M/S. SSPPL AND M/S. AIL WAS versus SALMA DAM JOINT VENTURE & ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 193 WAPCOS LTD. v. SALMA DAM JOINT VENTURE & ANR. (Civil Appeal No. 8595 of 2019) NOVEMBER 14, 2019 [A. M. KHANWILKAR AND DINESH MAHESHWARI, JJ.] Arbitration and Conciliation Act, 1996 – s.11(6) – Appointment of Arbitrators – SDJV, a joint venture of M/s. SSPPL and M/s. AIL was formed – SSPPL was nominated as a ‘Lead Partner’ of SDJV with 95% share as compared to 5% of AIL – SDJV was the successful bidder and that was followed by a Contract Agreement dated 09.03.2006 between the WAPCOSL and SDJV for the implementation of the work on “The Reconstruction, Rehabilitation and completion of Salma Dam Project” in Afghanistan – Several documents were signed including Conditions of Particular Applications (CoPA) – Cl.20.1 thereof dealt with Contractor’s claim and Cl.20.6 dealt with Arbitration – Subsequent to this, the rates of some of the items were revised, which raised the total consideration of the agreement – Thereafter, SDJV and WAPCOSL signed a revised agreement for the rates, referred to as the Amendment of Agreement (AOA) dated 09.06.2015 – Despite signing of AOA, SDJV raised certain claims before the Engineer of WAPCOSL – Subsequent to execution of AOA, dispute arose between the JV partners – On 21.09.2016, AIL revoked Power- of- Attorney executed in favour of SSPPL, which authorized it to appoint arbitrator on behalf of AIL – However, SSPPL filed petition on behalf of SDJV against WAPCOSL u/s. 11(6) of the Act, 1996 – The said petition was allowed by the High Court and the arbitrator was appointed – Aggrieved, WAPCOSL filed special leave petition before the Supreme Court – AIL asserted before the Court that it did not give consent to SSPPL for appointment of arbitrator or to file petition u/s. 11(6) of the Act, 1996 – Consequent to which, the order of the High Court was set aside and parties were relegated before the High Court for reconsideration of all the aspects – The High Court once again allowed the said arbitration petition and appointed a sole arbitrator and held that SSPPL had authority under the JV as well as Contract Agreement [2019] 17 S.C.R. 193 193 A B C D E F G H 194 SUPREME COURT REPORTS [2019] 17 S.C.R. to represent SDJV, as a leading partner to take recourse to arbitration – On appeal, held: The Cls 1.2 and 1.3 of Section-01 of the AOA made it clear that no claims will be raised by the Contractor on any of the pending/settled claims/other claims resulting out of correspondences made and there will be “no arbitration” for the settlement of claims – Neither SDJV nor SSPPL have disputed the execution of AOA – The terms and conditions specified in AOA leave no manner of doubt that the arbitration agreement was done away with – Having chosen to adopt that path, it is not open to the contractor to now take recourse to arbitration process or to resurrect the claim which has been resolved in terms of the amended agreement, after availing of steep revision of rates being condition precedent – Resultantly, the impugned judgment of the High Court set aside. Allowing the appeals, the Court HELD: 1. As regards the first reason weighed with the High Court that the Technical Committee entertained the five appeals filed on behalf of the Salma Dam Joint Venture (SDJV), that in view of this Court cannot undo the effect of terms and conditions of Amendment of Agreement (AoA) which had annulled the arbitration clause in the Contract Agreement. There are at least two other tangible reasons to overturn the stated opinion of the High Court. First, the Technical Committee was, as a matter of fact, constituted under clause 2.1 of Section – 02 of AoA by the CMD of WAPCOSL, as is evident from the communication dated 21.10.2015 sent by WAPCOSL to SDJV. That fact has been restated in the subsequent correspondence. The Technical Committee was, therefore, not constituted in terms of Clause 20.1 of Conditions of Particular Applications (CoPA) as has been erroneously assumed by the High Court. Second, the fact that the Technical Committee processed the appeals instituted by SDJV does not mean that WAPCOSL had waived the terms and conditions of AoA, in particular Clauses 1.2 and 1.3 of Section-01 thereof. No averment is found in the Arbitration Petition to even remotely suggest that it was a case of waiver express or tacit, by WAPCOSL qua the stipulation specified in Clauses 1.2 and 1.3 of Section-01 of AoA. Hence, this reason weighed with the High Court is manifestly wrong and cannot stand the test of judicia
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex