POWER GRID CORPORATION OF INDIA LTD. versus PUNJAB STATE POWER CORPORATION LTD. AND OTHERS
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B c D E F G H [2016] 2 S.C.R. 116 POWER GRID CORPORATION OF INDIA LTD. v. PUNJAB STATE POWER CORPORATION LTD. AND OTHERS (Civil Appeal No. 9193 of2012) MARCH 03, 2016 [RANJAN GOGOi AND PRAFULLA C. PANT, JJ.] Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulation, 2009: Regns. 2, 3(12) - Transmission Tariff - Determination of - Date of Commercial operation - Appellant is transmission licencee - Constructed ./00 KV Barh-Balia double circuit transmission - Respondent no. I is one of the beneficiaries - Construction of sub-station including switchgear and protection system at the Barh end was within the scope of work undertaken by NTPC - Appel/am filed petition before CERC for determination of Transmission Tariff for the period I. 7.20IO to 3I.3.201./ - Petition \\'OS heard and till that date respondent no. I had not raised any objection - Matter was reserved for judgment - Thereafter respondent no. I filed an affidavit stating that the line was not operational - CERC decided the tariff w.ej I. 7.2010 payable by beneficiaries - Appeal by respondent no. I - Tribunal remanded the matter accepting the plea of respondent no. l that since condition of trial operation and regulatory services were not fulfilled as such Commission erred in declaring tariff - On appeals, held: Switchgear and other works are part of transmission lines by virtue of its definition in s.2(72) - Switchgear at Barh end of Barh-Balia line for protection and metering were to be installed by NTPC and the same was not done by it when transmission line was completed by the appellant - As such the appellant might have suffered due to delay on the part of NTPC in completing the transmission lines for some period - But beneficiaries, including respondent No. 1, cannot be made liable to pay for this delay w.ej OI.07.2010 as the energy supply line had not started on said date and. beneficiaries could not be made liable to pay the tariff before transmission line was operational. Dismissing the appeals, the Court HELD: COD of transmission lines can he achieved only on fulfillment of following three conditions: The line has been charged 116 POWER GRID CORPORATION OF INDIA LTD. v. PUNJAB 117 STATE POWER CORPORATION LTD. successfully, its trial operation has been successfully carried out, A and it is in regular service. Switchgear and other works are part of transmission lines. Regulation 3(12) of the Regulations, 2009 cannot he interpreted against the spirit of the definition of "transmission lines" given in the statute. It is not a disputed fact that switchgear at Barh end of Barh-Balia line for protection and metering were to he installed by NTPC and the same was not done by it when transmission line was completed by the appellant. As such the appellant might have suffered due to delay B on the part of NTPC in completing the transmission lines for some period. But beneficiaries, including respondent no.I, cannot be made liable to pay for this delay w.e.f. 01.07.2010 as C the energy supply line had not started on said date. Meanwhile during the pendency of these appeals, in compliance of the interim order, after hearing all the concerned parties, C.E.R.C. has decided the matter on 30-06-2015, and transmission line has been now declared successfully charged w.e.f. 01-09-2011 and the D commercial operation has started on said date. However, the MΒ·der dated 30-06-2015 passed by C.E.R.C. is stated to be operative subject to decision of this Court in the present appeals, due to the interim order passed by this court. Respondent No. 1 and _the beneficiaries cou.Jd not have been made liable to pay the tariff before transmission line was operational, there is no infirmity in the impugned order. [Paras 7, 11, 12, 13) [120-H; 121-A-B, G- B; 122-A-D) CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9193 of2012 From the Judgment and Order dated 02.07.2012 of the Appellate Tribunal for Electricity, New Delhi in Appeal No. 123 of2011 WITH C.A. NO. 9302 OF 2012 E F C. A. Sundaram; Sr. Adv., M. G. Ramachandran, Pramod Dayal, G Nikunj Dayal, Ms. Paya! Dayal, Ms. Swana Shcshadri,Anand Ganesan, Advs. with him fortheAppellant. Subromonium Prasad, Sr. Adv., Abhay Kumar, Tenzing, Ashmit Singh, Pradeep Misra, Vishal Anand, Pukhrambam Ramesh Kumar, Sum it Kumar Vats, Advs., with him for the Respondents. H 118 SUPREME COURT REPORTS (2016] 2 S.C.R. A The Judgment of
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex