RAMACHANDRA REDDY AND CO. versus STATE OF ANDHRA PRADESH AND ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A RAMACHANDRA REDDY AND CO. v. STATE OF ANDHRA PRADESH AND ORS. FEBRUARY27, 2001 B [G.B. PATTANAIK, U,C. BANERJEE, BRIJESH KUMAR, JJ.] c D E The ArbitraJion Act, 1940 : Section 16-Remission of award-Power of Court-Discretionary-Ex- ercise of-When-Held, when there are omissions and defects in the award which cannot be modifiedorcon~cted-Appella!e Court---lnterference-When- Held, when discretion misused by Trial Court. Sections 16, SO and 33-Award-lnterference-Envr apparent on the face of award-Meaning of-Held, when basis of award erroneous Courts not to investigate beyond aivard of arbitrators and documents actually incorpo- raJed therein for purpose of finding out any alleged envr. Contractor seeking higher rate for extra quantity of work-Agreement not providing for escalated rate either expressly or imp/i,dly---Competent Authority granting extension of time but specifically intimating it will not make contractor eligible for extra claim-Whether contractor entitled to higher rate-Held, contractor not entitled to higher rate for additional excavation work-Arbitrator being creature of agreement, cannot pass award beyond tenns of agreement. Appellant-Claimant was awarded excavation work under a contract p by respondent. Dispute arose between parties which was referred to panel of arbitrators which rejected claim item Nos. 1, 2 and 3 while allowing claim item nos. 4 and 5. Claim Item No. 1 relates to increase in quantity of hard rock abnormally and appellant claimed Rs. 93,76,000 for such extra excavation. Claimant filed objection in the Civil Court under Section 16 of the Arbitration Act, 1940 against award of arbitrators rejecting claim G item Nos. 1, 2 and 3. Trial Court set aside award in relation to claim item No. 1 and some others and remitted the same for reconsideration to panel of arbitrators. Against the judgment of Trial Court, respondent preferred appeal under Section 39 which was allowed by the High Court in so far as it related to remitting claim item no. l while upholding other directions of H the Trial Court. Aggrieved by the judgment of High Court, claimant- 186 RAMACHANDRA REDDY v. STATE 187 contractor has filed the present appeal. Appellant contended that High Court committed serious error in re(erring to clause 59 as well as letters dated 15.7.1980 and 19.5.1983 while refusing payment at higher rate for additional excavation work; that arbitrators committed error apparent on the face of award;ยท that payment at higher rate for additional excavation was implied in view of recommen- dations of Executive Engineer; and that contractor was entitled to he paid at higher rate for additional excavation in accordance with Clause 63 ofยท -t the agreement. A B Respondent contended that the award did not contain any error C apparent on the face of it; that contention regarding payment at higher rate for additional excavation under clause 63 of the agreement was raised for the first time and should not he allowed to be raised and alternatively, that Clause 63 has no application for additional excavation since it applies only to supplemental items and additional excavation is not a si;pplemen- tal item; that claim for payment at higher rate for additional e:<cavation D was not sustainable in view of letters of respondent dated 15.7.1980 and ยท 19.5.1983 while allowing extension of time for completion of work; and that judgment of Trial Court tantamounts to gross error of jurisdiction in interfering with an award as ยทno reasons have been given for remitting claim item Nos. 1, 2 and 3 for reconsideration. E Dismissing the appeal, the Court HELD : I.I. Under the Arbitration Act, Section 16 is the provision under which the Court may remit the award for reconsideration of an arbitration and necessity for remitting the award arises when there are F omissions and defects in the award, which cannot he modified or cor- rected. Remission of an award is in the discretion of the Court and the powers of the Court are circumscribed by the provisions of Section 16 itself. Ordinarily, therefore, a Court may be justified. in remitting the matter if the arbitrator leaves any of the matters undetermined or a part of the matter which had not been referred to and answered and that part cannot be separated from the remaining part, without affecting the deci- sion on the matter, which was referred to arbitration or the award is so indefinite and incapable of execut
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex