SHYAM TELELINK LTD. NOW SISTEMA SHYAM TELESERVICES LTD. versus UNION OF INDIA
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2010] 12 S.C.R. 927 SHYAM TELELINK LTD. NOW SISTEMA SHYAM A TELESERVICES LTD. V. UNION OF INDIA (Civil Appeal No. 7236 of 2003) OCTOBER 5, 2010 B [MARKANDEY KAT JU AND T.S. THAKUR, JJ.) Telecom Regulatory Authority of India, Act, 1997 - s. 14(f!}(i) rlw s. 14A(1) - Grant of licence to a company under C Telecom Act for providing basic telecom services - Delay in commencing the commercial operations within the stipulated time provided in the agreement due to certain technical deficiencies - In the meantime, introduction of 'Migration Package' - The company unconditionally accepting the D package and paying the entire amount towards the licenceΒ· fee and liquidated damages in terms of the package - Further demand of amount towards liquidated damage - The company challenging the demand of entire amount towards liquidated damages and demanding refund thereof - The E tribunal declined the challenge - On appeal, Held: The company not entitled to question the terms of the Migration Package after unconditionally accepting and acting upon the same - The unconditional acceptance of the package would estop the company from challenging the recovery of the dues F under the package - The company cannot be allowed to approbate and reprobate the same instrument - Telecom Act, 1885 - Evidence - Estoppel. Maxim - Maxim 'qui approbat non reprobat' - Applicability of. G Doctrine - Doctrine of benefits and burdens - Applicability of. 927 H 928 SUPREME COURT REPORTS [2010] 12 S.C.R. A The appellant was granted a licence under the Telecom Act, 1885 on 4.3.1998 for providing basic telecom services. The licence agreement required the appellant to start the commercial operations within twelve months from the date of the agreement. The appellant, B when sought permission to commence the commercial operations, towards the end of the year, it was denied on the ground that certain technical deficiencies remained to be removed. In the meantime, the respondent-Union of India offered a Migration Package. The appellant gave an C unconditional acceptance to the Package. The respondent, in terms of the package, demanded 35% of the outstanding licence fee with interest, and also liquidated damages amounting to Rs. 7.30 crores. The appellant prayed for waiver of the damages and the same D on being turned down, paid the entire amount towards the liquidated damages. The appellant started the commercial operations on 5.6.2000. Thereafter, the respondent demanded a further amount of Rs. 70 lakhs as liquidated damages from the appellant for the delay in commissioning the service. Aggrieved by the demand of E the entire amount of Rs. 8 crores towards the liquidated damages, the appellant filed a petition before the Telecom Dispute Settlement and Appellate Tribunal and also demanded refund of the entire amount of Rs. 8 crores. The Tribunal dismissed the petition. Therefore, the F instant appeal was filed. Dismissing the appeal, the Court HELD: 1. The Tribunal was justified in holding that G the commercial operations were started only on 5th June, 2000 and that for the intervening period such operations could not be commenced on account of deficiencies that were attributed entirely to the defects in the system which the appellant had installed. It is not correct to say that the appellant was ready to commence commercial H SHYAM TELELINK LTD. v. UNION OF INDIA 929 operations in February 1999 i.e. within one year of the A date on which the agreement was signed between the parties, which is evident from the fact that it applied for the grant of permission to commence commercial operations from 3rd February, 1999 and this was sufficient to show its readiness to commence such B operations. It is not disputed that the actual operations started only on 5th June, 2000. The material placed before the Tribunal clearly established that during the intervening period, the appellant had been informed by the respondent that clearance for commencing c commercial operations could be considered only after certain requirements of the licence agreement were complied with. The material further established that the deficiencies pointed out by the Telecommunication Engineering Centre (TEC) could not be rectified by the 0 . manufacturer of the equipment purchased by the appellant forcing the latter to go for a new set of equipment from a new vendor in December 1999 which equipment was fin
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex