M/S PSA MUMBAI INVESTMENTS PTE. LIMITED versus THE BOARD OF TRUSTEES OF THE JAWAHARLAL NEHRU PORT TRUST AND ANR.
Open in Lexace · Ask the AI about this caseJudgment (excerpt)
A B C D E F G H 352 SUPREME COURT REPORTS [2018] 13 S.C.R. M/S PSA MUMBAI INVESTMENTS PTE. LIMITED v. THE BOARD OF TRUSTEES OF THE JAWAHARLAL NEHRU PORT TRUST AND ANR. (Civil Appeal No.9352 of 2018) SEPTEMBER 11, 2018 [R. F. NARIMAN AND INDU MALHOTRA, JJ.] Arbitration and Conciliation Act, 1996 β Arbitration clause β Activation of βRespondent No.1 issued Global invitation of Request for Qualification (RFQ) for development of a container terminal project β The bid was divided into two stages- first, the stage of eligibility and second, the Request for Proposal (RFP) β Appellant and Respondent No.2, as a consortium qualified the first stage β Letter of Award given by the Respondent No.1 to the Consortium β Respondent No.2 opted out of the bid process β Show- cause notice issued by the respondent no.1 to consortium to perform the bid β Since same was not done, the Letter of Award accorded and acknowledged by the appellant was withdrawn by Respondent No.1 β Consequent to this, arbitration notice was sent by the respondent no.1 β Appellant contended that no arbitration clause was entered into by way of agreement between the parties and the arbitration clause relied upon by respondent no.1 would not fit the bill as the disputes that were to be adjudicated under that clause related only to a Concession Agreement which was not entered into β High Court held that there was a concluded contract between the parties as the Letter of Award had been accepted by the appellant and that since the arbitration clause forms a part of the bid document between the parties, the arbitration clause would govern the parties β On appeal, held: On perusal of the RFP clauses, a disclaimer at the forefront of the RFP makes it clear that there was only a bid process that was going on between the parties and there was no concluded contract between them β Such a bid process would subsume a Letter of Award to be issued by the Respondent No.1 with two further steps under the schedule to be gone into before the draft Concession agreement finally becomes an agreement between Respondent No.1 and the Special Purpose Vehicle that was [2018] 13 S.C.R. 352 352 A B C D E F G H 353 constituted by the Consortium β In instant case, there was no absolute and unqualified acceptance by Letter of Award β Some very important steps had to be undergone before there could be an agreement enforceable in law as a contract β Furthermore, even assuming that there was an arbitration clause which governs the parties, the said clause would wholly be inapt as it would only cover the disputes between a Special Purpose Vehicle and the Respondent No.1 arising from the Concession agreement not yet entered into, and not between the Respondent No.1 and the appellant and Respondent No.2 β Thus, impugned judgment of the High Court set aside β Contract Act, 1872 β s.7. Allowing the appeal, the Court HELD: 1. On a conjoint reading of the Request For Proposal (RFP) clauses, a few things become clear - (i) first and foremost a Disclaimer at the forefront of the RFP makes it clear that there is only a bid process that is going on between the parties and that there is no concluded contract between the same (ii) it is equally clear that such bid process would subsume a Letter of Award to be issued by the Respondent No.1 with two further steps under the schedule to be gone into before the draft Concession Agreement finally becomes an agreement between Respondent No.1 and the Special Purpose Vehicle that is constituted by the Consortium for this purpose (iii) that through out the stage of the bid process, the forum for dispute resolution is exclusively with the Courts at Mumbai and (iv) that right uptil the stage of the entering into the Concession Agreement, the bid process may be annulled without giving any reason whatsoever by the Respondent No.1. [Para 13] [372-G-H; 373-A-B] 2. Under Section 7 of the Indian Contract Act, 1872 in order to convert a proposal into a promise, the acceptance must be absolute and unqualified. It is clear on the facts of this case that there is no absolute and unqualified acceptance by the Letter of Award β two or three very important steps have to be undergone before there could be said to be an agreement which would be enforceable in law as a contract between the parties. [Para 15] [373-G-H] M/S PSA MUMBAI INVESTMENTS PTE. LTD v. BOARD OF TRUSTEES OF THE JAWAHARLAL NEHRU PORT TRUST A B C D E F G H 354 SUPREME COURT REPORTS [2018] 13 S.C.R. 3. Appellant corre
Excerpt shown. Read the full judgment & AI analysis in Lexace.
Lex