R.L. KALATHIA & CO. versus STATE OF GUJARAT
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2011] 1 S.C.R. 391 R.L. KALATHIA & CO. A v. STATE OF GUJARAT (Civil Appeal No. 3245 of 2003) JANUARY 14, 2011 8 [P. SATHASIVAM AND DR. 8.5. CHAUHAN, JJ.] 1- CONTRACT: Construction contract - Claim for additional work carried c out - Refused on the ground that the claim was laid after receiving final payment -Held : If there is accepted claim, the court cannot reject the same merely because the contractor has issued "No Due Certificate" - Principles as regards claims after acceptance· of final bill, enumerated - In the instant case, D ..._ the contractor accepted the amount of the final bill under protest - The contractor had performed additional work and had a genuine claim which was considered in detail and was rightly allowed by trial court - High Court without adverting to factual details e"ed in reversing the judgment and decree of E trial court on the ground of estoppel - Instead of remitting the matter to High Court, claim examined on merits - Judgment of High Court set aside and judgment and decree of trial court --- restored - Estoppel. The appellant-contractor, a partnership firm, engaged F in the construction business, was awarded a contract by the respondent-State Government for construction of a Dam. During the execution of the said work, the · Executive Engineer in-charge of the project, made certain .+ additions, alterations and variations in respect of certain G items of work and directed the appellant to carry out the same also. The appellant filed a consolidated statement of claims for the additional/altered works, but in vain. Ultimately, the contractor filed a suit for recovery of a sum 391 H 392 SUPREME COURT REPORTS [2011] 1 S~C.R. A of Rs.3,66,538/- with running interest. The trial court decreed the suit for Rs. 2,27,758/- with proportionate costs and interest at the rate of 6% p.a. from the date of the suit till realization. However, the Division Bench of the High Court allowed the appeal of the employer~state B Government and dismissed the suit mainly on the ground that the plaintiff-contractor had accepted the amount as per final bill "under protest" without disclosing any real grievance on merits and it amounted to accepting the final bill without any valid objection and. grievance. It further c held that the conduct of the contractor in accepting the final bill and thereafter sending statutory notice and filing the suit for recovery of the differential amount was barred by the principle of estoppel. Aggrieved, the plaintiff. contractor filed the appeal. D . . Allowing the appeal, the Court HELD: 1.1 From various decisions of this Court, the following principles emerge: (i) Merely because the contractor has issued "No Due Certificate", if there is E acceptable claim, the court cannot reject the same on the ground of issuance of "No Due Certificate"; (ii) Inasmuch as it is common that unless a discharge certificate is given in advance by the contractor, payment of bills are generally delayed, therefore, such a clause in the contract F would not be an absolute bar to a contractor raising claims which are genuine at a later date even after submission of such "No-claim Certificate".; (iii) even after execution of full and final discharge voucher/receipt by one of the parties, if the said party is able to establish that G he is entitled to further amount for which he is having adequate materials, he is not barred from claiming such amount merely because of acceptance of the final bill by mentioning "without prejudice" or by issuing 'No Due Certificate'. [para 9) (402-8-E] H R.L. KALATHIA & CO. v. STATE OF GUJARAT 393 \ Chairman and MD, NTPC Ltd. vs. Reshmi Constructions, A Builders & Contractors, 2004 (1) SCR 62 = (2004) 2 SCC 663; Ambica Construction vs. Union of India, 2006 (9) Suppl. SCR 188 = (2006) 13 SCC 475; National Insurance Company Limited vs. Boghara Polyfab Private Ltd., 2008 (13) SCR 638 = (2009) 1 SCC 267 - relied on B 1.2 In the instant case, it is true that when the final bill was submitted, the plaintiff had accepted the amount as mentioned in the final bill but "under protest". It is also the specific claim of the plaintiff that on the direction of the Department, it had performed additional work and, !C therefore, was entitled to additional amount/damages as per the terms of agreement. Merely because the plaintiff had accepted the final bill, it cannot be deprived of its right to
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex