LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

POWER GRID CORPORATION OF INDIA LIMITED versus MADHYA PRADESH POWER TRANSMISSION COMPANY

Citation: [2025] 5 S.C.R. 2062 · Decided: 15-05-2025 · Supreme Court of India · Bench: J.B. PARDIWALA · Disposal: Appeal(s) allowed

cites 5 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2025] 5 S.C.R. 2062 : 2025 INSC 697
Power Grid Corporation of India Limited 
v. 
Madhya Pradesh Power Transmission Company  
Limited & Ors.
(Civil Appeal No. 6847 of 2025)
15 May 2025
[J.B. Pardiwala* and R. Mahadevan, JJ.]
Issue for Consideration
(i) Whether the CERC, while exercising its functions u/s.79(1) of 
the Electricity Act, 2003, is circumscribed by statutory regulations 
enacted u/s.178 of the Act, 2003; (ii) Whether the CERC exercises 
regulatory or adjudicatory functions u/s.79 of the Act, 2003. In 
other words, what is the scope of the CERC’s power to regulate 
inter-state transmission of electricity and determine tariff for the 
same under clauses (c) and (d) of s.79(1); (iii) Whether the grant 
of compensation by the CERC for the delay vide the orders 
dated 21.01.2020 and 27.01.2020 respectively, is a regulatory 
or adjudicatory function and to what extent are the principles 
of natural justice applicable to the exercise of such functions; 
(iv)  Whether the High Court was justified in admitting the writ 
petition filed by the respondent no. 1 herein challenging the order 
dated 21.01.2020 of the CERC when there existed an alternative 
remedy u/s.111 of the Act, 2003.
Headnotes†
Electricity Act, 2003 – ss.79, 178 – Relationship between ss.79 
and 178 of the Act, 2003:
Held: A perusal of the provisions laying down the functions of the 
CERC indicates that the statutory authority is enjoined with the 
task of regulation as well as adjudication of several aspects of the 
generation, transmission and distribution of electricity – S.79 of the 
Act, 2003 enumerates the functions of the CERC which includes 
the dual functions of regulation and adjudication – S.178, on the 
other hand, empowers the CERC to enact regulations by notification 
thereby delegating to the body, the power of legislating statutory 
regulations under the Act, 2003 – The aforesaid two provisions 
* Author
[2025] 5 S.C.R. 
2063
Power Grid Corporation of India Limited v. Madhya Pradesh  
Power Transmission Company Limited & Ors.
indicate that the CERC functions as both, decision-making and 
regulation-making authority u/ss.79 and 178 respectively – However, 
while the authority exercising both these functions is one and the 
same, it is a settled position of law that the functions by themselves 
are separate and distinct – The functions u/s.79 are administrative 
or adjudicatory whereas those u/s.178 are legislative – A regulation 
u/s.178 is of general application to the entirety of a particular subject 
matter as opposed to regulation on a case-to-case basis which may 
be done by the CERC u/s.79 – Therefore, making of a regulation 
u/s.178 has the effect of interfering with and overriding existing 
contractual relationships between the regulated entities – On the 
other hand, the orders u/s.79 have to be confined to the existing 
statutory regulations and do not have the effect of altering the 
terms of contract between the specific parties before the CERC. 
[Paras 37, 38, 40]
Electricity Act, 2003 – ss.79, 178 – The CERC vide its orders 
dated 21.01.2020 and 27.01.2020 respectively imposed the 
liability of payment of compensation for delay onto the 
respondent no. 1 – Correctness:
Held: It is the case of the respondent no. 1 that by doing so, the 
CERC did not act in conformity with the 2014 Tariff Regulations 
which do not provide for payment of transmission charges by a 
party to whom the delay is attributable – In considered view of this 
Court, the said argument does not hold any water – This Court’s 
dictum in PTC and Energy Watchdog respectively settles the law 
in this regard and the absence of a regulation u/s.178 does not 
preclude the CERC from exercising its powers u/s.79(1) to make 
specific regulations or pass orders between the parties before 
it.[Para 43]
Electricity Act, 2003 – s.79 – Regulatory and adjudicatory 
functions of the CERC:
Held: The regulatory powers provided to the CERC u/s.79 are of 
ad hoc nature and are required to be exercised by the CERC in 
context of the specific circumstances of the parties before it – The 
rationale for provision of such ad hoc powers by the Act, 2003 is 
to ensure that regulatory gaps, if any, that may be discovered on a 
case-to-case basis, are filled or removed – Therefore, there is no 
doubt that the CERC is enabled to exercise its regulatory powers 
by way of orders u/s. 79 and the purview of s.79 is not limited to 
2064
[2025] 5 S.C.R.
Supreme Court Reports
only adjudi

Excerpt shown. Read the full judgment & AI analysis in Lexace.