LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

NATIONAL HIGHWAY AUTHORITY OF INDIA versus M/S. PROGRESSIVEMVR (JV)

Citation: [2018] 2 S.C.R. 1015 · Decided: 23-02-2018 · Supreme Court of India · Bench: A.K. SIKRI · Disposal: Appeal(s) allowed

cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A
B
C
D
E
F
G
H
1015
NATIONAL HIGHWAY AUTHORITY OF INDIA
v.
M/S. PROGRESSIVEMVR (JV)
(Civil Appeal No. 458 of 2018)
FEBRUARY 23, 2018
[A. K. SIKRI AND ASHOK BHUSHAN, JJ.]
Contract – NHAI Contracts – Price adjustment formula, ‘note’
appended thereto – Interpretation of – Respondents-contractors
awarded contracts by appellant-NHAI for construction of roads
etc. – Tender document envisaged a ‘Price Adjustment formulae –
Sub-clause 70.3 of the Contract provided for the ‘adjustment
formulae’ for calculating the price adjustment amount wherein the
work is divided into seven components for which specific
percentages were given to govern the price adjustment– However,
such specific percentages were given only for 4 components, and
for rest three components i.e. bitumen, cement and steel, variable
percentages were given as  x%, y%, z% which were to be worked
out – ‘Note’ after sub-para (xi) of sub-clause 70.3 mentioned that
x, y, z were the actual percentage of the cost of material of bitumen,
cement and steel respectively which were used for execution of the
work – Dispute between parties as to basis for calculation of actual
percentage of cost of material of bitumen – Plea of NHAI that base
rate (i.e. the rate prevailing 28 days prior to the submission of the
bid) of these materials should be considered while applying the
formula – Respondents contended that it is the prevailing rate in
that particular month which would be the determining factor –
Dispute Review Board (DRB) held in favour of NHAI – Respondents
invoked arbitration – Arbitration Tribunal allowed the claim – NHAI
filed objections u/s.34, 1996 Act before High Court – Objections
dismissed by High Court – On appeal, held: Clause relating to price
adjustment indicates that certain components which go into the
execution of the projects like labour component, cement component,
steel component, plant and machinery and spares component,
bitumen component etc. may not remain static insofar as their price
is concerned – There is a possibility that from the date when the
price of these components was quoted by the contractor in his bid,
there may be increase or decrease in the said price from time to time
[2018] 2  S.C.R. 1015
1015
A
B
C
D
E
F
G
H
1016
SUPREME COURT REPORTS
[2018]  2 S.C.R.
during the execution of the contract – Towards this, adjustment
formula for working out the cost, at the time of execution of the
contract, is provided – This adjustment has to be arrived at, in
comparison with the base price/rates referred by the contractor/
bidder – Thus, while applying price adjustment formula for
calculating the price adjustment of bitumen, it is the base rate which
is to be applied and not the current rate – Arbitration and
Conciliation Act, 1996 – s.34.
Allowing the appeals, the Court
HELD: 1.1 Clause 70 of Conditions of Particular Application
(COPA) of the contract pertains to price adjustment. Clause
70.3(v) deals with ‘Adjustment for Bitumen Component’. As per
this clause, the price adjustment for increase or decrease in the
cost of bitumen is to be paid in accordance with the following
formula:
“ Vb=0.85 x Pb/100 x R1 x (Bi – Bo)/Bo”
Vb is increase or decrease in the cost of work during the month
under consideration due to changes in the rate of bitumen. Pb
denotes percentage of bitumen component of the work and R1 is
the total value of the work.  Bi denotes current rate/cost as it is
the average official retail price of bitumen at IOC Depot at
Barauni/Haldia on the day 28 days prior to the submission of bids,
which makes it clear that it is equivalent to the base rate.  Thus,
when this formula is considered of its own, Bo clearly refers to
the base rate. [Paras 14-16] [1029-E-F, G-H; 1030-F-G, G]
1.2  Pb = X% is calculated by NHAI by following
mathematical formula:
“Pb = Quantity of Bitumen consumed during the month x base
rate of bitumen x 100
 Total Work done during the month of x BOQ rates.”
[Para 18]  [1031-B-C]
1.3 The issue relates to price adjustment and such an
adjustment can be made in respect of various components which
are used in the contract. The contractual provisions specifically
deal with adjustment for labour component, cement, steel etc.
These components are seven in numbers which may undergo
A
B
C
D
E
F
G
H
1017
price adjustment during the period when the contract is in
progress, depending upon the market conditions, namely,
increase or decrease in market prices of these components from
time to time. The very nature of this price adjustme

Excerpt shown. Read the full judgment & AI analysis in Lexace.