NATIONAL FERTILIZERS versus PURAN CHAND NANGIA
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A NATIONAL FERTILIZERS v. PURAN CHAND NANG IA OCTOBER 17, 2000 B [M. JAGANNADHA RAO AND K.G. BALAKRISHNAN, JJ.) Arbitration : Works contract-Acceptance of tender-Applicability of quoted rates C for a variation upto ยฑ 25% of contract value and higher market rates beyond the variation-Claim for higher rates-Arbitrator awarding 50% of higher rates-Jurisdiction of arbitrator-Held, on facts, there is no error of law in the award of the arbitrator. D Works contract-Changes in terms of contract-Held, the terms of contract cannot be altered unilaterally to the detriment of opposite party. Appellant-company invited quotations for works amounting to Rs. 3,39,88,000. The quotation of respondent-contractor was accepted and was given 48% of the work only. The work order issued by the appellant consisted E a clause stating that the quoted rates of the respondent is applicable for a variation upto ยฑ. 25% of contract value beyond which higher market rates would be applicable. Original date of completion of work was extended by 4 months. The respondent submitted a final bill at higher rates since the variations went above 25% of the contract value. The appellant, besides holding F the respondent for delay in completion of work, rejected the bill stating that the higher rates is justified only if the total contract value of the work has increased or decreased by 25% and not on account of any increase or decrease in the quantity of individual items. Further, the appellant made a cross-claim from the respondent for compensation of Rs. 7.64 lakhs on account of delay in completion since another contractor had to be appointed for completing G the work. On reference of the disputes to arbitration, arbitrator gave a non- speaking award. The arbitrator awarded 50% of the.extra claim to the respondent and rejected the claim of the appellant for compensation. On appeal Trial Court set aside the award of the arbitrator on the ground that the reference was bad and gave alternative finding!'. High Court, allowing the appeal of the respondent, held that the reference was maintainable and directed H 26 .โข NA TI ON AL FERTILIZERS v. PU RAN CHAND NANG IA 27 that the award be made a Rule of Court. A In appeal to this Court, the appellant contended that tlie arbitrator acted beyond his jurisdiction in granting higher rates for the work done upto the extended date, which was contrary to the work order issued; that the higher rates are applicable only if the net difference between the increases and decreases works out to more than 25% of the contract value; that the variation B limit ofยฑ25% of the contract price was applicable on the total contract price and not on individual quantities or items; and that the award by the arbitrator at a flat rate of 50% of the extra claim is contrary to the terms and conditions of the tender. The respondent contended that if the sum total of the variations, both C plus and minus, exceeded 25%, the market rates are applicable; and that the Trial Court has found as a finding, that the sum total of the additions and deletions in the work exceeded l 00%. Dismissing the appeal, the Court D HELD: 1.1. The concept of variation of the question of work is a common feature of works contracts. This is because in contracts relating to major works, the estimates of work at the time of inviting the tenders can only be approximate. But the power of the employer to vary the terms relating to the quantum of work cannot be unlimited. Under the general law of Contracts, E . once the contract is entered into, any clause giving absolute power to one party to override or modify the terms of the contract at his sweet will or to cancel the contract - even if the opposite party is not in breach - will amount to interfering with the integrity of the contract. f35-E; 36-BJ 1.2. The variation clause was understood by the arbitrator in a F reasonable manner as being applicable to a case where the value of the sum total of the additions and deletions exceeded 25% of the contract price. That construction cannot be said to be vitiated by any serious error of law. When a contractor bids in a contract, he has to offer reasonable rates for the works which are both difficult to perform and others works, which are not difficult G to perform. Every contractor tries to balance his rates in such a manner that the employer may consider his offer reasonable. In that process the contractor
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex