SIME DARBY ENGINEERING SDN. BHD. versus ENGINEERS INDIA LTD.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2009] 11 S.C.R. 287
SIME DARBY ENGINEERING SON. BHD.
A
v.
ENGINEERS INDIA LTD.
(Arbitration Petition No. 3 of 2009)
JULY 22, 2009
B
[ASHOK KUMAR GANGULY, J.]
_..,
ARBITRATION AND CONCILIATION ACT, 1996:
ss.2(1)(d), (f), 10(2) and 11 - International Commercial
Arbitr3tion - Appointment of arbitral tribunal - Number of c
arbitrators - Dispute regarding - Held: In the instant case, the
relevant arbitration clause of agreement is silent about1: the
number of arbitrator - Therefore, s.10(2) squarely applies·-
In view of the arbitration clause read with s. 10(2)1 clear that D
'arbitral tribunal in the instant case would be consisting of a
... ,
sole arbitrator - Policy decision that for contracts costing over
a particular amount B committee of arbitrators would be
composed of, cannot change the contractual clause -
Besides, the policy decision coming into force after the
E
contract between the parties had been entered into, the said
policy decision cannot override the contract - UNCITRAL .
Model Law on International Commercial Arbitration - Articles .
2(b) and 10(2)-Administrative Law-Policy decision vis-a7vis,
~
contractual clause.
~
'F
s. 10(2) - Number of arbitrators - Held: Parties' autonomy
in the arbitration agreement must be given due importance
in construing intention of parties - Parties have freedom to
change the number of arbitrators even after the contract has
been entered, and by mutual consent parties may amend the
contract - Interpretation of commercial arbitration agreements.
G
-t. ·---1
Redfern and Hunter, Law and Practice of International
Commercial Arbitration, IV Edition, 2004, page 185 and Mustil
287
H
288
SUPREME COURT REPORTS
[2009] 11 S.C.R.
A and Boyd on Commercial Arbitration, 2nd Edition, page 17 4,
referred ·to.
B
c
D
E
F
G
H
CIVIL ORIGINAL JURISDICTION : Arbitration Petition No.
3 of 2009.
Petition Under Section 11 Sub section (5) r/w Sub section
(12) of The Arbitration & Conciliation Act, 1996.
Oipankar Gupta, Anil Bhatnagar, Amit Dhingra, Aman
Leekha and Dua Associates for the Petitioners.
Mukul Rohtagi, Syed Naqvi, Namrata ,Kapoor Sharma,
Diksha Rai Ninad Laud, Nikhil Rohtagi and Surya Kant for the
Respondents.
The following Order of the Court was delivered
ORDER
1. This petition has been filed under Section 11 of
Arbitration and Conciliation Act 1996 (hereinafter referred "the
said Act") by the petitioner praying for appointment of the
arbitral tribunal to adjudicate the claims and disputes between
the petitioner and the respondent.
2. The petitioner is a company incorporated and existing
under the laws of Malaysia and is engaged in the business of
fabrication of all types of offshore and onshore structures and
complexes. The respondent on the other hand is the company
incorporated under the (Indian) Companies Act, 1956 and is
inter alia engaged in the business of providing engineering and
related technical services for petroleum refineries and other
industrial projects.
3. The necessary facts of the case are that Oil and Natural
Gas Corporation Limited (ONGC) invited a tender vide
notification dated November 17, 2003 for carrying work of
Survey, Design, Engineering, Procurement, Fabrication,
~
;i
:iv
t>'-
~ ..
?--
SIME DARBY ENGINEERING SON. BHD. v.
289
ENGINEERS INDIA LTD.
~
Anticorrosion and Weight coating, Laying of submarine pipeline,
A
Installation of SPM, Load out, Tie-down/Sea-fastening and
various other jobs in respect of Mumbai High South Field
offshore site.
4. In connection with the said tender issued by ONGC,
B
respondent and petitioner entered into a Business Agreement
on 22/01/2004 by which it was agreed that the respondent shall
-{.
quote as a bidder against the said Tender with the petitioner
as a sub~contractor for identified scope of work. The tender was
awarded by ONGC to the respondent by notice dated 10/03/ c
2004 for the said fabrication and installation of D-1 Well-Cum-
Water Injection Platform at Mumbai High South field Off-shore
site on a turnkey basis for a sum of US $ 62,3000,000/- and
thereafter an agreement between the respondent and ONGC
was entered into. Then, the respondent entered into a
D
subcontract with the petitioner which was signed on 29th of
.i.,-
October 2004 and for Fabrication, Load Out and Transportation
of Jacket, Piles, Conductors and Deck for D-1 Well-Cum-Water
Injection Platform Project of ONGC 13t Bombay High South field
off-shoreExcerpt shown. Read the full judgment & AI analysis in Lexace.
Lex