the claims of the contractor. Railways as well as the contractor filed petitions u/ F s. 34 of the Arbitration and Conciliation Act, 1996. Single Judge of the High Court rejected both the challenges to G the award. As regards interest, it held that in view of the bar contained in Clause 16(2) of General Conditions of contract, the contractor was not entitled to it. Division Bench of the High Court dismissed the writ appeal filed 487 H 488 SUPREME COURT REPORTS [2010] 10 S.C.R. A by the contractor and allowed the writ appeal filed by the Railways. Therefore, the instant appeals were filed. B The questions for consideration in the instant appeal were: (1) Whether the contract between the parties contained an express bar regarding award of interest; and (2) Whether the arbitral tribunal was justified in c refusing interest for the period between the date of cause of action to the date of the award. Dismissing the appeals, the Court HELD: 1. Clause 16(2) of the General Conditions of D contract governing the contract between the parties in terms specifically bars payment of interest on earnest money or the security deposit or the amounts payable to the contractor under the contract. Claim No.4 (relating to erroneous billing) related to a work executed by the E contractor as a part and parcel of the work contemplated under the agreement. Payment directed by the arbitral tribunal for such work was also in accordance with the Agreement Schedule Item No.19. Therefore it is evident that the amount awarded in regard to claim No. (4) was F an amount payable to the contractor under the contract. Consequently, no interest could be paid thereon having regard to the bar under Clause 16(2) of the General conditions of contract. [Para 5] [492-F-H; 493-A-E] 2.1 If there is a bar against payment of interest in the G contract, the arbitrator cannot award any interest for the pre-reference period or pendente lite. In view of the specific bar under Clause 16(2) of the General Conditions of the contract, the arbitral tribunal was justified in refusing interest from the date of cause of action to the H date of awards. [Para 6] [495-E-F] SREE KAMATCHI AMMAN CONSTRUCTIONS v. DIVISIONAL 489 RLY MANAGER (WORKS), PALGHAT Sayeed Ahmed and Co. v. State of UP. 2009 (12) SCC A 26; Union oflndia v. Saraswat Trading Agency 2009 (16) sec 504, relied on. Irrigation Department, Government of Orissa v. G.C. Roy 1992 (1) SCC 508; Executive Engineer, Dhenkanal Minor B Irrigation Division v. NC. Budharaj 2001 (2) SCC 721; Bhagawati Oxygen Ltd. v. Hindustan Copper Ltd. 2005 (6) SCC 462; State of Rajasthan v. Ferro Concrete Construction (P) Ltd. 2009 (12) SCC 1, referred to. 2.2 The appellant will not be entitled to interest C pendente lite, that is, for the period from the date of reference to the date of the award. Section 37(1) of the Arbitration and Conciliation Act, 1996, by using the words "unless otherwise agreed by the parties" categorically clarifies that the arbitrator is bound by the terms of the D contract insofar as the award of interest from the date of cause of action to the date of the award. Therefore, where the parties hav
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex