LexaceLexace Ask the AI ›
⚖️ Ask the AI about your situation:🚗 Car Accident💼 Work / Job🏠 Housing / Eviction👪 Family / Divorce📋 Contract Dispute💰 Money Owed

M/S. S.D. SHINDE TR. PARTNER versus GOVT. OF MAHARASHTRA AND ORS

Citation: [2023] 11 S.C.R. 367 · Decided: 22-08-2023 · Supreme Court of India · Bench: S. RAVINDRA BHAT · Disposal: Appeal(s) allowed

cites 2 · see the full citation network in Lexace

Open in Lexace · Ask the AI about this case

Judgment (excerpt)

[2023] 11 S.C.R. 367 : 2023 INSC 751
CASE DETAILS
M/S. S.D. SHINDE TR. PARTNER
v.
GOVT. OF MAHARASHTRA AND ORS.
(Civil Appeal Nos. 6107-6108 of 2017)
AUGUST 22, 2023
[S. RAVINDRA BHAT AND DIPANKAR DATTA, JJ.]
HEADNOTES
Issue for consideration: Award made in favour of the appellant-
contractor was challenged by the respondent-State u/s.30, 33, Arbitration 
Act, 1940 and was set aside by Courts below inter alia holding that the 
claim was time-barred – Legality.
Arbitration Act, 1940 – ss.30 and 33 – Jurisdiction of Courts – 
Scope:
Held: A claim crystallizes upon the issuance of the fi nal bill which 
in this case was on 14.12.1992 – Contractor’s complaint with respect to 
payment was fi rst aired in 1988; the rejection resulted in an appeal before 
the higher authority, who never rendered his opinion or decision – Even 
in 1993, (after the fi nal bill was drawn), no decision was given – Thus, the 
claim before the civil court for the appointment of the arbitrator made in 
January, 1995 was within the period of limitation – Further, on facts, the 
question of claims not being within the contracted period, i.e., within the 
30-day time granted after foreclosure of the contract, does not arise – On 
account of the inordinate delay (in the decision by the authorities, resulting 
in fi ve extensions of time by mutual consent), the contractor voluntarily 
sought foreclosure – That request was acceded to – Originally, the period 
of completion of the contract/works was eighteen months – The request 
for foreclosure, therefore, was deemed reasonable by the department and 
accepted upon receipt of the appellant contractor’s letter dated 06.04.1990 
– Thus, there could have been no objection to delay in submission of the 
claim for dispute resolution or arbitration given the department itself sat over 
the request for settlement of disputes for more than 6 years – The scope of 
367
368
SUPREME COURT REPORTS 
[2023] 11 S.C.R.
jurisdiction of a court, u/ss.30/33 never extended beyond discerning if the 
award disclosed an “error apparent on the face of the award” which is an 
“error of law apparent on the face of the award and not an error of fact – In 
the present case, the award did not facially disclose any error of law; damages 
were awarded in accordance with principles embodied in law, and the 
fi ndings were based on the evidence placed before the tribunal – Impugned 
judgment and the judgment of the trial court set aside – Award restored.
Arbitration – Arbitration award – Interference – Duty of Courts:
Held: While adjudging whether an arbitration award calls for 
interference, Courts have to be conscious that the arbitrator is the sole 
judge of facts; unless an error of law is shown, interference with the 
award should be avoided.
Arbitration – Irregularity alleged making claim untenable:
Held: There is no merit in the respondent-State’s submission that 
the record became defective and procedurally the claim became untenable 
because the tribunal was not informed and the appellant did not bring all 
heirs of the original contractor on the record – This irregularity was cured 
because the trial court’s judgment had arrayed all legal representatives 
of the deceased.
LIST OF CITATIONS AND OTHER REFERENCES
Major (Retd.) Inder Singh Rekhi v Delhi Development Authority [1988] 
3 SCR 351; J.C. Budhraja v. Chairman, Orissa Mining Corporation Ltd. and 
Another (2008) 2 SCC 444 : [2008] 1 SCR 821; Bijendra Nath Srivastava 
v. Mayank Srivastava [1994] Supp 2 SCR 529; Trustees of Port of Madras 
v. Engineering Constructions [1995] Supp 2 SCR 672 – relied on. 
OTHER CASE DETAILS INCLUDING IMPUGNED 
ORDER AND APPEARANCES
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 6107-6108 
of 2017.
From the Judgment and Order dated 13.08.2009 in AFO No. 108 of 
2005 and dated 23.11.2010 in AFO No. 108 of 2005 and LPA No.190 of 
2009 of the High Court of Bombay at Aurangabad.
369
With
Civil Appeal No. 6109 of 2017.
Appearances:
Vinay Navare, Sr. Adv., Shashibhushan P. Adgaonkar, Omkar Jayant 
Deshpande, Mrs. Pradnya S Adgaonkar, JN Singh, Mrs. Sadhana Singh, 
Ms. Shreya Singh, Shashwat Goel, Sachin Pahwa, Arvind S. Avhad, V. K. 
Sidharthan, Rahul Chitnis, Sanjay Kharde, Sunil Kumar Verma, Umang 
Shankar, Shekhar Kumar, Saurabh Mishra, Abhishek Singh, Mrs. Shreya 
Singh, Ms. Priya Kaushik, Advs. for the appearing parties.
JUDGMENT / ORDER OF THE SUPREME COURT
JUDGMENT
S. RAVINDRA BHAT, J.
1. These appeals challenge a common judgment of the Aurangabad 

Excerpt shown. Read the full judgment & AI analysis in Lexace.