LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

PAM DEVELOPMENTS PRIVATE LIMITED versus THE STATE OF WEST BENGAL & ANR.

Citation: [2024] 8 S.C.R. 615 · Decided: 23-08-2024 · Supreme Court of India · Bench: PAMIDIGHANTAM SRI NARASIMHA

Cited by 4 judgment(s) · cites 15 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 8 S.C.R. 615 : 2024 INSC 628
Pam Developments Private Limited 
v. 
The State of West Bengal & Anr.
(Civil Appeal Nos. 9781-9782 of 2024)
23 August 2024
[Pamidighantam Sri Narasimha* and Pankaj Mithal, JJ.]
Issue for Consideration
Matter pertains to the arbitral award in favour of the contractor 
as regards labour charges for uneconomical stoppage of work, 
interest on delayed payment, and interest, upheld by the District 
Judge but set aside/modified by the High Court. 
Headnotes†
Arbitration and Conciliation Act, 1996 – ss. 34 and 37 – Arbitral 
awards – Work contract – Claims raised by the contractor under 
different heads alleging delays on the part of the State, referred 
to the arbitrator – Arbitral award in favour of the contractor 
under heads-loss of business, uneconomic utilization of plant 
and machinery, labour charges for uneconomical stoppage of 
work, interest on delayed payment, escalation bill, interest and 
costs – Award challenged by the State, whereby the District 
Judge set aside few of the claims – High Court modified the 
award – Interference with: 
Held: Decision of the High Court setting aside the award with 
respect to claim as regards labour charges for uneconomical 
stoppage of workup held since the arbitrator did not even refer to 
the contractual provisions which prohibited such claim – Judgment 
of the High Court setting aside claim of interest on delayed payment 
awarded by the Arbitrator, as upheld by the District Judge u/s. 34 is 
set aside since nothing perverse in the reasoning of the Arbitrator 
and nor such conclusion against public policy – Judgment of 
the High Court in so far as it modified claim as regards interest, 
to the extent of rejecting pre-reference interest awarded by the 
arbitrator, as upheld by the District Judge u/s. 34 is set aside since 
the High Court had no reason to interfere with the Arbitral Award 
with respect to grant of pre-reference interest, since the contract 
* Author
616
[2024] 8 S.C.R.
Digital Supreme Court Reports
between parties does not prohibit the same – Award as regards 
labour charges for uneconomical stoppage of work set aside and 
award as regards interest on delayed payment is upheld – As 
regards the claim of interest, the appellant entitled to claim pre-
reference interest. [Para 10]
Arbitration and Conciliation Act, 1996 – Work contract – 
Arbitration proceedings – Contractual clauses – Interpretation 
of – Claim relating to loss caused due to idle labour, machinery – 
High Court held that the said claim is impermissible under 
the contractual provisions – Correctness:
Held: Contract clauses speak for themselves – High Court did 
what the Arbitrator should have done and examined what the 
contract provides – This is not even a matter of interpretation – It 
is the duty of every arbitral tribunal and court alike and without 
exception, for contract is the foundation of the legal relationship – 
High Court came to the conclusion that awarding any amount 
towards idle, machinery, etc. is prohibited under the ‘Special Terms 
and Conditions’ of the Contract – Arbitrator did not even refer to 
the contractual provisions and the District Court dismissed the 
objections u/s. 34 with a standard phrase – High Court exercising 
jurisdiction u/s 37 did its duty and the conclusions of the High 
Court are correct and cannot be interfered with. [Paras 7, 7.3-7.5]
Arbitration and Conciliation Act, 1996 – ss. 34, 37 – Dispute 
relating to work contract – Arbitral award – Arbitrator awarded 
interest on delayed payment of running account bills – Upheld 
by the District Court – However, the High Court set aside the 
award – Challenge to:
Held: Conclusion of the High Court, that it appears that the bills 
were paid soon after they were prepared or that, in that case 
there could not have been any claim for interest cannot qualify 
as grounds for interference u/s 37 – Equally, the approach of 
the High Court in holding that the Arbitrator neither established 
nor discussed the questions posed by it, not a ground to set 
aside the Award – Reasoning of the Arbitrator is reflected in that 
portion of the Award and nothing perverse is seen in it – Nor 
such conclusion is against the public policy – Judgment of the 
High Court in relation to the said claim set aside and the Award 
is restored. [Paras 8.5, 8.6]
[2024] 8 S.C.R. 
617
Pam Developments Private Limited v. The State of West Bengal & Anr.
Arbitration and Conciliation Act, 1996 – ss. 34, 37 – D

Excerpt shown. Read the full judgment & AI analysis in Lexace.