LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

MOTILAL JAIN versus SMT. RAMDASI DEVI AND ORS.

Citation: [2000] SUPP. 1 S.C.R. 615 · Decided: 20-07-2000 · Supreme Court of India · Bench: S.S.M. QUADRI · Disposal: Appeal(s) allowed

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

MOTILAL JAIN 
v. 
SMT. RAMDAS[ DEVI AND ORS. 
JULY 20, 2000 
[SYED SHAH MOMAMMED QUADRI 
AND SHIVARAJ V. PATIL, JJ.) 
Specific Reliefs Act, 1963: Sections 9, 16 (c) and Section 21-Agreement 
A 
B 
to sell entered between the plaintiff and the defendant-Two-third payment C 
made at the time of entering into the agreement-Balance one-third to be 
paid at the time of execution of the sale deed-Defendant avoided acceptance 
of balance payment and execution of sale deed-Plaintiff sent three legal 
notices followed by a suit for specific performance and compensation in the 
alternative-Suit decreed for specific performance in favour of the p/aintifJ-
ln appeal, High Court set aside the decree for specific relief granting a D 
decree for compensation on the ground of delay in filing the suit; lack of 
readiness and willingness of the plaintiff to perform the contract and claim 
of compensation in the alternative-On appeal, Held: Ground of delay cannot 
be invoked as the last legal notice was sent to the defendant after around 
21 months and suit was filed after 9 months only i.e. not more than a year-
Averment of readiness and willingness in the plaint is not a mathematical E 
formula and need not be in specific words-Paras 6 and 11 of the plaint 
clearly indicated readiness and willingness of the plaintiff-Plaintiffs having 
parted with two-thirds of the consideration is evident of the fact that he 
would part with the balance one-third also-Mere claim of damages in 
alternative cannot bar the main relief 
F 
In 1977, the plaintiff entered into a contract with the defendant to 
purchase the suit property for a sum of Rs. 25,000. The plaintiff paid Rs. 
17,000 to the defendant vendor at the time of the execution of the contract i.e. 
in the month of February, 1977 whereas the balance amount of Rs. 8,000 was 
to be paid within next ftve months i.e. at the time of execution of the sale deed. G 
When the defendant evaded receiving the balance amount of Rs. 8,000 and 
execution of the sale deed, the plaintiff sent three notices to the defendant 
through his Advocate in the month of March, April and November, 1978. 
Later the plaintiff filed a suit for specific performance against the defendant 
and in the alternative claimed Rs. 38,000 as damages. The defendant denied H 
615 
616 
SUPREME COURT REPORTS [2000] SUPP. I S.C.R. 
A execution of the agreement to sell altogether including his signature on it 
and receipt of Rs. 17,000 as part-consideration. Trial court decreed the suit 
for specific performance holding that the defendant had executed the contract. 
In appeal, High Court confirmed the finding of the trial court as to the 
execution of the contract but set aside the relief of specific performance 
B granting a decree for compensation in the sum of Rs. 22,094. It held that the 
suit was filed two years after the accrual of cause of action and after about a 
year of sending of last legal notice; readiness and willingness of the plaintiff 
could not be inferred from the plaint and even assuming that the readiness 
and willingness was there, there was no evidence to prove such readiness and 
willingness. Hence, this appeal. 
c 
The appellant contended that there was no delay justifying denial of the 
relief of specific performance; there were averments in the plaint showing 
readiness and willingness and that under Section 16 (c) of the Specific Relief 
Act the plaint need not be in Forms 47 and 48 in Appendix A to Code of Civil 
Procedure. The respondent contended that para Nos. 6 & 11 of the plaint did 
D not conform to Forms 47 and 48 of the First Schedule to the CPC; and that 
the trial court ought to have framed an issue regarding readiness and 
wiilingness of the appellant. 
Allowing the appea~ the Court 
E 
HELD: I. The following aspects of delay are relevant in a case of specific 
performance of contract for sale of immovable property : (i) Delay running 
beyond the period prescribed under the Limitation Act; (ii) Delay in cases 
where though the suit is within the period of limitation, yet : (a) due to delay 
the third parties have acquirยทed rights in the subject matter of the suit; (b) in 
the facts and circumstances of the case, delay may give rise to plea of waiver 
F or otherwise it will be inequitable to grant a discretionary relief. Here none 
of the above mentioned aspects applies. That apart factually also, the High 
Court proceeded on an incorrect assumption with regard to cause of action. 
The agreement t

Excerpt shown. Read the full judgment & AI analysis in Lexace.