LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

RAJASTHAN STATE MINES AND MINERALS LTD. versus EASTERN ENGINEERING ENTERPRISES AND ANR.

Citation: [1999] SUPP. 2 S.C.R. 710 · Decided: 20-09-1999 · Supreme Court of India · Bench: D.P. WADHWA · Disposal: Appeal(s) allowed

cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
RAJASTHAN STATE MINES AND MINERALS LTD. 
v. 
EASTERN ENGINEERING ENTERPRISES AND ANR. 
SEPTEMBER 20, 1999 
B 
[D.P. WADHWA AND M.B. SHAH, JJ.] 
Arbitration Act, 1940: Ss. 30 and 33. 
Jurisdiction of Arbitrator-Determination of-Works contract-
C Agreement clauses stipulating fzxed payment-Claim for additional payments 
and compensation-Dispute-Arbitration-Arbitrator appointed solely on 
the basis of agreement between the parties-Arbitrator allowing the claim 
in a non-speaking award-Validity of-Held, arbitrator has travelled beyond 
his jurisdiction by passing an award against the stipulations and prohibitions 
D contained in the contract-Arbitrator cannot act arbitrarily, irrationally, 
capriciously or independently of the contract-Deliberate departure or 
conscious disregard of the contract tantamount to malafide action-Award 
quashed and set aside. 
Arbitration~Non-speaking order-Inte1ference by courts-Scope and 
E extent of-Held, courts cannot speculate or probe the mental process by 
which arbitrator has reached his conclusion. Award can be set aside if 
arbitrator acts beyond his jurisdiction. 
F 
Arbitration-Award-lnte1ference by courts-Arbitrator committing 
mere error of fact or la~Held, courts cannot interfere. 
Arbitration-Award-Arbitrator exc;eding his jurisdiction-
Determination of-Held, in order to find out whether arbitrator exceeded his 
jurisdiction, refere_nce to terms of award necessary .. 
Appellant-company entered into an agreement with respondent No. 1 
G contractor on turn-key basis for carrying out certain work. The agreement 
clauses 17 and 18, clearly and unambiguously stipulated that the contractor 
shall be paid fixed rates and shall not be entitled to claim any extra payment 
or Increase in cost. However, respondent No. 1 contractor claimed additional , 
payments and compensation on account of escalation of cost of work, which 
H 
was refuted by the appellant. Thus, a dispute arose between the parties which 
710 
.. __ 
-
RAJASTHAN STATE MINES AND MINERALS LTD. v. EASTERN ENG. ENTERPRISES 
711 
was referred to the arbitrator for adjudication. The arbitrator by a non- A 
speaking award allowed the claims of the contractor along with interest. 
Appellant unsuccessfully challenged the said award before the trial court 
and High Court Hence the present appeal. 
On behalf of the appellant it was contended that the claims made by 
respondent No.I were not entertainable in view of clauses 17 and 18 of the B 
agreement and therefore the arbitrator travelled beyond his jurisdiction in 
awarding the compensation for the said claims. 
On behalf of respondent No. 1 contractor it was submitted that 
arbitration clause was of widest amplitude and it provides that "all disputes C 
and differences arising out of or in any way touching or concerning the 
contract whatsoever shall be referred to the sole arbitration". Hence the 
award passed by the arbitrator cannot be held to be without jurisdiction or 
it cannot be held that arbitrator has travelled beyond jurisdiction; award was 
a non-speaking one and therefore, also .the Court cannot go behind the said 
award for finding out the mental process of the arbitrator for awarding the D 
said sum; jurisdictional question was not raised properly before the arbitrator 
or before the District Court and the appellant allowed the arbitrator to 
proceed with the proceeding without raising its objection of jurisdiction or 
competence. 
Allowing the appeal, the Court. 
HELD: 1.1. Arbitrator has travelled beyond his jurisdiction by passing 
an award against the stipulations and prohibitions contained in the contract 
between the parties. Hence the award passed by the arbitrator is quashed and 
set aside. (740-G; 741-A] 
E 
F 
1.2. Arbitrator is a creature of the contract between the parties and 
hence if he ignores the specific terms of the contract, it would amount to 
jurisdictional error. In the instant case, the appointment of arbitrator was 
solely on the basis of the agreement entered into between the parties. It was 
nowhere indicated that the arbitrator was empowered to adjudicate any other G 
claims beyond the agreement between the parties. Even the arbitrator in his 
interim award has specifically stated that he was appointed to adjudicate the 
disputes between the parties arising out of the agreement. The award made 
by the arbitrator disregarding the terms of the reference or the arbitration 
agreement or the terms of the contract would be a jurisdictio

Excerpt shown. Read the full judgment & AI analysis in Lexace.