LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

SOMDATT BUILDERS-NCC-NEC(JV) versus NATIONAL HIGHWAYS AUTHORITY OF INDIA & ORS.

Citation: [2025] 2 S.C.R. 203 · Decided: 26-01-2025 · Supreme Court of India · Bench: ABHAY S. OKA · Disposal: Appeal(s) allowed

cites 9 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 2 S.C.R. 203 : 2025 INSC 113
Somdatt Builders-NCC-NEC(JV) 
v. 
National Highways Authority of India & Ors.
(Civil Appeal No. 2058 of 2012)
27 January 2025
[Abhay S. Oka and Ujjal Bhuyan,* JJ.]
Issue for Consideration
Issue arose as regards correctness of the judgment of the Division 
Bench setting aside the arbitral award u/s.37 of the Arbitration and 
Conciliation Act.
Headnotes†
Arbitration and Conciliation Act, 1996 – s.34 and 37 – 
Jurisdiction under – Exercise of – Interference with the 
decision of the arbitrator – Execution of contract awarded by 
National Highways Authority of India-NHAI to the appellant 
regarding construction of lanes on National Highway – Dispute 
as regards geogrid/geotextile material exceeded the Bill of 
Quantities-BOQ quantities in the contract, and the power 
of the Engineer to revise the rates given in the BOQ in the 
event of increase in actual quantities – Appellant’s case that 
the Engineer/Employer intending wrongful application of the 
Conditions of Particular Application for downward revision of 
rates for BOQ item of geogrid for quantity in excess of BOQ 
quantity – Recommendation by Dispute Review Board-DRB that 
quantities of geogrid required limited to facia area provided 
in the BOQ to be paid as per the BOQ rates – Invocation of 
arbitration clause by NHAI – Arbitral tribunal holding that the 
quantity of geogrid given at the tender stage by NHAI was 
wrong, there was no change in the design but mere increase 
in the quantity beyond the BOQ quantity, directed NHAI to pay 
the appellant for the actual quantity of geogrid required to be 
executed to complete the work as per the approved design 
at the BOQ rate – Application by NHAI u/s.34 – Single Judge 
of the High Court upheld the arbitral award – However, the 
Division Bench set aside the same – Sustainability:
* Author
204
[2025] 2 S.C.R.
Digital Supreme Court Reports
Held: Not sustainable – Great deal of restraint is required to 
be shown by the Courts while examining the validity of an 
arbitral award when such an award has been upheld, wholly or 
substantially, u/s.34 – Court cannot undertake an independent 
assessment of the merits of the award and must only ascertain that 
the exercise of power by the court u/s. 34 has not exceeded the 
scope of the provision – View taken by DRB and arbitral tribunal, 
both comprising of technical experts, that there is no variation 
either in the form or quality or quantity of the works is the correct 
one which was acknowledged by the Single Judge – At the time 
of execution of the contract, the geogrid required turned out to 
be much more than the estimated figure given in the contract – 
As such both the fact finding authorities held that there was no 
variation in terms of Clause 51.1 and the Engineer did not have 
the competence to renegotiate the price or rate of the geogrid 
for the excess quantity of geogrid required – This is clearly a 
plausible view – It is the correct interpretation of Clause 51 made 
by the DRB and the arbitral tribunal, in a reasonable manner 
based on the evidence on record – As such, the Single Judge 
rightly declined to interfere with the award of the arbitral tribunal 
u/s.34, affirming the decision of the DRB – Division Bench of the 
High Court not at all justified in setting aside the arbitral award 
exercising extremely limited jurisdiction u/s.37 by merely using 
expressions like ‘opposed to the public policy of India’, ‘patent 
illegality’ and ‘shocking the conscience of the court’ – Thus, the 
judgment and order passed by the Division Bench of the High 
Court is set aside and the arbitral award is restored. [Paras 27.3, 
28, 33, 34, 36, 42, 43]
Arbitration and Conciliation Act, 1996 – Arbitral award – Public 
policy in India – Explanation:
Held: Public policy in India means the fundamental policy of Indian 
law – Violation of Indian statutes linked to public policy or public 
interest and disregarding orders of superior courts in India would 
be regarded as being contrary to the fundamental policy of Indian 
law – It would also mean that the arbitral award is against basic 
notions of justice or morality – Arbitral award can be set aside on 
the ground of patent illegality, where the illegality goes to the root 
of the matter but reappreciation of evidence cannot be permitted 
under the ground of patent illegality. [Para 37]
[2025] 2 S.C.R. 
205
Somdatt Builders-NCC-NEC(JV) v.  
National Highways Authority of India & Ors.
Case Law 

Excerpt shown. Read the full judgment & AI analysis in Lexace.