LexaceLexace Ask the AI ›
โš–๏ธ Ask the AI about your situation:๐Ÿš— Car Accident๐Ÿ’ผ Work / Job๐Ÿ  Housing / Eviction๐Ÿ‘ช Family / Divorce๐Ÿ“‹ Contract Dispute๐Ÿ’ฐ Money Owed

M/S. SHYAMA CHARAN AGARWALA AND SONS versus UNION OF INDIA

Citation: [2002] SUPP. 1 S.C.R. 148 · Decided: 15-07-2002 · Supreme Court of India · Bench: D.P. MOHAPATRA · Disposal: Disposed off

cites 1 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

A 
MIS. SHYAMA CHARAN AGARWALA AND SONS 
'v. 
UNION OF INDIA 
JULY 15, 2002 
B 
[D.P. MOHAPATRA AND P. VENKATARAMA REDDI, JJ.] 
ArbitNtitJn Act, 1940-Section 39-Arbitration award-:-Scope of 
interfereยป~ by Court-Parties entering into contract for construction work-
C Disputes referred to arbitrator-Arbitrator accepting the claim and passing 
t~ t:iWord-Award made rule of the court-High Court partly allowing claims-
Justification of. 
Appellant-contractors and respondents entered into contract for 
tertain construction work. Before the work was completed disputes arose 
D between the parties. The disputes were referred for arbitration. Appellant-
contractors claimed reimbursement of additional cost on account Of the 
procurement of stone aggregate from crushers of outside sources in lieu 
of local sources; excavation encountering rock other than soft/disintegrated 
rock/laterite rock and reimbursement of additional costs for working in 
restricted area. Arbitrator accepted the claims and passed an award. Civil 
E Judge made award Rule of the Court. Aggrieved, respondent filed appeals 
under Section 39 of the Arbitration Act, 1940. High Court partly allowed 
the appeals. Hence the present appeals. 
F 
Appellants-contractors contended that High Court exceeded the 
limits of the jurisdiction vested under Section 39 of the Act in deciding 
the appeals filed by respondent and in setting aside the award of the 
arbitrator in respect of claim nos. 2 and 3. It further contended that even 
assuming that the High Court found that the arbitrator had mis-
interpreted the relevant clauses of the agreement, it was not open to it to 
interfere with the award since there was no error of law apparent on the ยท 
G face of the award and the matter relating to interpretation of the 
conditions in the agreement was within the jurisdiction of the arbitrator. 
H 
Respondent contended that the award of the arbitrator relating to 
part of claim nos. 1 and claim nos. 2 and 3, was contrary to the specific 
conditions provided in the agreement, and, therefore, was patently 
148 
( 
, 
SHY AMA CHARAN AGAR WALA v. U.0.1. 
149 
erroneous and uncalled for .. It w~~ also contended that the arbitrator being A 
a creature of the agreemeut cuuld not Ignore the relevant stipulatim1s in 
the contract and travel beyond the terms of the contract. 
Disposing of the appeals, the Court 
HELD: 1.1, High Court did not exceed its jurisdiction in interfering B 
with the award nor failed to exercise the jurisdiction vested in it to set 
aside the award. The approach of the High Court cannot be said to be 
contrary to the well settled prlnclples governing the scope of interference 
with the award of the arbitrator under the old Act. Regarding the question 
whether the contract contemplates the use of stone aggregate and stone C 
metal from the local sources only, the source of supply being silent in the 
relevant clause, the arbitrator can be said to have taken a reasonably 
possible view and, therefore, High Court has rightly declined to set aside 
the award in so far as the quantity of stone aggregate/stone metal brought 
to site up to the date of filing of claim is concerned. (172-D, E; 173-F, G] 
1.2. The award in so far as the future period is concerned, that is 
subsequent to the date of filing of claim statement, High Court set aside 
D 
the award since such a claim did not form part of terms of reference, and 
that the future claim In respect of stone aggregate would be subject to 
various factors including market conditions and whether the shortage E 
continued. It is clear from the arbitration clause that all disputes between 
the parties to the contract (other than excepted matters) can be referred 
to arbitration. The eon tractor did make a claim in respect of future period 
also. The document appointing the arbitrator would show that the 
arbitrator was required to decide the disputes arising between the parties. 
It is not possible to hold that claim No.1 in so far as it relates to future F 
period during which the contract work continued is beyond the scope of 
reference or outside the ambit of arbitration clause. The aim of arbitration 
is to settle all the disputes between the parties and to avoid further 
litigation. There is no legal justification in restricting the scope of 
arbitration in the manner in which the High Court did. The observations G 
of High Court that conditions may not be the same for the future and, 
therefore, the arbitrator was

Excerpt shown. Read the full judgment & AI analysis in Lexace.