MCDERMOTT INTERNTIONAL INC. versus BURN STANDARD CO. LTD. AND ORS.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
MCDERMOTT INTERN A TI ON AL INC. v. BURN STANDARD CO. LTD. AND ORS. MAY 12, 2006 [B.P. SINGH AND S.B. SINHA, JJ.] Arbitration and conciliation Act, 1996: Sections 31, 33 and 34-Partial award made by deferring some claims-Nature and character of-Held: It is same as of interim award envisaged in the Act, even though expression "partial award" is not used therein-If it answered definition of award under Section 2(c), for all intent and purport, it would be a final award-It is not akin to a preliminary decree-It is final in all respects with regard to disputes referred to arbitrator which are subject matter of such award-By such an award no prejudice is caused as both partial and final awards are subject matter of challenge under Section 34-Additional award is not vitiated in law, especially keeping in view powers of arbitral tribunal under Section 33. Section 16-Plea that a claim was arbitrary or beyond its authority-- Held: It has to be raised before arbitrator. Contract-Construction of-Held: It is within jurisdiction of arbitrators even if it gives rise to determination of a question of law-In this regard conduct of parties and correspondences exchanged by them are relevant factors. Denial of claim-Held-Jn every case claim is not required to be followed_ by denial-If a matter is referred to any arbitrator within a reasonable time, the party invoking the arbitration clause may proceed on the basis that the other party to the contract has denied or disputed his claim or is not otherwise interested in referring the dispute to the arbitrator. Parties to arbitration-:-Reduction of claim of party to contract by one who was not party to it-Held: Latter was involved in the matter and had a direct nexus with claim of former. Contract Act, 1872: 409 A B c D E F G H 410 SUPREME COURT REPORTS (2006] SUPP. 2 S.C.R. A Section 55-Time being essence of construction contract-Specific date B c D E for performance set by contract at time when it was entered into-Notice invoking arbitration agreement therein served much after expiry of those dates-Held: Service of notice would not mean that party repudiated the contract as soon as schedule fixed by contract expired-Delay and disruptions might have occurred for various reasons-Parties did not intend time to be of essence of contract as (i) contract itself provided for extension of time and payment of damages in case of delay in execution of contract (ii) party claiming that time was of essence did not raise that plea before the Arbitrator (iii) contract being a construction contract wherein generally time was not essence unless special features existed therefor, which in facts of the case were not brought to notice of Court. Sections 55 and 73-Quantification of claim for damages-Held- Amount for damages is not required to be quantified as that is merely a matter of proof-Different formulas for quantification can be applied in different circumstances--Formulae evolved over the years and accepted internationally can be adopted as that is neither prohibited nor inconsistent with Indian law-However, court or arbitrator may insist on some proof of actual damages, and may not allow the parties to take recourse formula- One formula may be preferred as against ano!her--Jn facts of the case, choice of formula by arbitrator not interfered by Court-Section 16 of Arbitration and Conciliation Act, 1996. Section 7 3-Claim for damages for breach of contract--Held: Invoice is not the only base where under such claim be made as it is drawn only in respect ofa claim made in terms of contract-Claim for breach of contract F can be made through correspondence or in meetings-Jn facts of the case, held that the claim for overhead costs resulting in decrease in profit or additional management costs was a claim for damages, and it could be claimed in arbitration proceedings without invoice being drawn for it. G Section 73---Consequential damages-}vfain contract providing that neither of parties thereto were liable to other for such damages--Applicability to sub-contract with one of those parties with another party-Held: Main contract was a matter of an agreement between parties thereto and in law it could not be extended to obligations assumed by another party to sub- contract ft was nut subsumed in sub-contract irrespective of latter providing H for !Is application---Party common to it and sub-contract was not absolved MCDERMOIT INT
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex