MAHANADI COALFIELDS LTD. & ORS. versus M/S. DHANSAR ENGINEERING CO. PVT. LTD. & ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
[2016] 7 S.C.R. 127 MAHANADI COALFIELDS LTD. & ORS. v. MIS. DHANSAR ENGINEERING CO. PVT. LTD. & ANR. (Civil Appeal No. 9732of2016) SEPTEMBER 27, 2016 [T. S. THAKUR, CJI AND A. M. KHANWILKAR, J.] Contract - Work contract - For extraction and transfer of Coal/Coal Measure Strata by deploying surface 111iners - As per the terms and conditions of the tender docu111ent as well as the agreement, the tender quantity could be reduced or increased by 30% on the sa111e ter111s and conditions - Ti111e for co111pletion of contract work was extended at the request of the contractor - During the subsistence of the contract period appellant-company passed order for increase of 30% extra quantity - The contractor requested the company for closure of contract and informed its intention to withdraw fro111 operation after full contract period due to financial hardship - The. company therefore gave lhe re111aining work to a third party at higher rate - Co111pany i111posed penalty on the contractor for non-execution of lhe remaining work - The penalty was inclusive of the financial loss incurred by the company due to allocation of that work at higher rate - Contractor filed writ petition - Petition allowed by High Court - On appeal, held: Clause 5 of the agreement empoil'ered lhe company to increase or reduce the quantify of work by 30%, whilst the contract was subsisting - Therefore, obligation of contractor to complete the extra work in ter111s of the contract within the contract period or extended period was imperative - Contractor co111mitted breach of contractual obligation in not completing the balance work - The contractor is liable to compensate for the financial loss suffered by the company in assigning the remaining work at higher rate - However, liberty is granted to the contractor to make representation to the co111pany requesting to waive the penally in terms of the contract. Partly allowing the appeal, the Court A B c D E F G HELD: 1. Clause 5 of the Contract cannot be read in isolation. The other terms and conditions of the contract must be read as a whole. Clause 5 of the agreement dated 261h May 2003 posits authority in the appellants to reduce or increase the tendered quantity by +/- 30%, whilst the contract is subsisting. H 127 128 A B c D E F G H SUPREME COURT REPORTS [2016) 7 S.C.R. Indisputably, the original contract period was upto IS•h April, 2004. At the instance of the respondents, the same stood extended till ts•h July 2004. The extra 30% work was allotted to the respondents on 11 •h June 2004, before expiry of the extended contract period i.e. 151h July 2004. As the contract period was extended and that decision was allowed to attain finality, it inevitably obliged the respondents to fulfill all the contractual stipulations under the original agreement including to complete the assigned quantity of work - be it original quantity or extra quantity - before tS•h July 2004. The fact that they had to suffer financial loss due to low contract rate could not be cited as an excuse to extricate from that contractual qbligation. [Para 18] J148-F-H; 149-AJ 2. Failure to comply with the contractual obligation of executing the original quantity of work or the extra work, as the case may be, must visit the respondents with liability to compensate the appellants in terms of other express clauses of the contract to the extent of unfinished work and in particular the financial loss suffered by the appellants for getting the same work executed through a third agency at a higher rate. The fact that the respondents executed 108.47% of work before lS'h July 2004, could be no justification to relieve them of their obligation to compensate the appellants with suitable amount for the unfinished contract work (out of 130%). [Para 19) (149-B-C] 3. It is not correct to say that the extra quantity of work could not have been allotted to them, absent 45 clear days notice that too at the fag end of the contract period. It is one thing to say that the contractor should be given suffieient time to complete the extra work commensurate with the extra quantity required to be executed by him. However, in law, it is not open to contend that even though the contract period is still subsisting, the principal (appellants) could not have exercised its option to increase the quantity of work to the extent permissible under that clause, to be executed by the con
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex