M/S. SATHYANARAYAN BROTHERS (P) LTD. versus TAMIL NADU WATER SUPPLY & DRAINAGE BOARD
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
MIS. SA THYANARA YAN BROTHERS (P) LTD. A v. TAMIL NADU WATER SUPPLY & DRAINAGE BOARD NOVEMBER 18, 2003 [BRIJESH KUMAR AND ARUN KUMAR, JJ.] B Arbitration Act, 1940: Work contract for Water Supply Project subject to clearance of foreign collaboration arrangement/release of foreign exchange-Delay in import of C equipments-Non-compliance of the terms of the contract by the Board- Stoppage of work by Contractor-Raising of claims against Board- Arbitration clause-Invoking of-Arbitrator appointed by Contractor awarded the claim partly in· his favour-Arbitrator appointed by the Board did not agree-Appointment of Umpire-Award-Challenge to on ground of D denial of perusal of relevant documents-Single Judge held that non- production of relevant documents by the Board vitiating the award-Reversed by Division Bench of the High Court-On appeal, Held: Perusal of the contents of the relevant documents could not be denied even on ground of confidentiality-Single Judge rightly held that such infirmity vitiated the award-Hence matter remitted to the Division Bench of the High Court for E reconsideration/re-adjudication. Appellant-Contractor and Respondent-Board entered into a contract for manufacture, supply and delivery of pipes and fittings in connection with a Water Supply Project of the Board. The contract was subject to clearance of F the foreign collaboration arrangement and release of necessary foreign exchange by the Board. The Contractor, before accepting the contract, requested the concerned a·uthority for providing necessary assistance in procurement of foreign exchange to import equipments and getting Central Government clearance. G The contract contained an arbitration clause. Due to delay in procurement of imported equipment on account of necessary formalities, completion of the work was delayed. Contractor had requested for extension of time but the Authority did not accede to his request; however, it extended the time later. In the meanwhile, the Contractor raised certain conditions but the same was 733 1-1 734 SUPREME COURT REPORTS (2003] SUPP. 5 S.C.R. A not agreed to by the Board. The contractor stopped the work and invoked arbitration clause of the contract and appointed an arbitrator who awarded the claim partly in his favour. As per arbitration clause, the Board also appointed another arbitrator, who did not agree with the award of first arbitrator. Hence, an Umpire was appointed who gave an award. Contractor B raised objections against the award before the High Court. Single Judge of the High Court found that due to delay in extension of time, the Contractor stopped the work and that by doing so, the Contractor did not commit any breach of the contract; that non-production of relevant documents by the Board for perusal of the Contractor had vitiated the award given by the Umpire. The order was reversed by the Division Bench of the High Court. Hence the C present appeal. It was contended for the appellant-Contractor that as per clause 70 of the agreement, there should have been three arbitrators instead of two and an Umpire; that the authority did not render proper assistance in getting foreign exchange clearance which caused delay in procurement of the D imported equipments; that interrupted electric supply and low voltage affected the progress of the work adversely; that the authority had extended time belatedly in an unreasonable manner; and that non-production of relevant documents by the Board for his perusal vitiated the award. On behalf of the respondent-Board, it was submitted that the Board had E extended all possible assistance to the Contractor; and that the Board was not under any liability to arrange electricity for the contract. Allowing the appeals, the Court HELD: 1.1. Two arbitrators were appointed in accordance with the F provisions of arbitration clause as well as the third arbitrator called Umpire. The mode of hearing was adopted in the manner that the dispute was heard by two arbitrators appointed by the respective parties. The matter was referred to Umpire since there was no agreement between the two arbitrators. There is no justification to raise such an objection that board of three arbitrators G should have decided the matter. Such a plea contradicts appellant's own action, and it seems to be taken now to wriggle out of the award ultimately given by the Umpire, but it would not be permissible at this stage. (740-E-F-Gl Ar
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex