NATIONAL HIGHWAY AUTHORITY OF INDIA versus TRANSSTROY (INDIA) LIMITED
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 948 SUPREME COURT REPORTS [2022] 6 S.C.R. NATIONAL HIGHWAY AUTHORITY OF INDIA v. TRANSSTROY (INDIA) LIMITED (Civil Appeal No. 6732 of 2021) JULY 11, 2022 [M. R. SHAH AND SANJIV KHANNA, JJ.] Arbitration and Conciliation Act, 1996: s. 23(2A) β Statements of claim and defence β Contract between appellant (NHAI) and the respondent company β Dispute between the parties referred to the arbitrator β Application u/s. 23(2A) by the appellant to permit them to place on record its counter claim β Rejection of, by the tribunal as also the High Court β On appeal, held: When there is a provision for filing the counter claim-set off, which is expressly inserted in s. 23, there was no reason for curtailing the right of the appellant for making the counter claim or set off β If the counter claim made by the appellant is not allowed in the proceedings arising out of the claims made by the respondent, it may lead to parallel proceedings before various fora β It would defeat the object and purpose of permitting to file the counter claim/set off as provided u/s. 23(2A) β Furthermore, the appellant reserved its right to claim the damages and even in the Statement of Defence also claimed such a set off of Rs.1.23 crores β Thus, the High Court on a narrow interpretation of Clause 26 of the Contract erred in rejecting the application β Order passed by the arbitral tribunal and the High Court quashed and set aside. Allowing the appeal, the Court HELD: 1.1 It is not open for the Contractor to contend that the counter claim was without following the procedure as required in Clauses 26.1 and 26.2 of the Contract Agreement and, therefore, may not be taken on record. On a true and fair interpretation of Clause 26, failure to resolve the dispute (in the present case, the termination of the Contract by the NHAI), the arbitration proceedings would be maintainable. That does not mean that only a claim and/or counter claim as sought to be contended on behalf of the Contractor now would alone be entertained. [Para 13][966-D-E] [2022] 6 S.C.R. 948 948 A B C D E F G H 949 1.2 Both the Arbitral Tribunal as well as the High Court have failed to appreciate the difference between the expressions βclaimβ, which may be made by one side and βDisputeβ, which by its definition has two sides. [Para 13.1][966-E-F] 1.3 Even the Arbitral Tribunal while rejecting the application of the NHAI for extension of time to file the counter claim did not observe and/or rejected the application for extension of time to file the counter claim on the ground that the said counter claim would not be maintainable without following the process as required under Clause 26 of the Contract agreement. [Para 13.2][966-G] 1.4 When the NHAI filed the application under sub-section (2A) of Section 23 of the Arbitration Act, 1996 seeking to place on record its counter claim, Arbitral Tribunal rejected the said application by observing that in the application for permitting the NHAI to place on record the counter claim, the NHAI did not stated anything about having made an attempt for such amicable settlement. However, it is required to be noted that from the very beginning, the NHAI reserved its right to claim the damages and even in the Statement of Defence also claimed such a set off of Rs.1.23 crores and also specifically stated therein that the NHAI reserved its right to file the counter claim. Therefore, on the grounds on which the Arbitral Tribunal rejected the application of NHAI to place on record the counter claim can be said to be contrary to the intent between the parties to resolve the dispute (which was for termination of the Contract by the NHAI) through conciliation first. In the facts and circumstances of the case, by such a narrow interpretation, the Arbitral Tribunal has taken away the valuable right of the NHAI to submit counter claim, which is of a very huge amount thereby negotiating the statutory and contractual rights of the NHAI and paving way for a piecemeal and inchoate adjudication. [Para 13.3][968-F-H; 969-A-C] 1.5 When there is a provision for filing the counter claim- set off, which is expressly inserted in Section 23 of the Arbitration Act, 1996, there is no reason for curtailing the right of the appellant for making the counter claim or set off. If the counter NATIONAL HIGHWAY AUTHORITY OF INDIA v. TRANSSTROY (INDIA) LIMITED A B C D E F G H 950 SUPREME COURT REPORTS [2022] 6 S.C.R. claim made by the NHAI in the proceedings arising out of the cla
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex