NBCC (INDIA) LIMITED versus SHRI RAM TRIVEDI
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 280 SUPREME COURT REPORTS [2021] 2 S.C.R. [2021] 2 S.C.R. 280 280 NBCC (INDIA) LIMITED v. SHRI RAM TRIVEDI (Civil Appeal No 274 of 2020) MARCH 08, 2021 [DR. DHANANJAYA Y CHANDRACHUD AND M. R. SHAH, JJ.] Consumer Protection: Allotment of residential unit by builder β Clause 20 of the allotment letter stipulated for handing-over of the unit in two and half years and for compensation at the rate of Rs. 2 per sq. feet of the unit per month for the period of delay beyond one year form the stipulated date β Failure to hand-over the possession within the time agreed upon β Consumer complaint β Consumer Commission directed the builder to pay compensation with 10% interest pa. on the amount deposited by the complainant from June 2015 till actual date of possession i.e. on July 26, 2018 β Consumer Court also awarded an amount of Rs. 2 lakhs towards loss of rent and Rs.25,000/- as costs β Appeal to Supreme Court β Held: The compensation @ Rs. 2/- per sq.ft. was one sided and constitutes an unfair trade practice β As per clause 20 of allotment letter, the builder was required to hand-over the possession within three and half years (including extention due to force majeure) which came to an end by the end of December 2015 β Therefore, the interest would become payable from January 1, 2016 β In the light of prevailing market conditions, rate of interest @ 10% pa. is excessive and therefore, the rate is fixed at 7% pa. β Also, there was no justification to award an amount of Rs. 2 lakhs, once interest for delayed handing- over of possession was granted β Order of Consumer Commission modified. Words and Phrases: βendeavourβ β Meaning of. Partly allowing the appeal, the Court HELD: 1. Clause 20 of the letter of allotment provides that the appellant shall βendeavourβ to complete the construction of A B C D E F G H 281 the dwelling unit within two and a half years from the date of the letter of allotment. The expression βendeavourβ meant that the appellant would make an earnest effort to hand over possession by that date. Even if the expression does not mean an absolute commitment to hand over possession on or before a specified date, this expression has to be read in the context of the entirety of the clause. To construe the expression as leaving the date for handing over possession indefinite and at the absolute discretion of the developer would leave the purchaser at the mercy of the builder. Clause 20 must be construed to require the builder to make all reasonable efforts to comply with the duty to hand over possession by the stipulated date. The burden would lie on the developer to explain the steps taken to comply with the contractual stipulation. Clause 20 envisages that, save and except for delay on account of force majeure, the appellant would pay compensation at the rate of Rs 2 per sq ft of the super area of the dwelling unit per month for the period of delay beyond one year from the stipulated date. It stipulates that compensation would be payable after four years (plus a valid extension due to force majeure) from the date of allotment. The above condition would indicate that beyond a period of one year, from the expiry of two and a half years, which was envisaged under Clause 20, the appellant agreed to pay compensation to the flat buyer. The latter stipulation of four years is incongruous, because previously, a period of one year beyond the stipulated period of 2.5 years is fixed, beyond which compensation becomes payable. This indicates that three and a half years was by all accounts the period for handing over possession beyond which the purchaser was entitled to compensation. [Para 7][287-A-F] 2. The NCDRC was justified in taking the view that the condition in the allotment of payment of compensation at the rate of Rs 2 per sq ft is one-sided and constitutes an unfair trade practice. The letter of allotment is in a standard form. The purchaser has no option but to sign on the dotted line. On the other hand, under Clause 16, if the buyer were to delay in the payment of any instalment, a liability to pay simple interest at the rate of 12% per annum is attracted. Clause 20, in other words, is NBCC (INDIA) LIMITED v. SHRI RAM TRIVEDI A B C D E F G H 282 SUPREME COURT REPORTS [2021] 2 S.C.R. not even-handed. While, on the one hand, it contemplates only compensation at the rate of Rs 2 per sq ft in the event that there is a delay on the part of the appellant, the buyer is required to pay a substantially hi
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex