LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

OPG POWER GENERATION PRIVATE LIMITED versus ENEXIO POWER COOLING SOLUTIONS INDIA PRIVATE LIMITED & ANR.

Citation: [2024] 9 S.C.R. 490 · Decided: 20-09-2024 · Supreme Court of India · Bench: D.Y. CHANDRACHUD · Disposal: Dismissed

Cited by 1 judgment(s) · cites 29 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2024] 9 S.C.R. 490 : 2024 INSC 711
OPG Power Generation Private Limited 
v. 
Enexio Power Cooling Solutions India Private 
Limited & Anr.
(Civil Appeal Nos. 3981-3982 of 2024)
20 September 2024
[Dr. Dhananjaya Y. Chandrachud, CJI, 
J.B. Pardiwala and Manoj Misra,* JJ.]
Issue for Consideration
Issue arose as to whether the arbitral award is in conflict with the 
public policy of India, or/and is vitiated by patent illegality appearing 
on the face of the award; whether the holding company could 
have been subjected to arbitration and made jointly and severally 
liable along with the project beneficiary-appellant for the award; 
whether respondent’s claim for the outstanding principal amount 
barred by limitation; whether the counter claim, in respect of cost 
of repair/replacement of gear boxes and fan modules, could be 
treated as barred by time when the other side’s claim, arising out of 
same contractual relationship, was found within limitation; whether 
arbitral award for payment of the outstanding principal amount with 
interest is perverse; whether the reasoning of the arbitral tribunal 
is flawed and vitiated by adopting different yardstick for adjudging 
the counterclaim than what was adopted for adjudging the claim; 
if so, whether it vitiated the award and rendered it vulnerable to 
a challenge u/s. 34 of the Arbitration and Conciliation Act, 1996.
Headnotes†
Arbitration and Conciliation Act, 1996 – s. 34(2)(b)(ii) – Arbitral 
Award – Challenge to – Arbitral award, if in conflict with 
the public policy of India, or/and vitiated by patent illegality 
appearing on the face of the award – Appellant company floated 
composite tender for design, manufacture and commissioning 
of an air-cooled condenser unit, however, supply and 
erection orders issued by its holding company – Appellant 
later confirmed those orders – Respondent had bid for the 
project – Dispute between parties as regards declaration qua 
invalidity of debit notes, outstanding principal amount and 
* Author
[2024] 9 S.C.R. 
491
OPG Power Generation Private Limited v.  
Enexio Power Cooling Solutions India Private Limited & Anr.
interest – Respondent invoked arbitration – Arbitral award 
passed an award in favour of the respondent, holding that 
the holding company and appellant jointly and severally 
liable; that declaratory relief sought by respondent qua debit  
notes-towards liquidated damages and customs duty beyond 
the period of limitation, however, claim for unpaid dues payable 
under the contract within the period of limitation – Single 
Judge of the High Court set aside the award, however the 
Division Bench restored the same – Justification:
Held: Division Bench of the High Court justified in setting aside 
the judgment and order of the Single Judge and restoring the 
arbitral award – No palpable error in the arbitral award as to be 
termed ‘patently illegal’/‘perverse’, or in conflict with public policy 
of India – Though the ACC Unit /project was of the appellant, 
the holding company of the appellant actively participated in the 
formation of the contract for the project – They not only acted as 
a single economic entity but as agents of each other – Hence, 
the arbitral tribunal justified in holding that holding company was 
bound by the arbitration agreement and jointly and severally liable 
along with appellant to pay the awarded amount – Claim of the 
respondent was an indivisible claim for compensation in lieu of 
goods supplied, and work done, based on breach of the contract, 
thus limitation for the claim governed by Art. 55, and not by Arts. 
14, 18 and 113, of the Schedule to the 1963 Act – Claimant’s claim 
for the outstanding principal amount matured on 19 March 2016, 
thus, limitation started to run from that date – However, even if 
limitation is counted from 21 September 2015, deemed date of 
completion of the supply/work (as found by the tribunal) it would 
have no material bearing on the award – Limitation for the claim 
as well as counterclaim, other than those relating to cost of repair/
replacement of gear boxes and fan modules, stood extended, 
u/s. 18 of the 1963 Act, on the basis of acknowledgement made 
in the minutes of meeting, and, thus, those were within limitation 
and rightly considered on merit – Counterclaims qua cost of 
repair /replacement of gear boxes and fan modules rightly held 
barred by time as in respect thereof there was no recital in the 
minutes of meeting – Rejection of prayer to declar

Excerpt shown. Read the full judgment & AI analysis in Lexace.