OSWAL WOOLEN MILLS LTD. versus PUNJAB STATE ELECTRICITY BOARD & ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B OSWAL WOOLEN MILLS LTD. v. PUNJAB STA TE ELECTRICITY BOARD & ANR. APRIL 28, 2006 [S.B. SINHA AND P.K. BALASUBRAMANY AN, JJ.] Electricity (Supply) Act. 1948-Sections 46 & 49-Supply to industrial consumers-State Electricity Board issued circular stipulating levy of C surcharge on consumption of electricity till the consumers switched over their supply system to higher voltage-Challenge to-Held: Electricity Board being a statutory authority was entitled to levy surcharge only in terms of tariff notification issued under the Act and not by reason of any circular. State Electricity Board issued circular dated 2l.l.1991 stipulating levy D of surcharge @ I 7Yz% on actual consumption of electricity in respect of industrial consumers having supply from a 11 KV line till such consumers switched over their supply system to 33 KV or higher voltage. On 03.5.1991, vide another circular, the Board issued a clarification allowing exemption from surcharge for a period of one year to enable all its existing consumers to switch over their supply system to higher voltage. E The entire controversy in the present set of cross-appeals by a consumer company (mill) and by the Board is as to from what date the period of one year should be calculated. Applicability or otherwise of the tariff notification issued under Sections 46 and 49 of the Electricity (Supply) Act, 1948 which provided F for revision oftariffw.e.f. 01.02.1994 is also in question. Disposing of the cross-appeals, the Court HELD: I.I. The Board is a creature of the statute. It is constituted in terms of Section 5 of the Electricity (Supply) Act, 1948. Section 46 of the Act provides for the Grid Tariff and Section 49 thereof empowers the Board to G make provision for the sale of electricity by it to persons other than the licensees. While exercising the said power the Board would be governed by the general terms which may be issued by the State in terms of Section 79 of the Act. [ 487-CJ H 480 OS WAL WOOLEN MILLS LTD. v. PUNJAB STA TE ELECTRICITY BOARD 481 1.2. The Board being a statutory authority, its power to issue bills for A consumption of the electricity would be governed solely by the tariff notification. Such a power can be exercised by the Board only in exercise of its statutory power and not by reason of an executive power. In terms of a circular letter issued by the Board, therefore, neither any surcharge nor any penalty could be levied. Surcharge by way of additional rate or penalty can be B levied only in terms of a tariff notification. [487-G, DJ 2. The tariff notification dated 26.07.1991 speaks of levy of such surcharge inter alia on Arc furnaces. Similar is the position in regard to the notification dated 01.02.1994. As in the notification, it has clearly been stated that l 7Y. % surcharge on the above tariff should be leviable for all the C Arc furnace load consumers which were being given the supply at 11 KV, the High Court clearly fell in error in arriving at the finding that by reason of the said notification, the circular letters dated 21.01.1991 and 03.05.1991 were not superseded. The High Court failed to pose unto itself the correct question, namely, as to whether after issuance of the tariff notification, the Board could levy any surcharge@ 17Y.% on the tariff on those consumers D who did not have Arc Furnace. (487-F-G; 488-A, BJ 3.1. The question which falls for consideration is from which date the period of one year could have started. Although the company could have contended that from 03.05.1991, no surcharge could have been levied, but it E did not raise such a contention before the High Court. Herein also a limited notice was issued. (488-C) 3.2. The High Court by its order dated 29.01.1992 stated that the period of one year would start from the date when the feasible point for installation of 33KV or higher voltage sub-Station at the factory premises by the Board F was pointed out. But selection of a site for the purpose of drawing 33KV line was not an empty formality. Several factors including the convenience of the Board were required to be taken into consideration. In some cases probably compensation for acquisition of land was required to be paid. The High Court's observations might be incorrect; but then the same was accepted and the parties acted thereupon. [488-H; 489-A, BJ G 3.3. All the Courts below had arrived at a finding of fact, having regard to the Board's le
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex