PARSA KENTE COLLIERIES LIMITED versus RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 728 SUPREME COURT REPORTS [2019] 8 S.C.R. PARSA KENTE COLLIERIES LIMITED v. RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LIMITED (Civil Appeal No. 9023 of 2018) MAY 27, 2019 [ARUN MISHRA AND M. R. SHAH, JJ.] Arbitration and Conciliation Act, 1996: s. 37 – Appeal under – Jurisdiction of the appellate court while considering the award passed by the arbitrator – Coal Mining and Delivery Agreement between the appellant and the respondent for supply of coal – Disputes between the parties, as regards the escalation price, fixed costs, amount lying in escrow account and cost of construction of railway siding – Award by arbitrator allowing the claims under the heads of ‘price adjustment’, ‘fixed costs’ and ‘escrow account’, however, rejected under the head ‘construction of railway siding’ – Award confirmed by the commercial court, however, set aside by the High Court – Justification of – On appeal, held: With respect to claim no.1-price adjustment/escalation, interpretation by the arbitrator was both possible as well as plausible – Merely because some other view could have been taken, the High Court was not justified in interfering with the interpretation –Though the High Court observed that the award passed by the arbitrator with respect to claim no.1 was against the public policy, but there was no element of public policy – High Court exceeded in its jurisdiction in interfering with the award passed by the arbitrator as regards claim no. 1 – With respect to claim no.2-fixed costs, the High Court rightly set aside the award passed by the arbitrator – Except the CA’s certificate, no further evidence had been led with respect to actual loss – On the contrary, in the relevant year the quantity of the coal lifted by the respondent was much above the fixed quantity – As regards, claim no.3-escrow account, the object and purpose of opening the escrow account was to see that the appellant company fulfils the contract as per the agreement and till the closure of the coal blocks – It was not open for the appellant to claim the amount lying in the escrow account, else the object of opening the escrow account would be frustrated – Thus, with respect to claim no.3- [2019] 8 S.C.R. 728 728 A B C D E F G H 729 escrow account, the High Court rightly held the reasoning is perverse or so irrational that no reasonable person could have arrived at on the material/evidence on record – Thus, the order passed by the High Court as regards claim no. 1 is set aside and the award passed by the arbitrator with respect to claim no.1 is restored and the order passed by the High Court setting aside the award with respect to claim no.2-fixed costs and claim no.3-escrow account is upheld. Partly allowing the appeal, the Court HELD: 1.1 So far as the claim with respect to “price adjustment/escalation” is concerned, the arbitrator held that the date of commencement of the first operating year for the purposes of clauses 5.2.2 read with 5.4.3 would be 25.06.2011 and therefore zero year for the purpose of price escalation has to be 2011-12. Accordingly, the arbitrator considered the escalated price in F.Y. 2013-14 at Rs.895/- per MT. However, according to the respondent, as the date of commencement was changed from 25.06.2011 to 25.03.2013, the zero year for the purpose of price escalation would be 2013-14. Price escalation is permissible under the contract/agreement itself and there shall be price escalation every year as per the formulae mentioned in the agreement, commencing from the date of commencement. However, it is true that the initial date of commencement, i.e., 25.06.2011 came to be extended to 25.03.2013 by mutual agreement. However, the same was due to force majeure as there was a delay of 21 months in obtaining the forest clearance and environmental clearance. The price was quoted in the year 2007-08, applicable from 2011. However, there was a delay in obtaining the forest clearance and environmental clearance and therefore the date of commencement of supply came to be changed. In between there would be hike in labour charges, transportation charges, etc. Though the date of commencement of supply was extended, there was no corresponding amendment in the relevant clauses of the agreement with respect to price escalation. There was no specific agreement that in the year 2013, the appellant would supply the coal at the same price, without any price escalation. Therefore, considering the overall facts and circumstances of the case and by
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex